Oklahoma Administrative Code
Title 252 - Department of Environmental Quality
Chapter 633 - Drinking Water State Revolving Fund
Subchapter 3 - General Program Requirements
Section 252:633-3-20 - Project changes

Universal Citation: OK Admin Code 252:633-3-20

Current through Vol. 41, No. 13, March 15, 2024

(a) After an application for financial assistance has been approved by the OWRB and the DEQ has approved the plans and specifications for the project, no change from the approved plans and specifications which would materially or significantly affect total project or cost, estimated revenues, or design shall be made without the prior written approval. Additionally, the amount of the funding provided may only be increased through an amended application for financial assistance.

(b) The recipient must receive approval from the DEQ before implementing changes which:

(1) Alter the project performance standards;

(2) Alter the type of water treatment provided by the project;

(3) Significantly delay or accelerate the project schedule; or,

(4) Substantially alter the design drawings and specifications, or the location, size, capacity, or quality of any major part of the project.

Added at 14 Ok Reg 1139, eff 3-18-97 (emergency); Added at 14 Ok Reg 1690, eff 6-2-97; Amended at 15 Ok Reg 1957, eff 6-1-98; Amended at 25 Ok Reg 1140, eff 7-1-08

Disclaimer: These regulations may not be the most recent version. Oklahoma may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.