New Hampshire Code of Administrative Rules
We - Water Well Board
Chapter We 600 - STANDARDS FOR THE CONSTRUCTION, MAINTENANCE AND ABANDONMENT OF WELLS
Part We 602 - NEW WELL CONSTRUCTION
Section We 602.13 - Setback Reductions: General Requirements
Current through Register No. 40, October 3, 2024
Where site conditions prevent compliance with We 602.06 through We 602.09, a water well contractor shall:
(a) In consultation with the property owner, identify an alternate well location that maximizes setback distances to the greatest extent possible;
(b) Alert the property owner of the potential for contamination at the proposed alternate location;
(c) Except as specified in We 602.14, below, obtain a written acknowledgement from the property owner, prior to construction of the well, using the setback reduction form obtained from the board, that the property owner understands and accepts the potential consequences of constructing a well in the proposed alternate location; and
(d) Submit a copy of the signed "Setback Reduction Form" to the board together with the "Well Completion Report".
#7307, eff 6-13-00; ss by 7307, eff 6-13-00 ; ss by #9179, eff 6-13-08