Bureau of Land Management May 16, 2008 – Federal Register Recent Federal Regulation Documents

Notice of Intent To Prepare an Environmental Impact Statement, for the Gateway West 230/500 kV Transmission Line Project in Idaho and Wyoming and Possible Land Use Plan Amendments
Document Number: E8-11060
Type: Notice
Date: 2008-05-16
Agency: Department of Agriculture, Forest Service, Department of the Interior, Bureau of Land Management
Pursuant to section 102(2)(C) of the National Environmental Policy Act (NEPA) of 1969 and in response to a Right-of-Way (ROW) application filed by Idaho Power and Rocky Mountain Power, the Bureau of Land Management (BLM), Wyoming State Office, U.S. Forest Service (USFS), Caribou-Targhee and Medicine Bow-Routt National Forests, announces their intention to prepare an EIS and conduct public scoping meetings. Idaho Power and Rocky Mountain Power propose to construct electric transmission lines from the proposed Windstar Substation near the Dave Johnston Power Plant at Glenrock, Wyoming to the proposed Hemingway substation near Melba, Idaho, approximately 20 miles southwest of Boise, Idaho. The project is composed of 11 transmission line segments with a total length of approximately 1,250 miles. Authorization of this proposal may result in the amendment of Forest Service and BLM land use plans (Forest Plans, Management Framework Plans, and Resource Management Plans).
Information Notice of Planning Criteria for the Programmatic Environmental Impact Statement for Leasing of Geothermal Resources
Document Number: E8-11059
Type: Notice
Date: 2008-05-16
Agency: Department of the Interior, Bureau of Land Management, Land Management Bureau
On June 13, 2007, the Department of the Interior, Bureau of Land Management (BLM), and the United States Department of Agriculture, Forest Service (FS), published in the Federal Register [72FR32679] a Notice of Intent (NOI) to prepare a joint Programmatic Environmental Impact Statement (PEIS) to analyze the leasing of BLM- and FS- administered lands with potential for geothermal resources in 11 western states and Alaska. The Federal Land Policy and Management Act (FLPMA) requires the BLM to develop land use plans, also known as Resource Management Plans (RMPs), to guide the BLM's management of the public lands. The BLM's land use planning regulations, which implement FLPMA, require the BLM to publish, and provide for public review of, the proposed planning criteria that will guide the BLM's land use planning process. The purpose of this Information Notice is to identify the RMPs that the BLM may amend and set out the proposed planning criteria that would guide the BLM's planning amendment process. Please note that while the preparation of the PEIS is a joint project with the FS, this Notice applies only to public lands that the BLM manages and does not apply in any way to lands that the FS administers. The FS manages lands that are under its jurisdiction under a separate statutory and regulatory framework.
Alaska Native Claims Selection
Document Number: E8-10990
Type: Notice
Date: 2008-05-16
Agency: Department of the Interior, Bureau of Land Management, Land Management Bureau
As required by 43 CFR 2650.7(d), notice is hereby given that an appealable decision approving lands for conveyance pursuant to the Alaska Native Claims Settlement Act will be issued to Far West Incorporated. The lands are in the vicinity of Chignik, Alaska, and are located in: