Oklahoma Administrative Code
Title 252 - Department of Environmental Quality
Chapter 515 - Management of Solid Waste
Subchapter 41 - Roofing Material Recycling
Section 252:515-41-12 - Operational requirements
Current through Vol. 41, No. 13, March 15, 2024
(a) Acceptable wastes. Only roofing material shall be accepted at a roofing material recycling facility.
(b) Prohibited wastes. Non-Hazardous Industrial Waste, Hazardous Waste, and all other non-roofing material shall be prohibited.
(c) Roofing material. All roofing material recycling facilities shall separate the recyclable material from the material that will not be recycled. The non-recyclable material shall be kept in roll-offs or other containers that will prevent the material from blowing, leaching, or otherwise causing contamination. All non-recyclable material must be properly disposed at an approved disposal facility within thirty(30) days of receipt.
(d) Recyclable material. All roofing material that is intended for recycling must be kept in either containers or piles. Roofing material stored on the ground while awaiting processing shall be placed in piles, as follows:
(e) Fire lane. An unobstructed fire lane at least 50 feet in width shall be maintained around the perimeter of each recyclable material pile.
(f) Buffer zone. A clean buffer zone of at least 50 feet shall be maintained between recyclable material piles and adjacent properties.
(g) Weighing roofing material. Each load of roofing material received shall be weighed on scales tested and certified in accordance with the requirements of the Oklahoma Department of Agriculture, Food and Forestry.
(h) Daily log. A daily log shall be maintained for each load of roofing material received. The daily log shall reflect: