Petitions for Modification of Application of Existing Mandatory Safety Standards, 34701-34706 [2017-15674]
Download as PDF
mstockstill on DSK30JT082PROD with NOTICES
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
to re-energizing and testing the
machine. Once circuits have been tested
and no adverse conditions are present,
the boom raising/lowering procedure as
outlined above will be resumed.
(j) During this construction/
maintenance procedure, persons cannot
get on/off the dragline while the ground
fault ground check circuits are disabled
unless the circuit to the dragline is deenergized, locked and tagged out as
verified by the MSHA-qualified
electrician at the substation.
(k) After the boom raising/lowering is
completed, the MSHA-qualified
electrician at the substation will restore
all the protective devices to their normal
state. When this has been completed,
the MSHA-qualified electrician at the
substation will notify the MSHAqualified electrician at the dragline that
all circuits are in their normal state. At
this time, normal work procedures can
begin.
The petitioner asserts that the
proposed alternative method will
always guarantee the miners affected no
less than the same measure of protection
afforded by the existing standard.
Docket Number: M–2017–002–M.
Petitioner: Martin Marietta Materials,
Midwest Division, 11252 Aurora
Avenue, Des Moines, Iowa 50322.
Mine: Fort Calhoun Underground
Mine, 5765 County Road P 30, Fort
Calhoun, Nebraska 68023, MSHA I.D
No. 25–01300, located in Washington
County, Nebraska.
Regulation Affected: 30 CFR
57.11052(d) (Refuge areas).
Modification Request: The petitioner
requests a modification of the existing
standard to permit an alternative
method of compliance to permit use of
bottled water in refuge areas in lieu of
waterlines. The petitioner states that:
(1) The Fort Calhoun Underground
Mine will soon be developing two
parallel decline tunnels to access an
identified limestone reserve near Fort
Calhoun, Nebraska. The decline tunnels
will each be approximately 3,200 feet in
length. The tunnels will be spaced
roughly 155 feet horizontally between
tunnel center lines. Two cross passages
are planned to connect the two parallel
tunnels during development. The Fort
Calhoun Underground Mine will
provide a portable prefabricated refuge
chamber in each of the two decline
tunnels for the purpose of barricading in
the event of a mine emergency.
(2) The petitioner seeks modification
of 30 CFR 57.11052(d) specifically with
the standard’s directive that refuge areas
be provided with waterlines. The Fort
Calhoun Underground Mine will
provide waterlines to each of the two
aforementioned refuge chambers;
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
however, the installed waterlines will
not support a potable water supply.
(3) In lieu of a plumbed potable water
supply, potable water will be provided
in each of the two refuge chambers in
the form of commercially purchased
bottled water in sealed bottles.
(4) The two planned portable refuge
chambers to be used underground at the
Fort Calhoun Underground Mine are
each designed to sustain 20 miners for
a period of 36 hours under battery
backup power. These prefabricated
refuge chambers will, at all times, be
equipped with waterlines being directly
fed from the surface. The waterline
supplied to the refuge chamber will not
be a source of potable water for miners
taking refuge. The reliability of source
water quality and volume being fed to
the chambers is jeopardized considering
water transmission line will be installed
in a mining environment and inherently
susceptible to mechanical damage or
restriction in the event of a mine
emergency. Sourcing of water from a
surface reservoir to the refuge chambers
is affected by climate conditions on the
surface. Adversely cold surface
temperatures could restrict or cut off the
supply of water to the refuge chambers
resulting in a diminution of safety. Addin contaminants (industrial or bacteria)
in piped-in water results in a
diminution of safety for the miners.
(5) Potable water will be provided in
each of the chambers in the form of
commercially purchased bottled water
in sealed bottles. Each of the two
chambers will be provided with a
minimum of 2.25 quarts of potable
drinking water per person, per day.
Considering that each of the chambers
are designed to support 20 miners for a
period of 36 hours, each chamber will
be outfitted with a minimum of 67.5
quarts or 2160 ounces of commercially
purchased potable drinking water in
sealed bottles. Provisioned water will
have a maximum shelf life of 2 years.
The condition and quantity of stored
water will be confirmed by monthly
inspections. Written instructions for
conservation of water will also be
provided within the refuge chambers for
reference.
The petitioner asserts that the
proposed alternative method will at all
times guarantee no less than the same
measure of protection afforded by the
existing standard.
Sheila McConnell,
Director, Office of Standards, Regulations,
and Variances.
[FR Doc. 2017–15673 Filed 7–25–17; 8:45 am]
BILLING CODE 4520–43–P
PO 00000
Frm 00079
Fmt 4703
Sfmt 4703
34701
DEPARTMENT OF LABOR
Mine Safety and Health Administration
Petitions for Modification of
Application of Existing Mandatory
Safety Standards
Mine Safety and Health
Administration, Labor.
ACTION: Notice.
AGENCY:
This notice is a summary of
petitions for modification submitted to
the Mine Safety and Health
Administration (MSHA) by the parties
listed below.
DATES: All comments on the petitions
must be received by MSHA’s Office of
Standards, Regulations, and Variances
on or before August 25, 2017.
ADDRESSES: You may submit your
comments, identified by ‘‘docket
number’’ on the subject line, by any of
the following methods:
1. Electronic Mail: zzMSHAcomments@dol.gov. Include the docket
number of the petition in the subject
line of the message.
2. Facsimile: 202–693–9441.
3. Regular Mail or Hand Delivery:
MSHA, Office of Standards,
Regulations, and Variances, 201 12th
Street South, Suite 4E401, Arlington,
Virginia 22202–5452, Attention: Sheila
McConnell, Director, Office of
Standards, Regulations, and Variances.
Persons delivering documents are
required to check in at the receptionist’s
desk in Suite 4E401. Individuals may
inspect copies of the petitions and
comments during normal business
hours at the address listed above.
MSHA will consider only comments
postmarked by the U.S. Postal Service or
proof of delivery from another delivery
service such as UPS or Federal Express
on or before the deadline for comments.
FOR FURTHER INFORMATION CONTACT:
Barbara Barron, Office of Standards,
Regulations, and Variances at 202–693–
9447 (Voice), barron.barbara@dol.gov
(Email), or 202–693–9441 (Facsimile).
[These are not toll-free numbers.]
SUPPLEMENTARY INFORMATION: Section
101(c) of the Federal Mine Safety and
Health Act of 1977 and Title 30 of the
Code of Federal Regulations part 44
govern the application, processing, and
disposition of petitions for modification.
SUMMARY:
I. Background
Section 101(c) of the Federal Mine
Safety and Health Act of 1977 (Mine
Act) allows the mine operator or
representative of miners to file a
petition to modify the application of any
mandatory safety standard to a coal or
E:\FR\FM\26JYN1.SGM
26JYN1
34702
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
mstockstill on DSK30JT082PROD with NOTICES
other mine if the Secretary of Labor
(Secretary) determines that:
1. An alternative method of achieving
the result of such standard exists which
will at all times guarantee no less than
the same measure of protection afforded
the miners of such mine by such
standard; or
2. That the application of such
standard to such mine will result in a
diminution of safety to the miners in
such mine.
In addition, the regulations at 30 CFR
44.10 and 44.11 establish the
requirements and procedures for filing
petitions for modification.
II. Petitions for Modification
Docket Number: M–2017–010–C.
Petitioner: Peabody Gateway North
Mining, LLC, 12968 Illinois State Route
13, Coulterville, IL 62237.
Mine: Gateway North Mine, MSHA
I.D. No. 11–03235, located in Randolph
County, Illinois.
Regulation Affected: 30 CFR 75.500(d)
(Permissible electric equipment).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the use of
nonpermissible electronic testing
equipment in the last open crosscut.
