Western Area Power Administration January 21, 2020 – Federal Register Recent Federal Regulation Documents
Results 1 - 1 of 1
Proposed Salt Lake City Area Integrated Projects Firm Power Rate and Colorado River Storage Project Transmission and Ancillary Services Rates-Rate Order No. WAPA-190
Western Area Power Administration (WAPA) proposes a new Salt Lake City Area Integrated Projects (SLCA/IP) firm power rate and revised Colorado River Storage Project (CRSP) transmission and ancillary services formula rates. The existing rates for these services expire on September 30, 2020. Currently, there is a 4.25 percent projected decrease to the firm power composite rate. WAPA also proposes modifications to the Cost Recovery Charge (CRC) formula. WAPA proposes changes to the annual transmission revenue requirement. WAPA also proposes to add generator imbalance service to the energy imbalance rate schedule and implement a new rate schedule for the sale of surplus products.