Findings for the Sacramento Area Voltage Support Project (DOE/EIS-0323S1)
Document Number: E8-9956
Type: Notice
Date: 2008-05-06
Agency: Department of Energy, Western Area Power Administration
Western Area Power Administration (Western) plans to construct a new double-circuit, 230-kilovolt (kV) transmission line, approximately 31 miles long, between Western's O'Banion Substation and the area just south of the Sacramento Municipal Utility District's (SMUD) Elverta Substation and reconstruct SMUD's existing 230 kV/115 kV transmission line between SMUD's Elverta and Natomas substations. The Sacramento Area Voltage Support (SVS) Project (Project) would be located in Sutter, Placer, and Sacramento counties in California. Western proposes to build the Project to provide needed transmission system additions and upgrades to maintain system voltage stability, reliability, and security. Western evaluated seven action alternatives and the No Action Alternative in its supplemental environmental impact statement (SEIS). Of these, Alternative B was selected as both the Preferred Alternative and the Environmentally Preferred Action Alternative.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.