The petitioner states that:
(1) Nonpermissible electronic testing
and diagnostic equipment to be used
includes: Laptop computers,
oscilloscopes, vibration analysis
machines, cable fault detectors, point
temperature probes, infrared
temperature devices, insulation testers
(meggers), voltage, current resistance,
power testers, and electronic
tachometers. Other testing and
diagnostic equipment may be used if
approved in advance by the MSHA
District Manager.
(2) All nonpermissible testing and
diagnostic equipment used in or inby
the last open crosscut will be examined
by a qualified person as defined in 30
CFR 75.153, prior to use to ensure the
equipment is being maintained in a safe
operating condition. These examination
results will be recorded in the weekly
examination book and will be made
available to MSHA and the miners at the
mine.
(3) A qualified person as defined in 30
CFR 75.151 will continuously monitor
for methane immediately before and
during the use of nonpermissible
electronic testing and diagnostic
equipment in or inby the last open
crosscut.
(4) Nonpermissible electronic testing
and diagnostic equipment will not be
used if methane is detected in
concentrations at or above one percent.
When one percent or more methane is
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
detected while the nonpermissible
electronic equipment is being used, the
equipment will be de-energized
immediately and will be withdrawn
outby the last open crosscut.
(5) All hand-held methane detectors
will be MSHA-approved and
maintained in permissible and proper
operating condition as defined in 30
CFR 75.320.
(6) Except for time necessary to
troubleshoot under actual mining
conditions coal production in the
section will cease. However, coal may
remain in or on the equipment to test
and diagnose the equipment under
‘‘load’’.
(7) All electronic testing and
diagnostic equipment will be used in
accordance with the safe use procedures
recommended by the manufacturer.
(8) Qualified personnel who use
electronic testing and diagnostic
equipment will be properly trained to
recognize the hazards and limitations
associated with use of the equipment.
The petitioner asserts that the
proposed alternative method will at all
times guarantee no less than the same
measure of protection afforded by the
standard.
Docket Number: M–2017–011–C.
Petitioner: Peabody Gateway North
Mining, LLC, 12968 Illinois State Route
13, Coulterville, IL 62237.
Mine: Gateway North Mine, MSHA
I.D. No. 11–03235, located in Randolph
County, Illinois.
Regulation Affected: 30 CFR 75.507–
1(a) (Electric equipment other than
power-connection points; outby the last
open crosscut; return air; permissibility
requirements).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the use of
nonpermissible electronic testing
equipment in return air outby the last
open crosscut. The petitioner states that:
(1) Nonpermissible electronic testing
and diagnostic equipment to be used
includes: Laptop computers,
oscilloscopes, vibration analysis
machines, cable fault detectors, point
temperature probes, infrared
temperature devices, insulation testers
(meggers), voltage, current resistance,
power testers, and electronic
tachometers. Other testing and
diagnostic equipment may be used if
approved in advance by the MSHA
District Manager.
(2) All nonpermissible testing and
diagnostic equipment used in return air
outby the last open crosscut will be
examined by a qualified person as
defined in 30 CFR 75.153, prior to use
to ensure the equipment is being
PO 00000
Frm 00080
Fmt 4703
Sfmt 4703
maintained in a safe operating
condition. These examination results
will be recorded in the weekly
examination book and will be made
available to MSHA and the miners at the
mine.
(3) A qualified person as defined in 30
CFR 75.151 will continuously monitor
for methane immediately before and
during the use of nonpermissible
electronic testing and diagnostic
equipment in return air outby the last
open crosscut.
(4) Nonpermissible electronic testing
and diagnostic equipment will not be
used if methane is detected in
concentrations at or above one percent.
When one percent or more methane is
detected while the nonpermissible
electronic equipment is being used, the
equipment will be de-energized
immediately and will be withdrawn
from the return air outby the last open
crosscut.
(5) All hand-held methane detectors
will be MSHA approved and maintained
in permissible and proper operating
condition as defined in 30 CFR 75.320.
(7) All electronic testing and
diagnostic equipment will be used in
accordance with the safe use procedures
recommended by the manufacturer.
(8) Qualified personnel who use
electronic testing and diagnostic
equipment will be properly trained to
recognize the hazards and limitations
associated with use of the equipment.
The petitioner asserts that the
proposed alternative method will at all
times guarantee no less than the same
measure of protection afforded by the
standard.
Docket Number: M–2017–012–C.
Petitioner: The Marion County Coal
Company, 151 Johnny Cake Road, Metz,
West Virginia 26585.
Mine: Marion County Mine, MSHA
I.D. No. 46–01433, located in Marion
County, West Virginia.
Regulation Affected: 30 CFR 75.1700
(Oil and gas wells).
Modification Request: The petitioner
requests a modification of that part of
the existing standard that requires the
operator to establish and maintain
barriers around its surface directional
drilled (SDD) wells. The petitioner
asserts that the proposed alternative
method has been successfully used to
prepare coal bed methane (CBM) wells
for safe intersection by using one or
more of the following methods: (1)
Cement Plug, (2) Polymer Gel, (3)
Bentonite Gel, (4) Active Pressure
Management and Water Infusion, and
(5) Remedial Work. The proposed
alternative method will prevent the
CBM well methane from entering the
E:\FR\FM\26JYN1.SGM
26JYN1
mstockstill on DSK30JT082PROD with NOTICES
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
underground mine. The alternative
method includes well plugging
procedures, water infusion and
ventilation method, and procedures for
mining through a CBM well with
horizontal laterals. The petitioner states
that:
(1) A minimum working barrier of 300
feet in diameter will be maintained
around all SDD wells until approval to
proceed with mining has been obtained
from the District Manager (DM). The
barrier would extend around all vertical
and horizontal branches drilled in the
coal seam. The barrier would also
extend around all vertical and
horizontal branches within overlying
coal seams subject to caving or
subsidence from the coal seam being
mined when methane leakage through
the subsidence zone is possible.
(2) The DM may choose to approve
each branch intersection, each well, or
a group of wells as applicable to the
conditions. The DM may require a
certified review of the proposed
methods to prepare the SDD wells for
intersection by a professional engineer
in order to assess the applicability of the
proposed system(s) to the mine-specific
conditions.
a. The petitioner proposes to use the
following procedures for preparing,
plugging, and replugging SDD wells
using mandatory computations and
administrative procedures prior to
plugging or replugging:
(1) Probable Error of Location—
Directional drilling systems rely on
sophisticated angular measurement
systems and computer models to
calculate the estimated location of the
well bore. This estimated hole location
is subject to cumulative measurement
errors so that the distance between
actual and estimated location of the well
bore increases with the depth of the
hole. Modern directional drilling
systems are typically accurate within
one or two degrees depending on the
specific equipment and techniques. The
probable error of location is defined by
a cone described by the average
accuracy of angular measurement
around the length of the hole. For
example, a hole that is drilled 500
vertical feet and deviated into a coal
seam at a depth of 700 feet would have
a probable error of location at a point
that is 4,000 feet from the hole collar
(about 2,986 feet horizontally from the
well collar) of 69.8 feet (4,000 feet × sine
(1.0 degree)) if the average accuracy of
angular measurement was on degree and
139.6 feet if the average accuracy of
angular measurement was two degrees.
In addition to the probable error of
location, the true hole location is also
affected by underground survey errors,
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
surface survey errors, and random
survey errors.
