North Dakota Administrative Code
Title 43 - Industrial Commission
Article 43-02 - Mineral Exploration and Development
Chapter 43-02-02.2 - In Situ Leach Mining Rules
Section 43-02-02.2-06 - Review period

Current through Supplement No. 392, April, 2024

1. The department will have one hundred eighty days after the filing date to approve or disapprove the application.

2. The department may extend the review period not to exceed an additional one hundred eighty days if:

a. Additional time is needed to correct application deficiencies.

b. Significant changes are submitted that in the department's judgment require additional time to review. The department may require additional public notification of the amended application.

c. The department requires additional time to conduct an informal conference or a formal hearing or complete the decision.

General Authority: NDCC 38-12-03

Law Implemented: NDCC 38-12-03

Disclaimer: These regulations may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.