Nuclear Regulatory Commission August 24, 2016 – Federal Register Recent Federal Regulation Documents

Pacific Gas and Electric Company; Diablo Canyon Power Plant, Units 1 and 2; Annual Updates to License Renewal Application
Document Number: 2016-20272
Type: Notice
Date: 2016-08-24
Agency: Nuclear Regulatory Commission, Agencies and Commissions
The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to an August 1, 2016, request from Pacific Gas and Electric Company (PG&E), which requested an exemption from the requirement to submit annual updates to its license renewal application (LRA) for Diablo Canyon Power Plant (DCPP), Units 1 and 2. The NRC staff reviewed this request and determined that it is appropriate to grant the exemption while the review of the LRA remains suspended.