Alaska Administrative Code
Title 3 - Commerce, Community, and Economic Development
Part 7 - Regulatory Commission of Alaska
Chapter 46 - Electric Reliability Organizations and Integrated Resource Planning
Article 1 - Certification and Practice of Electric Reliability Organizations
3 AAC 46.070 - Certification of an electric reliability organization with an independent board or a combination independent and balanced stakeholder board
Current through February 27, 2024
(a) The commission may issue a certificate to an applicant formed with an independent board consistent with AS 42.05.762(4)(B)(i) only after the commission finds that the board is, and has rules to ensure that it is likely to remain, independent. A board is Independent if no board member
(b) The commission may issue a certificate to an applicant formed with a combination independent and balanced stakeholder board consistent with AS 42.05.762(4)(B)(iii) only after the commission finds that the board is a combination of a balanced stakeholder board and independent members.
(c) The commission may waive or modify by order the requirements of this section, in whole or in part, upon application and a showing of good cause or on the commission's own motion, if the waiver does not also require a waiver of the requirements set out in AS 42.05.760 - 42.05.790.
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.760
AS 42.05.762
AS 42.05.770