Western Area Power Administration June 2009 – Federal Register Recent Federal Regulation Documents
Results 1 - 6 of 6
Big Stone II Power Plant and Transmission Project Final Environmental Impact Statement (DOE/EIS-0377)
The Western Area Power Administration (Western) announces the availability of the Big Stone II Power Plant and Transmission Project (Project) Final Environmental Impact Statement (EIS). This Final EIS analyzes the environmental impacts of constructing and operating the proposed Project. Western is considering whether to grant a request to interconnect the proposed Project with Western's transmission system at Morris and Granite Falls substations in Minnesota, an action which requires Western to complete modifications to these substations to support the interconnection.\1\ The U.S. Army Corps of Engineers (USACE) participated as a cooperating agency in the EIS process. USACE is considering whether to issue a permit for Section 10 of the Rivers and Harbors Act and for Section 404 of the Clean Water Act for construction of the proposed Project within or across navigable waters and waters of the United States.
Construction, Operation, and Maintenance of the Proposed Transmission Agency of Northern California Transmission Project, California
On February 23, 2009, Western Area Power Administration (Western), an agency of the Department of Energy (DOE), announced the Notice of Intent to prepare an Environmental Impact Statement/ Environmental Impact Report (EIS/EIR) for the construction, operation, and maintenance of the proposed Transmission Agency of Northern California (TANC) Transmission Project. In that notice, Western described the schedule for scoping meetings and advised the public that comments on the scope of the EIS/EIR were due by April 30, 2009. On May 8, 2009, Western published a notice in the Federal Register extending the comment period to May 31, 2009. By this notice, Western extends the due date for comments on the scope of the EIS/EIR to July 30, 2009.
Pick-Sloan Missouri Basin Program-Eastern Division-Rate Order No. WAPA-148
The Western Area Power Administration (Western) proposes to add a penalty rate for Unreserved Use of Transmission Service for the Pick-Sloan Missouri Basin ProgramEastern Division (P-SMBPED) in a new rate schedule, Rate Schedule UGP-TSP1. The new rate schedule for Unreserved Use of Transmission System Penalties, Rate Schedule UGP- TSP1, is proposed to go into effect on the later of January 1, 2010, or when Western's Open Access Transmission Tariff (OATT) is revised to provide for Unreserved Use Penalties. Prior to implementing the penalty rate, Western will post notice on its Open Access Same-Time Information System (OASIS) Web site. If Rate Schedule UGP-TSP1 is implemented, it will remain in effect through December 31, 2014, or until superseded. Western will prepare a brochure that provides detailed information on the proposed rate to all interested parties. Publication of this Federal Register notice begins the formal process for the proposed penalty rate.
Amistad and Falcon Projects Rate Order No. WAPA-143
The Deputy Secretary of Energy confirmed and approved Rate Order No. WAPA-143 placing a power rate formula for the Amistad and Falcon Projects of the Western Area Power Administration (Western) into effect on an interim basis. The provisional power rate formula will be in effect on an interim basis until the Federal Energy Regulatory Commission (FERC) confirms, approves, and places it into effect on a final basis, or until the power rate formula is replaced by another power rate formula.
Pick-Sloan Missouri Basin Program-Eastern Division-Rate Order No. WAPA-144
The Western Area Power Administration (Western) is proposing to update its rates for transmission and ancillary services for the Pick-Sloan Missouri Basin ProgramEastern Division (P-SMBPED). Current formula rates, under Rate Schedules UGP-NT1, UGP-FPT1, UGP- NFPT1, UGP-AS1, UGP-AS2, UGP-AS3, UGP-AS4, UGP-AS5, and UGP-AS6 will expire on September 30, 2010. Western is also proposing to add a new rate schedule, Rate Schedule UGP-AS7, for Generator Imbalance Service. Western is proposing these rates to meet evolving and expanding transmission system and ancillary services requirements. Western will prepare a brochure that provides detailed information on the proposed rates to all interested parties. The proposed rates, under Rate Schedules UGP-NT1, UGP-FPT1, UGP-NFPT1, UGP-AS1, UGP-AS2, UGP-AS3, UGP- AS4, UGP-AS5, and UGP-AS6, are scheduled to go into effect on January 1, 2010, and will remain in effect through December 31, 2014, or until superseded. The new rate schedule for Generator Imbalance Service, under Rate Schedule UGP-AS7, is scheduled to go into effect on the latter of January 1, 2010, or when Western's Open Access Transmission Tariff (OATT) is revised to provide for Generator Imbalance Service. If implemented, Rate Schedule UGP-AS7 will also remain in effect through December 31, 2014, or until superseded, to coincide with the other ancillary service rates in this rate order. Publication of this Federal Register notice begins the formal process for the proposed formula rates.
Call for 2015 Resource Pool Applications
The Western Area Power Administration (Western), a Federal power marketing administration of DOE, published its 2004 Power Marketing Plan (Marketing Plan) for the Sierra Nevada Customer Service Region (SNR) in the Federal Register on June 25, 1999, at 64 FR 34417. The Marketing Plan specifies the terms and conditions under which Western will market power from the Central Valley Project (CVP) and the Washoe Project beginning January 1, 2005, and continuing through December 31, 2024. With this Federal Register notice, Western is issuing a call for applications for SNR's 2015 Resource Pool.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.