Alaska Administrative Code
Title 3 - Commerce, Community, and Economic Development
Part 7 - Regulatory Commission of Alaska
Chapter 52 - Operation of Public Utilities
Article 7 - Criteria for Determination of Power Cost Equalization
3 AAC 52.650 - Processing of power cost equalization requests

Universal Citation: 3 AK Admin Code 52.650

Current through February 27, 2024

(a) Within 45 days after a participating electric utility makes a complete request under 3 AAC 52.640 for an adjustment of its power cost equalization per kilowatt-hour, the commission by order will approve the filing, modify and approve it, or suspend it in whole or in part for further action. If the commission enters an order suspending a power cost equalization request only in part, the part that is not suspended takes effect at the end of the 45-day period.

(b) If the commission determines that a request for an adjustment of power cost equalization per kilowatt-hour should be suspended, the commission will, in its discretion, grant interim, refundable power cost equalization per kilowatt-hour.

Authority:AS 42.05.141

AS 42.05.151

AS 42.45.110

AS 42.45.130

AS 42.45.160

AS 42.45.170

Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.