Department of Energy November 30, 2010 – Federal Register Recent Federal Regulation Documents
Results 1 - 16 of 16
Biomass Research and Development Technical Advisory Committee
This notice announces an open meeting of the Biomass Research and Development Technical Advisory Committee under Section 9008(d) of the Food, Conservation, and Energy Act of 2008. The Federal Advisory Committee Act requires that agencies publish these notices in the Federal Register to allow for public participation. This notice announces the meeting of the Biomass Research and Development Technical Advisory Committee.
Intent To Prepare an Environmental Impact Statement and To Conduct Scoping Meetings: Interconnection of the Proposed Hyde County Wind Energy Center Project, South Dakota
NextEra Energy Resources (NextEra) applied to interconnect its proposed 150-megawatt (MW) Hyde County Wind Energy Center Project (Project), located in Hyde County, South Dakota, with the Western Area Power Administration's (Western) existing Fort Thompson Substation in Buffalo County, South Dakota. Western will prepare an environmental impact statement (EIS) on the proposal to interconnect the Project in accordance with the National Environmental Policy Act of 1969 (NEPA), U.S. Department of Energy (DOE) NEPA Implementing Procedures, and the Council on Environmental Quality (CEQ) regulations for implementing NEPA. Western's need for agency action is precipitated by NextEra's application to interconnect with Western's power transmission system. Western needs to consider NextEra's interconnection request under its Open Access Transmission Service Tariff (Tariff). This EIS will address Western's Federal action of interconnecting the proposed Project to Western's transmission system, making changes within Western's existing Fort Thompson Substation to physically connect NextEra's proposed Project, and making any necessary system modifications to accommodate the interconnection. Existing transmission line approaches to Fort Thompson Substation may also need to be realigned. By taking these actions, power generated by NextEra's proposed Project would use Western's transmission system to reach the market. Portions of NextEra's proposed Project may affect floodplains and wetlands, so this Notice of Intent (NOI) also serves as a notice of proposed floodplain or wetland action in accordance with DOE floodplain and wetland environmental review requirements.
Intent To Prepare an Environmental Impact Statement and To Conduct Scoping Meetings: Interconnection of the Proposed Crowned Ridge Wind Energy Center Project, South Dakota
NextEra Energy Resources (NextEra) applied to interconnect its proposed 150-megawatt (MW) Crowned Ridge Wind Energy Center Project (Project) with the Western Area Power Administration's (Western) existing Watertown Substation in Codington County, South Dakota. The proposed Project would be located in Codington and Grant counties, South Dakota. Western will prepare an environmental impact statement (EIS) on the proposal to interconnect the Project in accordance with the National Environmental Policy Act of 1969 (NEPA), U.S. Department of Energy (DOE) NEPA Implementing Procedures, and the Council on Environmental Quality (CEQ) regulations for implementing NEPA. Western's need for agency action is precipitated by NextEra's application to interconnect with Western's power transmission system. Western needs to consider NextEra's interconnection request under its Open Access Transmission Service Tariff (Tariff). This EIS will address Western's Federal action of interconnecting the proposed Project to Western's transmission system, making changes within Western's existing Watertown Substation to physically connect NextEra's proposed Project, and making any necessary system modifications to accommodate the interconnection. By taking these actions, power generated by NextEra's proposed Project would use Western's transmission system to reach the market. Portions of NextEra's proposed Project may affect floodplains and wetlands, so this Notice of Intent (NOI) also serves as a notice of proposed floodplain or wetland action in accordance with DOE floodplain and wetland environmental review requirements.
Worker Safety and Health Program: Safety Conscious Work Environment
The Department of Energy received a petition from the Hanford Challenge on August 18, 2009, requesting the initiation of a rulemaking regarding safety policies at DOE's nuclear facilities. The petition calls for DOE to establish by regulation a safety program using the Nuclear Regulatory Commission's ``Safety-Conscious Work Environment'' guidelines as a model. DOE published this petition and a request for comment on October 16, 2009. DOE denies the petition for rulemaking.