(2) Minimum Working Barrier Around
Well—For purposes of this petition, the
minimum working barrier around any
CBM well or branches of a CBM well in
the coal seam is 50 feet plus the
probable error of location. For example,
a hole that is drilled 500 vertical feet
and deviated into a coal seam at a depth
of 700 feet using drilling equipment that
has an average accuracy of angular
measurement of one degree, the
probable error of location at a point that
is 4,000 feet from the hole collar is 69.8
feet. Therefore, the minimum working
barrier around this point of the well
bore is 120 feet (69.8 feet plus 50 feet
rounded up to the nearest foot). The 50
additional feet is a reasonable
separation between the probable
location of the well and mining
operations. When mining is within the
minimum working barrier distance from
a CBM well or branch, the mine
operator must comply with the
provisions of this petition. CBM wells
must be prepared in advance for safe
intersection and specific procedures
must be followed on the mining section
in order to protect the miners when
mining within this minimum working
barrier around the well. The DM may
require a greater minimum working
barrier around CBM wells where
geologic conditions, historical location
errors, or other factors warrant a greater
barrier.
(3) Ventilation Plan Requirements—
The ventilation plans will contain a
description of all SDD CBM wells
drilled in the area to be mined. This
description would include the well
numbers, the date drilled, the diameter,
the casing information, the coal seams
developed, maximum depth of the
wells, abandonment pressures, and any
other information required by the DM.
All or part of this information may be
listed on the mine ventilation map as
required in 30 CFR 75.372. As required
in 30 CFR 75.371, the ventilation plan
will include the techniques that the
mine operator plans to use to prepare
the SDD wells for safe intersection, the
specifications and stops necessary to
implement these techniques, and the
operational precautions that are
required when mining within the
minimum working barrier. The
ventilation plan will also contain any
additional information or provisions
related to the SDD wells required by the
DM.
(4) Ventilation Map—The mine
ventilation map specified in 30 CFR
75.372 will contain the following
information:
PO 00000
Frm 00081
Fmt 4703
Sfmt 4703
34703
(i) The surface location of all CBM
wells in the active mining area and any
projected mining area as specified in 30
CFR 75.372(b)(14);
(ii) Identifying information of CBM
wells (i.e. API) hole number or
equivalent;
(iii) The date that gas production
began from the well;
(iv) The coal seam intersection of all
CBM wells;
(v) The horizontal extents in the coal
seam of all CBM wells and branches;
(vi) The outline of the probable error
of location of all CBM wells; and
(vii) The date of mine intersection and
the distance between estimated and
actual locations for all intersections of
the CBM well and branches.
b. The petitioner proposes the
following mandatory procedures for
plugging or replugging SDD Wells:
—The mine operator will include in the
mine ventilation plan one or more of
the methods listed below to prepare
SDD wells for safe intersection. The
methods approved in the mine
ventilation plan must be completed
on each SDD well before mining
encroaches on the minimum working
barrier around the well or branch of
the well in the coal seam being
mined. If methane leakage through
subsidence cracks is a problem when
retreat mining, the minimum working
barrier must be maintained around
wells and branches in overlying coal
seams or the wells and branches must
be prepared for safe intersection as
specified in the mine ventilation plan.
(1) Cement Plug—Cement will be
used to fill the entire SDD hole system.
Squeeze cementing techniques are
necessary for SDD plugging due to the
lack of tubing in the hole. Cement
would fill void spaces and eliminate
methane leakage along the hole. Once
the cement has cured, the SDD system
may be intersected multiple times
without further hole preparation. Gas
cutting occurs if the placement pressure
of the cement is less than the methane
pressure in the coal seam. Under these
conditions, gas will bubble out of the
coal seam and into the unset cement
creating a pressurized void or series of
interconnected pressurized voids. Water
cutting occurs when formation water
and standing water in the hole invades
or displaces the unset cement. Standing
water has to be bailed out of the hole or
driven into the formation with
compressed gas to minimize water
cutting. The cement pressure must be
maintained higher than the formation
pressure until the cement sets to
minimize both gas and water cutting.
The cementing program in the
E:\FR\FM\26JYN1.SGM
26JYN1
mstockstill on DSK30JT082PROD with NOTICES
34704
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
ventilation plan must address both gas
and water cutting.
Due to the large volume to be
cemented and potential problems with
cement setting prior to filling the entire
SDD system, adequate sized pumping
units with backup capacity must be
used. Various additives such as
retarders, lightweight extenders,
viscosity modifiers, thixotropic
modifiers, and fly ash may be used in
the cement mix. The volume of cement
pumped would exceed the estimated
hole volume to ensure the complete
filling of all voids.
The complete cementing program,
including hold dewatering, cement,
additives, pressures, pumping times and
equipment must be specified in the
mine ventilation plan. The material
safety data sheets (MSDS) for all
cements, additives and components and
any personal protective equipment and
techniques to protect workers from the
potentially harmful effects of the cement
and cement components would be
included in the ventilation plan.
Records of cement mixes, cement
quantities, pump pressures, and flow
rates and times would be retained for
each hole plugged. SDD holes may be
plugged with cement years in advance
of mining. However, the DM will
require suitable documentation of the
cement plugging in order to approve
mining within the minimum working
barrier around CBM wells.
(2) Polymer Gel—Polymer gels start
out as low viscosity, water-based
mixtures of organic polymer that are
crosslinked using time-delayed
activators to form a water-insoluble,
high-viscosity gel after being pumped
into the SDD system. Although polymer
gel systems never solidify, the activated
gel should develop sufficient strength to
resist gas flow. A gel that is suitable for
treating SDD wells for mine intersection
will reliably fill the SDD system and
prevent gas-filled voids. Any gel
chemistry used for plugging SDD wells
should be resistant to bacterial and
chemical degradation and remain stable
for the duration of mining through a
SDD system.
Water may dilute the gel mixture to
the point where it will not set to the
required strength. Water in the holes
would be removed before injecting the
gel mixture. Water removal can be
accomplished by conventional bailing
and then injecting compressed gas to
squeeze the water that accumulated in
low spots back into the formation. Gas
pressurization would be continued until
the hole is dry. Another potential
problem with gels is that dissolved salts
in the formation waters may interfere
with the cross-linking reactions. Any
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
proposed gel mixtures must be tested
with actual formation waters.
Equipment to mix and pump gels
would have adequate capacity to fill the
hole before the gel sets. Backup units
would be available in case something
breaks while pumping. The volume of
gel pumped would exceed the estimated
hole volume to ensure the complete
filling of all voids and allow for gel to
infiltrate the joints in the coal seam
surrounding the hole. Gel injection and
setting pressures would be specified in
the mine ventilation plan. To reduce the
potential for an inundation of gel, the
final level of gel would be close to the
level of the coal seam and the remainder
of the hole would remain open to the
atmosphere until mining in the vicinity
of the SDD system is completed. Packers
may be used for isolate portions of the
SDD system.
The complete polymer gel program,
including advance testing of the gel
with formation water, dewatering
systems, gel specifications, gel
quantities, gel placement, pressures, and
pumping equipment must be specified
in the mine ventilation plan. The MSDS
for all gel components and any personal
protective equipment and techniques to
protect workers from potentially
harmful effects of the gel and gel
components would be included in the
mine ventilation plan. A record of the
calculated hold volume, gel quantities,
gel formulation, pump pressures and
flow rates and times would be retained
for each hole that is treated with gel.
Other gel chemistries other than organic
polymers may be included in the mine
ventilation plan with appropriate
methods, parameters, and safety
precautions.
(3) Bentonite Gel—High pressure
injection of bentonite gel into the SDD
system will infiltrate the cleat and butt
joints of the coal seam near the well
bore and effectively seal these conduits
against the follow of methane. Bentonite
gel is a thixotropic fluid that sets when
it stops moving, and has a significantly
lower setting viscosity than polymer gel.
The polymer gel fills and seals the
borehole, the lower strength bentonite
gel must penetrate the fractures and
jointing in the coal seam to be effective
in reducing formation permeability
around the hole. The use of bentonite
gel is restricted to deleted CBM
applications that have low
abandonment pressures and limited
recharge potential. In general, these
applications will be mature CBM fields
with long production histories.
