Section We 602.33 - Development of Well Yield, Generally

Universal Citation: NH Admin Rules We 602.33

Current through Register No. 40, October 3, 2024

(a) Well yield shall be measured periodically during well construction when there is a readily observable change in yield.

(b) A well shall be flushed or surged to remove debris and by-products of the construction process.

(c) A well constructed in unconsolidated materials shall be surged or pumped to develop yield and remove fine soil particles.

(d) The final yield shall be measured for all new wells, after development, and indicated on the well completion report.

(e) For wells yielding more than 5 gallons per minute (GPM), yield measurement shall be for a minimum of 15 minutes.

(f) For wells yielding 5 gallons per minute or less, yield measurement shall be for a minimum of 30 minutes after dewatering the hole and until the flow has stabilized.

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.