Section 952-001-0040 - Pre-Marking Required by the Excavator; Exemption

Universal Citation: OR Admin Rules 952-001-0040

Current through Register Vol. 64, No. 3, March 1, 2025

(1) Except as provided in paragraph (2) of this rule, prior to notifying the Oregon Utility Notification Center, an excavator shall pre-mark with the color white the immediate area of the proposed excavation within both the public rights-of-way and underground easements.

(2) An excavator need not pre-mark as required in paragraph (1) of this rule if:

(a) The operator can determine precisely the direction, length and location of the proposed excavation by referring to a locate ticket; or

(b) The excavator and operator have had a meeting prior to the beginning of the proposed project, at the construction site for the exchange of information required under paragraph (1) of this rule.

Stat. Auth.: Sec. 1 - 5 & 7, Ch. 691, OL 1995

Stats. Implemented:

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.