Alaska Administrative Code
Title 3 - Commerce, Community, and Economic Development
Part 7 - Regulatory Commission of Alaska
Chapter 52 - Operation of Public Utilities
Article 7 - Criteria for Determination of Power Cost Equalization
3 AAC 52.650 - Processing of power cost equalization requests
Current through February 27, 2024
(a) Within 45 days after a participating electric utility makes a complete request under 3 AAC 52.640 for an adjustment of its power cost equalization per kilowatt-hour, the commission by order will approve the filing, modify and approve it, or suspend it in whole or in part for further action. If the commission enters an order suspending a power cost equalization request only in part, the part that is not suspended takes effect at the end of the 45-day period.
(b) If the commission determines that a request for an adjustment of power cost equalization per kilowatt-hour should be suspended, the commission will, in its discretion, grant interim, refundable power cost equalization per kilowatt-hour.
Authority:AS 42.05.141
AS 42.05.151
AS 42.45.110
AS 42.45.130
AS 42.45.160
AS 42.45.170