(a) A pipeline carrier may file a simplified pipeline tariff containing rules complying with 3 AAC 48.462, rates complying with 3 AAC 48.464, or both, for a new pipeline facility, the new portion of an existing pipeline facility, or a pipeline facility or portion of a pipeline facility to be constructed.
(b) A pipeline carrier that has not had permanent tariff rules for an existing pipeline facility may file a simplified pipeline tariff containing rules complying with 3 AAC 48.462.
(c) A pipeline carrier that has not had permanent tariff rates for an existing pipeline facility may file a simplified pipeline tariff containing rates complying with 3 AAC 48.464.
(d) A pipeline carrier that has not had either permanent tariff rules or rates for an existing pipeline facility may file rules complying with 3 AAC 48.462, rates complying with 3 AAC 48.464, or both.
(e) A pipeline carrier may file a simplified pipeline tariff containing rules complying with 3 AAC 48.462, rates complying with 3 AAC 48.464, or both, for an existing pipeline facility not previously regulated under AS 42.05 or AS 42.06.
Authority:AS 42.06.140
AS 42.06.350
AS 42.06.390
AS 42.06.620