A slug of water would be injected
prior the bentonite gel in order to
minimize moisture loss bridging near
the well bore. The volume of gel
PO 00000
Frm 00082
Fmt 4703
Sfmt 4703
pumped would exceed the estimated
hole volume to ensure that the gel
infiltrates the joints in the coal seam for
several feet surrounding the hole. Due to
the large gel volume and potential
problems with premature thixotropic
setting, adequately sized pumping units
with back-up capacity are required.
Additives to the gel may be required to
modify viscosity, reduce filtrates,
reduce surface tension, and promote
sealing of the cracks and joints around
the hole. To reduce the potential for an
inundation of bentonite gel, the final
level of gel would be approximately the
elevation of the coal seam and the
remainder of the hole would remain
open to the atmosphere until mining in
the vicinity of the SDD system is
complete. If a water column is used to
pressurize the gel, it must be bailed
down to the coal seam elevation prior to
intersection.
The complete bentonite gel program,
including formation infiltration and
permeability reduction data, hole
pretreatment, gel specifications, and
additives, gel quantities flow rates,
injection pressures and infiltration
times, must be specified in the
ventilation plan. The ventilation plan
should list the equipment used to
prepare and pump the gel. The MSDS
for all gel components and any personal
protective equipment and techniques to
protect workers from the potentially
harmful effects of the gel and additives
would be included in the ventilation
plan. A record of the hole preparation,
gel quantities, gel formulation, pump
pressures, and flow rates and times
would be retained for each hole that is
treated with bentonite gel.
(4) Active Pressure Management and
Water Infusion—Reducing the pressure
in the hole to less than atmospheric
pressure by operating a vacuum blower
connected to the wellhead may facilitate
safe intersection of the hole by a coal
mine. The negative pressure in the hole
will limit the quantity of methane
released into the higher pressure mine
atmosphere. If the mine intersection is
near the end of a horizontal branch of
the SDD system, air will flow from the
mine into the upstream side of the hold
and be exhausted through the blower on
the surface. On the downstream side of
the intersection, if the open hole length
is short, the methane emitted from this
side of the hole may be diluted to safe
levels with ventilation air. Conversely,
safely intersecting this system near the
bottom of the vertical hole may not be
possible because the methane emissions
from the multiple downstream branches
may be too great to dilute with
ventilation air. The methane emission
rate is directly proportional to the
E:\FR\FM\26JYN1.SGM
26JYN1
mstockstill on DSK30JT082PROD with NOTICES
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
length of the open hole. Successful
application of vacuum systems may be
limited by caving of the hole or water
collected in dips in the SDD system.
Another important factor in the success
of vacuum systems is the methane
liberation rate of the coal formation
around the well. Older, more depleted
wells that have lower methane emission
rates are more amenable to this
technique. The remaining methane
content and the formation permeability
should be addressed in the mine
ventilation plan.
Packer may be used to reduce
methane inflow into the coal mine after
intersection. All packers on the
downstream side of the hole must be
equipped with a center pipe so that the
inby methane pressure may be
measured or so that water may be
injected. Subsequent intersections
would not take place if pressure in a
packer-sealed hole is excessive.
Alternatively, methane produced by the
downstream hole may be piped to an inmine degas system to safely transport
the methane out of the mine or may be
piped to the return air course for
dilution. In-mine methane piping would
be protected as stipulated in ‘‘Piping
Methane in Underground Coal Mines,
MSHA IR 1094, (1978). Protected
methane diffusion zones may be
established in return air courses if
needed.
Detailed sketches and safety
precautions for methane collection,
piping and diffusion systems must be
included in the mine ventilation plan
(30 CFR 75.371(ee)).
Water infusion prior to intersecting
the well will temporarily limit methane
flow. Water infusion may also help
control coal dust levels during mining.
High water infusion pressures may be
obtained prior to the initial intersection
by the hydraulic head resulting from the
hole depth or by pumping. Water
infusion pressures for subsequent
intersections are limited by leakage
around in-mine packers and limitations
of the mine water distribution system. If
water is infused prior to the initial
intersection, the water level in the hole
must be lowered to the coal seam
elevation before the intersection.
The complete pressure management
strategy including negative pressure
application, wellhead equipment, and
use of packers, in-mine piping, methane
dilution, and water infusion must be
specified in the mine ventilation plan.
Procedures for controlling methane in
the downstream hole must be specified
in the mine ventilation plan. The
remaining methane content and
formation permeability would be
addressed in the mine ventilation plan.
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
The potential for the coal seam to cave
into the well would be addressed in the
mine ventilation plan. Dewatering
methods would be included in the mine
ventilation plan. A record of the
negative pressures applied to the
system, methane liberation, use of
packers and any water infusion
pressures and application time would
be retained for each intersection.
(5) Remedial Work—If problems are
encountered in preparing the holes for
safe intersection, remedial measures
must be taken to protect the miners. For
example, if only one-half of the
calculated hold volume of cement could
be placed into a SDD well due to hole
blockage, holes would be drilled near
each branch that will be intersected and
squeeze cemented using pressures
sufficient to fracture into the potentially
empty SDD holes. The DM will approve
remedial work in the mine ventilation
plan on a case-by-case basis.
c. The petitioner proposes to use the
following mandatory procedures after
approval has been granted by the DM to
mine within the minimum working
barrier around the well or branch of the
well:
(1) The mine operator, the DM, a
representative of the miners, or the
appropriate State agency may request a
conference prior to any intersection or
after any intersection to discuss issues
or concerns. Upon receipt of any
request, the DM will schedule a
conference. The party requesting the
conference will notify all other parties
listed above within a reasonable time
prior to the conference to provide
opportunity for participation.
(2) The mine operator must notify the
DM, the State agency, and the
representative of the miners at least 48
hours prior the intended intersection of
any CBM well.
(3) The initial intersection of a well or
branch of a well typically has higher
risk than subsequent intersections. The
initial intersection typically indicates if
the well preparation is sufficient to
prevent the inundation of methane. For
the initial intersection of a well or
branch the following procedures are
mandatory:
(a) When mining advances within the
minimum barrier distance of the well or
branches of the well, the entries that
will intersect the well or branches must
be posted with a readily visible
marking. For longwalls, both the head
and tailgate entries must be so marked.
Marks must be advanced to within 100
feet of the working face as mining
progresses. Marks will be removed after
well or branches are intersected in each
entry or after mining has exited the
minimum barrier distance of the well.
PO 00000
Frm 00083
Fmt 4703
Sfmt 4703
34705
(b) Entries that will intersect vertical
segments of a well will be marked with
drivage sights in the last open crosscut
when mining is within 100 feet of the
well. When a vertical segment of a well
will be intersected by a longwall,
drivage sights will be installed on 10foot centers starting 50 feet in advance
of the anticipated intersection. Drivage
sights will be installed in both the
headgate and tailgate entries of the
longwall.
(c) Firefighting equipment, including
fire extinguishers, rock dust, and
sufficient fire hose to reach the working
face area of the mine-through (when
either the conventional or continuous
mining method is used), will be
available and operable during each well
mine-through. A fire hose will be
located in the last open crosscut of the
entry or room. A water line to the belt
conveyor tailpiece will be maintained
along with a sufficient amount of fire
hose to reach the farthest point of
penetration on the section. When the
longwall mining method is used, a hose
to the longwall water supply is
sufficient. All fire hoses will be
connected and ready for use, but do not
have to be charged with water during
the cut-through.
(d) The operator will keep available at
the working section a sufficient supply
of roof support and ventilation
materials. In addition, emergency plugs,
packers, and setting tools to seal both
sides of the well or branch will be
available in the immediate area of the
cut-through.
(e) When mining advances within the
minimum working barrier distance from
the well or branch of the well, the
operator will service all equipment and
check for permissibility at least once
daily. Daily permissibility examinations
must continue until the well or branch
is intersected or until mining exits the
minimum working barrier around the
well or branch.
