Pick-Sloan Missouri Basin Program-Eastern Division-Rate Order Nos. WAPA-144 and WAPA-148
The Deputy Secretary of Energy confirmed and approved Rate Order Nos. WAPA-144 and WAPA-148 and Rate Schedules UGP-NT1, UGP-FPT1, UGP-NFPT1, UGP-AS1, UGP-AS2, UGP-AS3, UGP-AS4, UGP-AS5, UGP-AS6, UGP- AS7 and UGP-TSP1 on an interim basis. The provisional rates will be in effect until the Federal Energy Regulatory Commission (FERC) confirms, approves, and places them into effect on a final basis or until they are superseded. The provisional rates will provide sufficient revenue to pay all annual costs, including interest expenses, and repay required investments within the allowable periods.