(a) A well casing for a well constructed by excavation shall be made of a material and weight appropriate to assure adequate performance of the functions for which the casing is used.

(b) A well casing for a well constructed by excavation shall:

(1) Provide access for withdrawal of ground water;

(2) Provide a storage area for water prior to withdrawal;

(3) Prevent intrusion of contaminants or soil particles into the well;

(4) Provide a reference for locating the well;

(5) Not be made of or contain materials that are a source of pollution;

(6) Be made of the following materials:
a. Interlocking concrete tile;

b. Steel; or

c. Plastic; and

(7) If made of plastic, be Schedule 40 or better and National Sanitation Foundation approved including but not limited to Polyvinyl chloride (PVC), Chlorinated polyvinyl chloride (CPVC), or Acrylonitrile butadiene styrene (ABS).

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.