(f) When mining advances within the
minimum working barrier distance from
the well or branch of the well, the
operator will calibrate the methane
monitor(s) on the longwall, continuous
mining machine and loading machine at
least once daily. Daily methane monitor
calibration must continue until the well
or branch is intersected or until mining
exits the minimum working barrier
around the well or branch.
(g) When mining is in progress, the
operator will perform tests for methane
with a handheld methane detector at
least every 10 minutes from the time
mining with the continuous mining
machine or longwall face is within the
minimum working barrier around the
well or branch. During the cutting
E:\FR\FM\26JYN1.SGM
26JYN1
mstockstill on DSK30JT082PROD with NOTICES
34706
Federal Register / Vol. 82, No. 142 / Wednesday, July 26, 2017 / Notices
process, no individual will be allowed
on the return side until the minethrough has been completed and the
area has been examined and declared
safe. The shearer must be idle when any
miners are inby the tail drum.
(h) When using continuous or
conventional mining methods, the
working place will be free from
accumulations of coal dust and coal
spillages, and rock dust will be placed
on the roof, rib, and floor to within 20
feet of the face when mining through the
well or branch. On longwall sections,
rock dust will be applied on the roof,
rib, and floor up to both the headgate
and tailgate pillared area.
(i) Immediately after the well or
branch is intersected, the operator will
de-energize all equipment, and the
certified person will thoroughly
examine and determine the working
place safe before mining is resumed.
(j) After a well or well branch has
been intersected and the working place
determined safe, mining will continue
inby the well a sufficient distance to
permit adequate ventilation around the
area of the well or branch.
(k) No open flame will be permitted
in the area until adequate ventilation
has been established around the
wellbore or branch. Any casing, tubing
or stuck tools will be removed using the
methods approved in the mine
ventilation plan.
(l) No person will be permitted in the
working place of the mine-through
operation during active mining except
those persons actually engaged in the
mining operation, including mine
management, representatives of miners,
personnel from MSHA, and personnel
from the appropriate State agency.
(m) The mine operator will warn all
personnel in the mine of the planned
intersection of the well or branch prior
to their going underground if the
planned intersection is to occur during
their shift. This warning will be
repeated for all shifts until the well or
branch has been intersected.
(n) A certified official will directly
supervise the mine-through operation
and only the certified official in charge
will issue instructions concerning the
mine-through operation.
(o) All miners will be in known
locations and will stay in
communication with the responsible
person, in accordance with the site
specific approved emergency response
plan when active mining occurs within
the minimum working barrier of the
well or branch.
(p) The responsible person required in
30 CFR 75.1501 is responsible for well
intersection emergencies. The well
intersection procedures must be
VerDate Sep<11>2014
17:49 Jul 25, 2017
Jkt 241001
reviewed by the responsible person
prior to any planned intersection.
(q) A copy of the approved petition
will be maintained at the mine and be
available to the miners.
(r) The provisions of the approved
petition do not impair the authority of
representative of MSHA to interrupt or
halt the mine-through operation and to
issue a withdrawal order when its
deemed necessary for the safety of the
miners. MSHA may order an
interruption or cessation of the minethrough operation and/or withdrawal of
personnel by issuing either a verbal or
a written order to that effect to a
representative of the operator, and will
include the basis for the order.
Operations in the affected area of the
mine may not resume until a
representative of MSHA permits
resumption of mine-through operations.
The miner operator and miners will
comply with verbal or written MSHA
orders immediately. All verbal orders
will be committed to in writing within
a reasonable time as conditions permit.
(s) For subsequent intersections of
branches of a well, appropriate
procedures to protect the miners will be
specified in the mine ventilation plan.
d. The petitioner proposes to use the
following mandatory procedures after
SDD intersections:
(1) All intersections with SDD wells
and branches that are in intake air
courses will be examined as part of the
pre-shift examinations required in 30
CFR 75.360.
(2) All other intersections with SDD
wells and branches will be examined as
part of the weekly examinations
required in 30 CFR 75.364.
Within 30 days after this petition
becomes final, the petitioner will submit
proposed revisions for its approved Part
48 training plan to the DM. These
proposed revisions will include initial
and refresher training regarding
compliance with the terms and
conditions stated in the petition. The
mine operator will provide all miners
involved in the mine-through of a well
or branch with training regarding the
requirements of this petition prior to
mining within the minimum working
barrier of the next well or branch
intended to be mined through.
Within 30 days after this petition
becomes final, the petitioner will submit
proposed revisions for its approved
mine emergency evacuation and
firefighting program of instruction
required in 30 CFR 75.1502. The mine
operator will revise the program to
include the hazards and evacuation
procedures to be used for well
intersections. All underground miners
will be trained in the revised program
PO 00000
Frm 00084
Fmt 4703
Sfmt 4703
within 30 days of the approval of the
revised mine emergency evacuation and
firefighting program of instruction.
The petitioner asserts that the
proposed alternative method will
always guarantee the miners no less
than the same measure of protection
afforded by the standard.
Sheila McConnell,
Director, Office of Standards, Regulations,
and Variances.
[FR Doc. 2017–15674 Filed 7–25–17; 8:45 am]
BILLING CODE 4520–43–P
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
[Notice: 17–053]
Notice of Intent To Hold International
Space Station Stakeholder Workshop
National Aeronautics and
Space Administration.
ACTION: Stakeholder workshop.
AGENCY:
The International Space
Station (ISS) Stakeholder Workshop is
intended to engage ISS stakeholders in
gathering information that may be used
in the development of NASA’s future
ISS planning activities. Specifically, the
workshop targets the commercial space
sector, researchers, technology
developers, transportation and
habitation providers, other government
agencies, and other interested parties,
providing a forum for dialogue with
NASA on topics relevant to ISS future
planning. Topics for discussion include
the low Earth orbit (LEO) commercial,
research, and development market;
access to space; the value of permanent
human habitation in LEO; and structure
and planning for public/private
partnerships in LEO.
DATES: Wednesday, August 9, 2017,
8:30am–6:00pm, Local Time.
ADDRESSES: Marriott Marquis
Washington DC, 901 Massachusetts Ave
NW., Washington, DC 20001. Please see
the workshop Web site at: https://
www.nasa.gov/content/internationalspace-station-stakeholder-workshop.
FOR FURTHER INFORMATION CONTACT:
Jacob Keaton, 202–358–1507, hq-issleo@mail.nasa.gov.
SUPPLEMENTARY INFORMATION: The
meeting will be open to the public up
to the seating capacity of the room.
Attendees are requested to register at:
https://www.nasa.gov/content/
international-space-station-stakeholderworkshop. The agenda will consist of a
plenary session in the morning followed
by topic-specific breakouts in the
afternoon.
SUMMARY:
E:\FR\FM\26JYN1.SGM
26JYN1
Agencies
[Federal Register Volume 82, Number 142 (Wednesday, July 26, 2017)]
[Notices]
[Pages 34701-34706]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-15674]
-----------------------------------------------------------------------
DEPARTMENT OF LABOR
Mine Safety and Health Administration
Petitions for Modification of Application of Existing Mandatory
Safety Standards
AGENCY: Mine Safety and Health Administration, Labor.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: This notice is a summary of petitions for modification
submitted to the Mine Safety and Health Administration (MSHA) by the
parties listed below.
DATES: All comments on the petitions must be received by MSHA's Office
of Standards, Regulations, and Variances on or before August 25, 2017.
ADDRESSES: You may submit your comments, identified by ``docket
number'' on the subject line, by any of the following methods:
1. Electronic Mail: zzMSHA-comments@dol.gov. Include the docket
number of the petition in the subject line of the message.
