Nuclear Regulatory Commission June 10, 2021 – Federal Register Recent Federal Regulation Documents
Results 1 - 1 of 1
Exelon Generation Company, LLC; Braidwood Station, Units 1 and 2
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an amendment to Renewed Facility Operating License Nos. NPF-72 and NPF-77, issued to Exelon Generation Company, LLC, for operation of the Braidwood Station, Units 1 and 2. The proposed amendment is contained in the licensee's letter dated May 27, 2021, and would change Technical Specification (TS) Surveillance Requirement (SR) 3.7.9.2 to allow an ultimate heat sink (UHS) temperature of less than or equal to 102.8 degrees Fahrenheit ([deg]F) through September 30, 2021.