A. The Commission may periodically inspect land disturbing activities performed pursuant to the plan required by this regulation. In the event the Commission finds that the measures in the plan are not adequate to control erosion, retain sediment on the site and manage stormwater in a manner that neither any on-site nor off-site damage or problem is caused or increased, it shall require that necessary additional measures be implemented.

B. Upon completion, the Department shall notify the Commission of the completion and acceptance of the project.

C. In the event the Commission finds that a land disturbing activity is not being performed in accordance with the submitted stormwater management and sediment control plan, the Commission may issue a written order either directing conformance with the plan, suspending additional work until conformance is achieved, or directing other measures that it deems necessary to control erosion, retain sediment on the site and manage stormwater in a manner that neither any on-site nor off-site damage or problem is caused or increased.

D. Complaints from any party shall be investigated by the Commission.

Disclaimer: These regulations may not be the most recent version. South Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.