2. Facsimile: 202-693-9441.
3. Regular Mail or Hand Delivery: MSHA, Office of Standards,
Regulations, and Variances, 201 12th Street South, Suite 4E401,
Arlington, Virginia 22202-5452, Attention: Sheila McConnell, Director,
Office of Standards, Regulations, and Variances. Persons delivering
documents are required to check in at the receptionist's desk in Suite
4E401. Individuals may inspect copies of the petitions and comments
during normal business hours at the address listed above.
MSHA will consider only comments postmarked by the U.S. Postal
Service or proof of delivery from another delivery service such as UPS
or Federal Express on or before the deadline for comments.
FOR FURTHER INFORMATION CONTACT: Barbara Barron, Office of Standards,
Regulations, and Variances at 202-693-9447 (Voice),
barron.barbara@dol.gov (Email), or 202-693-9441 (Facsimile). [These are
not toll-free numbers.]
SUPPLEMENTARY INFORMATION: Section 101(c) of the Federal Mine Safety
and Health Act of 1977 and Title 30 of the Code of Federal Regulations
part 44 govern the application, processing, and disposition of
petitions for modification.
I. Background
Section 101(c) of the Federal Mine Safety and Health Act of 1977
(Mine Act) allows the mine operator or representative of miners to file
a petition to modify the application of any mandatory safety standard
to a coal or
[[Page 34702]]
other mine if the Secretary of Labor (Secretary) determines that:
1. An alternative method of achieving the result of such standard
exists which will at all times guarantee no less than the same measure
of protection afforded the miners of such mine by such standard; or
2. That the application of such standard to such mine will result
in a diminution of safety to the miners in such mine.
In addition, the regulations at 30 CFR 44.10 and 44.11 establish
the requirements and procedures for filing petitions for modification.
II. Petitions for Modification
Docket Number: M-2017-010-C.
Petitioner: Peabody Gateway North Mining, LLC, 12968 Illinois State
Route 13, Coulterville, IL 62237.
Mine: Gateway North Mine, MSHA I.D. No. 11-03235, located in
Randolph County, Illinois.
Regulation Affected: 30 CFR 75.500(d) (Permissible electric
equipment).
Modification Request: The petitioner requests a modification of the
existing standard to permit the use of nonpermissible electronic
testing equipment in the last open crosscut. The petitioner states
that:
(1) Nonpermissible electronic testing and diagnostic equipment to
be used includes: Laptop computers, oscilloscopes, vibration analysis
machines, cable fault detectors, point temperature probes, infrared
temperature devices, insulation testers (meggers), voltage, current
resistance, power testers, and electronic tachometers. Other testing
and diagnostic equipment may be used if approved in advance by the MSHA
District Manager.
(2) All nonpermissible testing and diagnostic equipment used in or
inby the last open crosscut will be examined by a qualified person as
defined in 30 CFR 75.153, prior to use to ensure the equipment is being
maintained in a safe operating condition. These examination results
will be recorded in the weekly examination book and will be made
available to MSHA and the miners at the mine.
(3) A qualified person as defined in 30 CFR 75.151 will
continuously monitor for methane immediately before and during the use
of nonpermissible electronic testing and diagnostic equipment in or
inby the last open crosscut.
(4) Nonpermissible electronic testing and diagnostic equipment will
not be used if methane is detected in concentrations at or above one
percent. When one percent or more methane is detected while the
nonpermissible electronic equipment is being used, the equipment will
be de-energized immediately and will be withdrawn outby the last open
crosscut.
(5) All hand-held methane detectors will be MSHA-approved and
maintained in permissible and proper operating condition as defined in
30 CFR 75.320.
(6) Except for time necessary to troubleshoot under actual mining
conditions coal production in the section will cease. However, coal may
remain in or on the equipment to test and diagnose the equipment under
``load''.
(7) All electronic testing and diagnostic equipment will be used in
accordance with the safe use procedures recommended by the
manufacturer.
(8) Qualified personnel who use electronic testing and diagnostic
equipment will be properly trained to recognize the hazards and
limitations associated with use of the equipment.
The petitioner asserts that the proposed alternative method will at
all times guarantee no less than the same measure of protection
afforded by the standard.
Docket Number: M-2017-011-C.
Petitioner: Peabody Gateway North Mining, LLC, 12968 Illinois State
Route 13, Coulterville, IL 62237.
Mine: Gateway North Mine, MSHA I.D. No. 11-03235, located in
Randolph County, Illinois.
Regulation Affected: 30 CFR 75.507-1(a) (Electric equipment other
than power-connection points; outby the last open crosscut; return air;
permissibility requirements).
Modification Request: The petitioner requests a modification of the
existing standard to permit the use of nonpermissible electronic
testing equipment in return air outby the last open crosscut. The
petitioner states that:
(1) Nonpermissible electronic testing and diagnostic equipment to
be used includes: Laptop computers, oscilloscopes, vibration analysis
machines, cable fault detectors, point temperature probes, infrared
temperature devices, insulation testers (meggers), voltage, current
resistance, power testers, and electronic tachometers. Other testing
and diagnostic equipment may be used if approved in advance by the MSHA
District Manager.
(2) All nonpermissible testing and diagnostic equipment used in
return air outby the last open crosscut will be examined by a qualified
person as defined in 30 CFR 75.153, prior to use to ensure the
equipment is being maintained in a safe operating condition. These
examination results will be recorded in the weekly examination book and
will be made available to MSHA and the miners at the mine.
(3) A qualified person as defined in 30 CFR 75.151 will
continuously monitor for methane immediately before and during the use
of nonpermissible electronic testing and diagnostic equipment in return
air outby the last open crosscut.
(4) Nonpermissible electronic testing and diagnostic equipment will
not be used if methane is detected in concentrations at or above one
percent. When one percent or more methane is detected while the
nonpermissible electronic equipment is being used, the equipment will
be de-energized immediately and will be withdrawn from the return air
outby the last open crosscut.
(5) All hand-held methane detectors will be MSHA approved and
maintained in permissible and proper operating condition as defined in
30 CFR 75.320.
(7) All electronic testing and diagnostic equipment will be used in
accordance with the safe use procedures recommended by the
manufacturer.
(8) Qualified personnel who use electronic testing and diagnostic
equipment will be properly trained to recognize the hazards and
limitations associated with use of the equipment.
The petitioner asserts that the proposed alternative method will at
all times guarantee no less than the same measure of protection
afforded by the standard.
Docket Number: M-2017-012-C.
Petitioner: The Marion County Coal Company, 151 Johnny Cake Road,
Metz, West Virginia 26585.
Mine: Marion County Mine, MSHA I.D. No. 46-01433, located in Marion
County, West Virginia.
Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).
Modification Request: The petitioner requests a modification of
that part of the existing standard that requires the operator to
establish and maintain barriers around its surface directional drilled
(SDD) wells. The petitioner asserts that the proposed alternative
method has been successfully used to prepare coal bed methane (CBM)
wells for safe intersection by using one or more of the following
methods: (1) Cement Plug, (2) Polymer Gel, (3) Bentonite Gel, (4)
Active Pressure Management and Water Infusion, and (5) Remedial Work.
The proposed alternative method will prevent the CBM well methane from
entering the
[[Page 34703]]
underground mine. The alternative method includes well plugging
procedures, water infusion and ventilation method, and procedures for
mining through a CBM well with horizontal laterals. The petitioner
states that:
(1) A minimum working barrier of 300 feet in diameter will be
maintained around all SDD wells until approval to proceed with mining
has been obtained from the District Manager (DM). The barrier would
extend around all vertical and horizontal branches drilled in the coal
seam. The barrier would also extend around all vertical and horizontal
branches within overlying coal seams subject to caving or subsidence
from the coal seam being mined when methane leakage through the
subsidence zone is possible.
