Western Area Power Administration May 2014 – Federal Register Recent Federal Regulation Documents
Results 1 - 3 of 3
Notice of Cancellation of Environmental Impact Statement for the Proposed Hermosa West Wind Energy Project, Albany County, Wyoming
The U.S. Department of Energy (DOE), Western Area Power Administration (Western) is issuing this notice to advise the public that it is cancelling the preparation of an environmental impact statement (EIS) under the National Environmental Policy Act (NEPA) on an interconnection request by Shell WindEnergy, Inc. (SWE).
Loveland Area Projects, Colorado River Storage Project, Pacific Northwest-Pacific Southwest Intertie Project, Central Arizona Project, and Parker-Davis Project-Rate Order No. WAPA-163
The Deputy Secretary of Energy confirmed and approved Rate Order No. WAPA-163 and Rate Schedule WC-8, placing new hourly, non- firm, point-to-point transmission service formula rates for the Loveland Area Projects (LAP), Colorado River Storage Project (CRSP), Pacific Northwest-Pacific Southwest Intertie Project (INT), Central Arizona Project (CAP), and Parker-Davis Project (P-DP) in use under WestConnect's PA into effect on an interim basis.
Falcon and Amistad Projects' Rate Order No. WAPA-164
This action is to extend the existing Falcon and Amistad Projects' Firm Power Rate Formula, established in Rate Order No WAPA- 143, through June 7, 2019. The Falcon and Amistad Projects' Firm Power Rate Formula is set to expire June 7, 2014.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.