(a) Within seven calendar days, an electric utility shall file with the commission in writing

(1) notification of a period in which purchases of power from a qualifying facility are curtailed under 3 AAC 50.770(b)(1);

(2) notification of a system emergency in which purchases of power from a qualifying facility are curtailed under 3 AAC 50.770(b)(2);

(3) notification of an agreement in which an electric utility transmits power from a qualifying facility under 3 AAC 50. 770(b)(3);

(4) notification of a request for interconnection with an entity claiming qualifying facility rights under 3 AAC 50.750- 3 AAC 50.820;

(5) notification of denial of interconnection with an entity claiming qualifying facility rights under 3 AAC 50.750- 3 AAC 50.820.

(b) A qualifying facility shall comply with the state commission service requirement of 18 C.F.R. 292.207(c)(1) by concurrently filing with the commission an explanatory cover letter accompanied by a copy of all forms and documents filed with the Federal Energy Regulatory Commission under either 18 C.F.R. 292.207(a) or 18 C.F.R. 292.207(b)(1) and (2).

Authority:AS 42.05.141

AS 42.05.151

Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.