Oregon Administrative Rules
Chapter 952 - OREGON UTILITY NOTIFICATION CENTER
Division 1 - Oregon Utility Notification Center
- Section 952-001-0001 - Adoption of Model Rules
- Section 952-001-0003 - Permanent Rulemaking Notice
- Section 952-001-0010 - Definitions
- Section 952-001-0020 - Project Plans to Notify Excavator of Requirements of Law
- Section 952-001-0030 - Permits to Notify Excavator of Requirements of Law
- Section 952-001-0040 - Pre-Marking Required by the Excavator; Exemption
- Section 952-001-0050 - Excavator to Give Notice of Proposed Work; Exemption
- Section 952-001-0060 - When Excavator May Give Less than Two Full Business Day Notice
- Section 952-001-0070 - Operators to Mark Underground Facilities or Notify Excavator that None Exist
- Section 952-001-0080 - Operators to Respond to Notifications Requesting Design Information
- Section 952-001-0090 - Delay of Excavation until Response from Facility Operators; Duty of Excavator to Use Reasonable Care; Damage to Facilities
- Section 952-001-0100 - Record Keeping Requirements
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.