Alaska Administrative Code
Title 3 - Commerce, Community, and Economic Development
Part 7 - Regulatory Commission of Alaska
Chapter 46 - Electric Reliability Organizations and Integrated Resource Planning
Article 3 - Electric Reliability Organization Tariffs and Rules
3 AAC 46.450 - Transmission cost recovery
Current through February 27, 2024
(a) Not later than the date specified in the order approving an application to serve as an electric reliability organization, an electric reliability organization's tariff must include methodologies for addressing transmission costs that ensure that the transmission system costs are allocated to those that derive benefits from the system in a manner that is at least roughly commensurate with estimated benefits.
(b) A filing to implement a standard for transmission system cost recovery must demonstrate that the standard
(c) The showing required under (b)(2) of this section must describe in detail the cost allocation principles used to develop the cost allocation recommendations for a transmission project, including an explanation of
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.770