(a) Subject to (c), below, no reduction to the setback to an effluent disposal system, as specified in Table 1008-4 in Env-Wq 1008.06(b), shall be permitted except on:
(b) Setback reductions for wells on lots specified in (a), above, shall not be permitted unless:
(c) A water well contractor shall not commence construction of any well with a proposed setback to an effluent disposal area of less than 25 feet except after inspection by the department, in accordance with (d), below, and receipt of written confirmation that no practicable alternative location for the well exists.
(d) An inspection by the department shall be conducted within 7 business days following receipt of a request for inspection. Written requests may be made by electronic mail.