Intent To Prepare a Draft Environmental Impact Statement Titled: Alexandria, LA, to the Gulf of Mexico Flood Control Improvements in the Chatlan Lake Canal Basin
Document Number: 05-10544
Type: Notice
Date: 2005-05-26
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The U.S. Army Corps of Engineers, New Orleans District, is initiating this study authorized by a July 23, 1997 resolution of the Committee on Transportation and Infrastructure of the U.S. House of Representatives. The resolution reads: ``Resolved by the Committee on Transportation and Infrastructure of the U.S. House of Representatives, that the Secretary of the Army is required to review the report of the Chief of Engineers on the Mississippi River and Tributaries Project, published as House Document 308, Eighty-eighth Congress, Second Session, and other pertinent reports, to determine whether modifications of the recommendations contained therein are advisable at the present time in the interest of flood control, navigation, wetlands, conservation restoration, wildlife habitat, commercial and recreational fishing, saltwater intrusion, freshwater and sediment diversion, and other purposes in the area drained by the West Atchafalaya Basin Protection Levee, from Alexandria, Louisiana, to the Gulf of Mexico.''
Intent To Prepare a Draft Environmental Impact Statement (DEIS) for the Construction of a Proposed Disposal Site for Dredged material in the Middle Branch of the Patapsco River, at Masonville, Baltimore City/Application for a Corps Section 10/404 Individual Permit
Document Number: 05-10543
Type: Notice
Date: 2005-05-26
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The Baltimore District, U.S. Army Corps of Engineers (Corps) expects receipt of an application in January 2006 from the State of Maryland Department of Transportation, Maryland Port Administration (MPA) for a Section 10/404 individual permit for the construction of a disposal site for dredged material in the Middle Branch of the Patapsco River, at Masonville, Baltimore City, MD. Based on preliminary discussions with the MPA, the Corps has determined that an environmental impact statement (EIS) is required for this proposed project. The applicant's stated purpose of the proposed project is to provide a disposal site to accommodate dredged material generated by dredging projects occurring over the next 5 to 10 years in the Baltimore Harbor area. The EIS will focus on the 5-10 year dredging needs within Baltimore Harbor and upland containment and beneficial use of dredged materials from the Port of Baltimore channel system in the Patapsco River and its tributaries. As part of this study, in accordance with the National Environmental Policy Act (NEPA) of 1969, an EIS will be prepared to document the plan formulation process and recommendations of this study.
Intent To Prepare a Draft Environmental Impact Statement for the Kissimmee Chain of Lakes Portion of the Kissimmee River Restoration Project
Document Number: 05-9996
Type: Notice
Date: 2005-05-19
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The Jacksonville District, U.S. Army Corps of Engineers, intends to prepare a Draft Environmental Impact Statement (DEIS) for the Kissimmee Chain of Lakes (KCOL) portion of the Kissimmee River Restoration (KRR) project. This project involves the establishment of a coordinated schedule of water level drawdowns throughout the seventeen lakes comprising the Kissimmee Chain of Lakes (KCOL), for the ultimate purpose of facilitating environmental restoration throughout those water bodies. The local sponsor is the South Florida Water Management District.
Intent to Prepare a Draft Environmental Impact Statement (DEIS) for the Nourishment of 7.25 Miles of Beach, the Repositioning of the New River Inlet Channel, and the Implementation of an Inlet Management Plan, in North Topsail Beach, Onslow County, NC
Document Number: 05-9995
Type: Notice
Date: 2005-05-19
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The U.S. Army Corps of Engineers (COE), Wilmington District, Wilmington Regulatory Field Office has received a request for Department of the Army authorization, pursuant to Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbor Act, from the Town of North Topsail Beach to nourish approximately 7.25 miles of beachfront to protect residential homes and town infrastructures, and to implement an inlet management plan with the New River Inlet to control the positioning of the inlet channel. The new channel will be centrally located perpendicular to the adjacent shorelines of North Topsail Beach and Onslow Beach. The proposed source of the material for the nourishment will be dredged from offshore borrow area(s) and from the repositioning of the inlet. The placement of beach fill along the Town's shoreline would result in the initial widening of the beach by 50 to 100 feet. The widened beach would be maintained through a program of undefined periodic beach nourishment events with the material extracted primarily from the New River Inlet. The ocean shoreline in the Town of North Topsail Beach encompasses approximately 11.1 miles along the northern end of Topsail Island. Currently, the U.S. Army Corps of Engineers is developing a Federal shoreline protection plan for parts of North Topsail Beach. This Federal plan will only cover 3.85 miles of the southern part of the beach. The remaining 7.25-miles of North Topsail Beach, with the exception of two small areas, is located within the Coastal Barrier Resource System (CBRS), which prohibits the expenditure of Federal funds that would encourage development. Therefore, the Town is pursuing to develop this non-Federal shoreline protection plan that will preserve existing development and infrastructure along the 7.25 miles of shoreline. The channel through New River Inlet has been maintained by the COE for commercial and recreational boating interest for over 55 years. The COE is authorized to maintain the channel in the inlet to a depth of 6 feet mean low water (mlw) over a width of 90 feet.
