(a) A person may protest a simplified pipeline tariff under 3 AAC 48.130. Upon the filing of a protest, or upon the commission's own motion, the commission will open a docket and appoint a settlement judge who shall
(b) If a docket is opened under (a) of this section, proposed simplified pipeline tariff rules or rates take effect 121 days after their filing unless suspended or otherwise ordered by the commission.
(c) If the settlement process does not resolve all issues, the commission may suspend the tariff filing and order additional proceedings and filings as required by AS 42.04 and AS 42.06.
(d) The commission will assign an administrative law judge other than the assigned settlement judge to preside over any proceeding required under (c) of this section.
Authority:AS 42.04.070
AS 42.04.080
AS 42.06.055
AS 42.06.140
AS 42.06.350
AS 42.06.400