(2) The DM may choose to approve each branch intersection, each
well, or a group of wells as applicable to the conditions. The DM may
require a certified review of the proposed methods to prepare the SDD
wells for intersection by a professional engineer in order to assess
the applicability of the proposed system(s) to the mine-specific
conditions.
a. The petitioner proposes to use the following procedures for
preparing, plugging, and replugging SDD wells using mandatory
computations and administrative procedures prior to plugging or
replugging:
(1) Probable Error of Location--Directional drilling systems rely
on sophisticated angular measurement systems and computer models to
calculate the estimated location of the well bore. This estimated hole
location is subject to cumulative measurement errors so that the
distance between actual and estimated location of the well bore
increases with the depth of the hole. Modern directional drilling
systems are typically accurate within one or two degrees depending on
the specific equipment and techniques. The probable error of location
is defined by a cone described by the average accuracy of angular
measurement around the length of the hole. For example, a hole that is
drilled 500 vertical feet and deviated into a coal seam at a depth of
700 feet would have a probable error of location at a point that is
4,000 feet from the hole collar (about 2,986 feet horizontally from the
well collar) of 69.8 feet (4,000 feet x sine (1.0 degree)) if the
average accuracy of angular measurement was on degree and 139.6 feet if
the average accuracy of angular measurement was two degrees. In
addition to the probable error of location, the true hole location is
also affected by underground survey errors, surface survey errors, and
random survey errors.
(2) Minimum Working Barrier Around Well--For purposes of this
petition, the minimum working barrier around any CBM well or branches
of a CBM well in the coal seam is 50 feet plus the probable error of
location. For example, a hole that is drilled 500 vertical feet and
deviated into a coal seam at a depth of 700 feet using drilling
equipment that has an average accuracy of angular measurement of one
degree, the probable error of location at a point that is 4,000 feet
from the hole collar is 69.8 feet. Therefore, the minimum working
barrier around this point of the well bore is 120 feet (69.8 feet plus
50 feet rounded up to the nearest foot). The 50 additional feet is a
reasonable separation between the probable location of the well and
mining operations. When mining is within the minimum working barrier
distance from a CBM well or branch, the mine operator must comply with
the provisions of this petition. CBM wells must be prepared in advance
for safe intersection and specific procedures must be followed on the
mining section in order to protect the miners when mining within this
minimum working barrier around the well. The DM may require a greater
minimum working barrier around CBM wells where geologic conditions,
historical location errors, or other factors warrant a greater barrier.
(3) Ventilation Plan Requirements--The ventilation plans will
contain a description of all SDD CBM wells drilled in the area to be
mined. This description would include the well numbers, the date
drilled, the diameter, the casing information, the coal seams
developed, maximum depth of the wells, abandonment pressures, and any
other information required by the DM. All or part of this information
may be listed on the mine ventilation map as required in 30 CFR 75.372.
As required in 30 CFR 75.371, the ventilation plan will include the
techniques that the mine operator plans to use to prepare the SDD wells
for safe intersection, the specifications and stops necessary to
implement these techniques, and the operational precautions that are
required when mining within the minimum working barrier. The
ventilation plan will also contain any additional information or
provisions related to the SDD wells required by the DM.
(4) Ventilation Map--The mine ventilation map specified in 30 CFR
75.372 will contain the following information:
(i) The surface location of all CBM wells in the active mining area
and any projected mining area as specified in 30 CFR 75.372(b)(14);
(ii) Identifying information of CBM wells (i.e. API) hole number or
equivalent;
(iii) The date that gas production began from the well;
(iv) The coal seam intersection of all CBM wells;
(v) The horizontal extents in the coal seam of all CBM wells and
branches;
(vi) The outline of the probable error of location of all CBM
wells; and
(vii) The date of mine intersection and the distance between
estimated and actual locations for all intersections of the CBM well
and branches.
b. The petitioner proposes the following mandatory procedures for
plugging or replugging SDD Wells:
--The mine operator will include in the mine ventilation plan one or
more of the methods listed below to prepare SDD wells for safe
intersection. The methods approved in the mine ventilation plan must be
completed on each SDD well before mining encroaches on the minimum
working barrier around the well or branch of the well in the coal seam
being mined. If methane leakage through subsidence cracks is a problem
when retreat mining, the minimum working barrier must be maintained
around wells and branches in overlying coal seams or the wells and
branches must be prepared for safe intersection as specified in the
mine ventilation plan.
(1) Cement Plug--Cement will be used to fill the entire SDD hole
system. Squeeze cementing techniques are necessary for SDD plugging due
to the lack of tubing in the hole. Cement would fill void spaces and
eliminate methane leakage along the hole. Once the cement has cured,
the SDD system may be intersected multiple times without further hole
preparation. Gas cutting occurs if the placement pressure of the cement
is less than the methane pressure in the coal seam. Under these
conditions, gas will bubble out of the coal seam and into the unset
cement creating a pressurized void or series of interconnected
pressurized voids. Water cutting occurs when formation water and
standing water in the hole invades or displaces the unset cement.
Standing water has to be bailed out of the hole or driven into the
formation with compressed gas to minimize water cutting. The cement
pressure must be maintained higher than the formation pressure until
the cement sets to minimize both gas and water cutting. The cementing
program in the
[[Page 34704]]
ventilation plan must address both gas and water cutting.
Due to the large volume to be cemented and potential problems with
cement setting prior to filling the entire SDD system, adequate sized
pumping units with backup capacity must be used. Various additives such
as retarders, lightweight extenders, viscosity modifiers, thixotropic
modifiers, and fly ash may be used in the cement mix. The volume of
cement pumped would exceed the estimated hole volume to ensure the
complete filling of all voids.
The complete cementing program, including hold dewatering, cement,
additives, pressures, pumping times and equipment must be specified in
the mine ventilation plan. The material safety data sheets (MSDS) for
all cements, additives and components and any personal protective
equipment and techniques to protect workers from the potentially
harmful effects of the cement and cement components would be included
in the ventilation plan. Records of cement mixes, cement quantities,
pump pressures, and flow rates and times would be retained for each
hole plugged. SDD holes may be plugged with cement years in advance of
mining. However, the DM will require suitable documentation of the
cement plugging in order to approve mining within the minimum working
barrier around CBM wells.
(2) Polymer Gel--Polymer gels start out as low viscosity, water-
based mixtures of organic polymer that are crosslinked using time-
delayed activators to form a water-insoluble, high-viscosity gel after
being pumped into the SDD system. Although polymer gel systems never
solidify, the activated gel should develop sufficient strength to
resist gas flow. A gel that is suitable for treating SDD wells for mine
intersection will reliably fill the SDD system and prevent gas-filled
voids. Any gel chemistry used for plugging SDD wells should be
resistant to bacterial and chemical degradation and remain stable for
the duration of mining through a SDD system.
Water may dilute the gel mixture to the point where it will not set
to the required strength. Water in the holes would be removed before
injecting the gel mixture. Water removal can be accomplished by
conventional bailing and then injecting compressed gas to squeeze the
water that accumulated in low spots back into the formation. Gas
pressurization would be continued until the hole is dry. Another
potential problem with gels is that dissolved salts in the formation
waters may interfere with the cross-linking reactions. Any proposed gel
mixtures must be tested with actual formation waters.
Equipment to mix and pump gels would have adequate capacity to fill
the hole before the gel sets. Backup units would be available in case
something breaks while pumping. The volume of gel pumped would exceed
the estimated hole volume to ensure the complete filling of all voids
and allow for gel to infiltrate the joints in the coal seam surrounding
the hole. Gel injection and setting pressures would be specified in the
mine ventilation plan. To reduce the potential for an inundation of
gel, the final level of gel would be close to the level of the coal
seam and the remainder of the hole would remain open to the atmosphere
until mining in the vicinity of the SDD system is completed. Packers
may be used for isolate portions of the SDD system.
