Department of Energy November 22, 2016 – Federal Register Recent Federal Regulation Documents
Results 1 - 6 of 6
Record of Decision for Issuing a Presidential Permit to Minnesota Power
The U.S. Department of Energy (DOE) announces its decision to issue a Presidential permit to Minnesota Power, a regulated utility division of ALLETE, Inc. (Applicant), to construct, operate, maintain, and connect a new electric transmission line across the U.S./Canada border in northern Minnesota. The potential environmental impacts associated with the transmission line are analyzed in the Great Northern Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0499). The transmission line would cross the U.S./Canada border in Roseau County, Minnesota and extend southeast approximately 220 miles to the proposed Iron Range 500-kilovolt (kV) Substation, located just east of the existing Blackberry Substation near Grand Rapids, Minnesota.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.