Intent to Prepare a Draft Supplemental Environmental Impact Statement for Boston Harbor Inner Harbor Maintenance Dredging Project
Document Number: C5-9316
Type: Notice
Date: 2005-05-17
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
Intent To Prepare a Draft Environmental Impact Statement in Conjunction With Proposed Sediment Management and Restoration Measures on the Grand Calumet River and non-Federal Portions of the Indiana Harbor Canal in Lake County, IN
Document Number: 05-9584
Type: Notice
Date: 2005-05-13
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The study involves sediment management and restoration measures on the Grand Calumet River and non-Federal portions of the Indiana Harbor Canal. Potential alternatives to be evaluated are type and extent of dredging, possibility of capping areas, disposal options and restoration measures. The Draft Environmental Impact Statement (DEIS) is expected to be released for public review in June 2006. As part of the scoping process, written comments will be accepted for a 60-day period, starting from the date of this notice. Comments should be submitted to Mr. Keith Ryder (see ADDRESSES).
Availability of Draft Integrated Feasibility Report & Environmental Impact Statement for the Flood Damage Reduction Project, Bloomsburg, PA
Document Number: 05-9583
Type: Notice
Date: 2005-05-13
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
In accordance with the requirements of the National Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers (USACE), Baltimore District has prepared a Draft Integrated Feasibility Report & Environmental Impact Statement (EIS) for the flood damage reduction project for the Town of Bloomsburg, in Columbia County, PA. The integrated report investigates the potential environmental effects of an array of alternative plans based on reducing flood damages in Bloomsburg. The preferred alternative includes 16,555 linear feet of levee/floodwall systems with fourteen drainage structures, and nine closure structures, six of which incorporate limited road raisings. We are making the integrated report and EIS available to the public for a 45-day review and comment period.
Coastal Engineering Research Board (CERB)
Document Number: 05-9581
Type: Notice
Date: 2005-05-13
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
In accordance with Section 10(a)(2) of the Federal Advisory Committee Act (Pub. L. 92-463), announcement is made of the following committee meeting: Name of Committee: Coastal Engineering Research Board (CERB). Date of Meeting: June 7-9, 2005. Place: William A. Egan Civic and Convention Center, 555 West 5th Avenue, Anchorage, AK 99501. Times:
Intent to Prepare a Draft Supplemental Environmental Impact Statement for the Boston Harbor Inner Harbor Maintenance Dredging Project
Document Number: 05-9316
Type: Notice
Date: 2005-05-10
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The U.S. Army Corps of Engineers, New England District is preparing a Supplemental Environmental Impact Statement (SEIS) to maintenance dredge the federal navigation channels landward of Spectacle Island in Boston Harbor, MA. Maintenance dredging of the navigation channels landward of Spectacle Island is needed to remove shoals and restore the navigation channels to their authorized depths. Ships are currently experiencing tidal delays and potential damage from grounding. Material dredged from the federal channels will either be disposed at the Massachusetts Bay Disposal Site (if the material is suitable for ocean disposal) or, if the material is not suitable for ocean disposal, in confined aquatic disposal (CAD) cell(s). Major navigation channel improvements (depending) were made in 1999 through 2001 in the Reserved Channel, the Mystic River, Inner Confluence and the Chelsa River. A final EIS was prepared for this previous navigation improvement project in June of 1995 in which the use of CAD cells in the Mystic River, Inner Confluence, and Chelsea River were investigated. CAD cells not used during the construction of the previous navigation improvement project will be investigated for acceptability during the preparation of this SEIS.
Notice of Intent To Prepare a Joint Environmental Impact Statement and Environmental Impact Report for Lower American River Common Features Project, Mayhew Levee Raise
Document Number: 05-8666
Type: Notice
Date: 2005-05-02
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The action being taken is an Environmental Impact Statement/ Environmental Impact Report (EIS/EIR) to address potential improvements to the existing flood management systems along the American River. This portion of the Lower American River Common Features project is located in Sacramento County. The Corps of Engineers is in the process of completing slurry wall work on approximately 26 miles of levee along the American River. In 1996, Congress authorized the raising of levees along the American River in the Mayhew Drain area under the American River Common Features project. Subsequently, section 366 of the Water Resources Development Act of 1999 authorized the raising of the left bank of the non-Federal levee upstream of the Mayhew Drain for a distance of 4,300 feet and the installation of gates to the existing Mayhew Drain culvert.