1. The operator shall develop, for the department's approval, a construction quality assurance plan that addresses all aspects of constructing surface facilities. The plan must include the following:

a. A description of the responsibilities and authorities of key personnel, including the level of experience and training;

b. A description of the required level of experience, training, and duties of the contractor, the contractor's employees, and the quality assurance inspectors;

c. A description of the testing protocols for every major phase of construction, including the frequency of inspections, field testing, and sampling for laboratory testing;

d. The sampling and field testing procedures and the equipment to be used;

e. The calibration of field testing equipment;

f. The laboratory procedures to be used; and

g. Documentation to be maintained.

2. The operator shall submit the construction quality assurance plan at the same time the plans and specifications required in section 43-02-02.2-35 are submitted.

General Authority: NDCC 38-12-02

Law Implemented: NDCC 38-12-02

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.