3 AAC 46.040 - Petition to find an electric reliability organization should be established
Current through February 27, 2024
(a) A petition under AS 42.05.760(f) for an interconnected electric energy transmission network that is not an interconnected bulk-electric system must include
(b) The commission may reject a petition filed under this section if the petition does not comply with the requirements of this chapter and 3 AAC 48.020 - 3 AAC 48.100.
(c) The commission will grant or deny a petition filed under this section based upon a determination of whether granting the petition is in the public interest. The commission will base its determination on
(d) If it grants a petition filed under AS 42.05.762(f), the commission will simultaneously accept the informational application attached to the petition for consideration under 3 AAC 46.060 or 3 AAC 46.070. The commission will docket and consider the application separately under the procedures set out in 3 AAC 48.645.
(e) The commission may waive or modify by order the requirements of this section, in whole or in part, upon application and a showing of good cause or on the commission's own motion, if the waiver does not also require a waiver of the requirements set out in AS 42.05.760(f).
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.760
AS 42.05.770