Alaska Administrative Code
Title 3 - Commerce, Community, and Economic Development
Part 7 - Regulatory Commission of Alaska
Chapter 50 - Energy Conservation
Article 2 - Cogeneration and Small Power Production
3 AAC 50.795 - Reporting
Universal Citation: 3 AK Admin Code 50.795
Current through November 28, 2024
(a) Within seven calendar days, an electric utility shall file with the commission in writing
(1) notification of a period in which
purchases of power from a qualifying facility are curtailed under
3
AAC 50.770(b)(1);
(2) notification of a system emergency in
which purchases of power from a qualifying facility are curtailed under
3
AAC 50.770(b)(2);
(3) notification of an agreement in which an
electric utility transmits power from a qualifying facility under 3 AAC 50.
770(b)(3);
(4) notification of a
request for interconnection with an entity claiming qualifying facility rights
under 3 AAC 50.750-
3
AAC 50.820;
(5) notification of denial of interconnection
with an entity claiming qualifying facility rights under
3
AAC 50.750-
3
AAC 50.820.
(b) A qualifying facility shall comply with the state commission service requirement of 18 C.F.R. 292.207(c)(1) by concurrently filing with the commission an explanatory cover letter accompanied by a copy of all forms and documents filed with the Federal Energy Regulatory Commission under either 18 C.F.R. 292.207(a) or 18 C.F.R. 292.207(b)(1) and (2).
Authority:AS 42.05.141
AS 42.05.151
Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.