The complete polymer gel program, including advance testing of the
gel with formation water, dewatering systems, gel specifications, gel
quantities, gel placement, pressures, and pumping equipment must be
specified in the mine ventilation plan. The MSDS for all gel components
and any personal protective equipment and techniques to protect workers
from potentially harmful effects of the gel and gel components would be
included in the mine ventilation plan. A record of the calculated hold
volume, gel quantities, gel formulation, pump pressures and flow rates
and times would be retained for each hole that is treated with gel.
Other gel chemistries other than organic polymers may be included in
the mine ventilation plan with appropriate methods, parameters, and
safety precautions.
(3) Bentonite Gel--High pressure injection of bentonite gel into
the SDD system will infiltrate the cleat and butt joints of the coal
seam near the well bore and effectively seal these conduits against the
follow of methane. Bentonite gel is a thixotropic fluid that sets when
it stops moving, and has a significantly lower setting viscosity than
polymer gel. The polymer gel fills and seals the borehole, the lower
strength bentonite gel must penetrate the fractures and jointing in the
coal seam to be effective in reducing formation permeability around the
hole. The use of bentonite gel is restricted to deleted CBM
applications that have low abandonment pressures and limited recharge
potential. In general, these applications will be mature CBM fields
with long production histories.
A slug of water would be injected prior the bentonite gel in order
to minimize moisture loss bridging near the well bore. The volume of
gel pumped would exceed the estimated hole volume to ensure that the
gel infiltrates the joints in the coal seam for several feet
surrounding the hole. Due to the large gel volume and potential
problems with premature thixotropic setting, adequately sized pumping
units with back-up capacity are required. Additives to the gel may be
required to modify viscosity, reduce filtrates, reduce surface tension,
and promote sealing of the cracks and joints around the hole. To reduce
the potential for an inundation of bentonite gel, the final level of
gel would be approximately the elevation of the coal seam and the
remainder of the hole would remain open to the atmosphere until mining
in the vicinity of the SDD system is complete. If a water column is
used to pressurize the gel, it must be bailed down to the coal seam
elevation prior to intersection.
The complete bentonite gel program, including formation
infiltration and permeability reduction data, hole pretreatment, gel
specifications, and additives, gel quantities flow rates, injection
pressures and infiltration times, must be specified in the ventilation
plan. The ventilation plan should list the equipment used to prepare
and pump the gel. The MSDS for all gel components and any personal
protective equipment and techniques to protect workers from the
potentially harmful effects of the gel and additives would be included
in the ventilation plan. A record of the hole preparation, gel
quantities, gel formulation, pump pressures, and flow rates and times
would be retained for each hole that is treated with bentonite gel.
(4) Active Pressure Management and Water Infusion--Reducing the
pressure in the hole to less than atmospheric pressure by operating a
vacuum blower connected to the wellhead may facilitate safe
intersection of the hole by a coal mine. The negative pressure in the
hole will limit the quantity of methane released into the higher
pressure mine atmosphere. If the mine intersection is near the end of a
horizontal branch of the SDD system, air will flow from the mine into
the upstream side of the hold and be exhausted through the blower on
the surface. On the downstream side of the intersection, if the open
hole length is short, the methane emitted from this side of the hole
may be diluted to safe levels with ventilation air. Conversely, safely
intersecting this system near the bottom of the vertical hole may not
be possible because the methane emissions from the multiple downstream
branches may be too great to dilute with ventilation air. The methane
emission rate is directly proportional to the
[[Page 34705]]
length of the open hole. Successful application of vacuum systems may
be limited by caving of the hole or water collected in dips in the SDD
system. Another important factor in the success of vacuum systems is
the methane liberation rate of the coal formation around the well.
Older, more depleted wells that have lower methane emission rates are
more amenable to this technique. The remaining methane content and the
formation permeability should be addressed in the mine ventilation
plan.
Packer may be used to reduce methane inflow into the coal mine
after intersection. All packers on the downstream side of the hole must
be equipped with a center pipe so that the inby methane pressure may be
measured or so that water may be injected. Subsequent intersections
would not take place if pressure in a packer-sealed hole is excessive.
Alternatively, methane produced by the downstream hole may be piped to
an in-mine degas system to safely transport the methane out of the mine
or may be piped to the return air course for dilution. In-mine methane
piping would be protected as stipulated in ``Piping Methane in
Underground Coal Mines, MSHA IR 1094, (1978). Protected methane
diffusion zones may be established in return air courses if needed.
Detailed sketches and safety precautions for methane collection,
piping and diffusion systems must be included in the mine ventilation
plan (30 CFR 75.371(ee)).
Water infusion prior to intersecting the well will temporarily
limit methane flow. Water infusion may also help control coal dust
levels during mining. High water infusion pressures may be obtained
prior to the initial intersection by the hydraulic head resulting from
the hole depth or by pumping. Water infusion pressures for subsequent
intersections are limited by leakage around in-mine packers and
limitations of the mine water distribution system. If water is infused
prior to the initial intersection, the water level in the hole must be
lowered to the coal seam elevation before the intersection.
The complete pressure management strategy including negative
pressure application, wellhead equipment, and use of packers, in-mine
piping, methane dilution, and water infusion must be specified in the
mine ventilation plan. Procedures for controlling methane in the
downstream hole must be specified in the mine ventilation plan. The
remaining methane content and formation permeability would be addressed
in the mine ventilation plan. The potential for the coal seam to cave
into the well would be addressed in the mine ventilation plan.
Dewatering methods would be included in the mine ventilation plan. A
record of the negative pressures applied to the system, methane
liberation, use of packers and any water infusion pressures and
application time would be retained for each intersection.
(5) Remedial Work--If problems are encountered in preparing the
holes for safe intersection, remedial measures must be taken to protect
the miners. For example, if only one-half of the calculated hold volume
of cement could be placed into a SDD well due to hole blockage, holes
would be drilled near each branch that will be intersected and squeeze
cemented using pressures sufficient to fracture into the potentially
empty SDD holes. The DM will approve remedial work in the mine
ventilation plan on a case-by-case basis.
c. The petitioner proposes to use the following mandatory
procedures after approval has been granted by the DM to mine within the
minimum working barrier around the well or branch of the well:
(1) The mine operator, the DM, a representative of the miners, or
the appropriate State agency may request a conference prior to any
intersection or after any intersection to discuss issues or concerns.
Upon receipt of any request, the DM will schedule a conference. The
party requesting the conference will notify all other parties listed
above within a reasonable time prior to the conference to provide
opportunity for participation.
(2) The mine operator must notify the DM, the State agency, and the
representative of the miners at least 48 hours prior the intended
intersection of any CBM well.
(3) The initial intersection of a well or branch of a well
typically has higher risk than subsequent intersections. The initial
intersection typically indicates if the well preparation is sufficient
to prevent the inundation of methane. For the initial intersection of a
well or branch the following procedures are mandatory:
(a) When mining advances within the minimum barrier distance of the
well or branches of the well, the entries that will intersect the well
or branches must be posted with a readily visible marking. For
longwalls, both the head and tailgate entries must be so marked. Marks
must be advanced to within 100 feet of the working face as mining
progresses. Marks will be removed after well or branches are
intersected in each entry or after mining has exited the minimum
barrier distance of the well.
(b) Entries that will intersect vertical segments of a well will be
marked with drivage sights in the last open crosscut when mining is
within 100 feet of the well. When a vertical segment of a well will be
intersected by a longwall, drivage sights will be installed on 10-foot
centers starting 50 feet in advance of the anticipated intersection.
Drivage sights will be installed in both the headgate and tailgate
entries of the longwall.
(c) Firefighting equipment, including fire extinguishers, rock
dust, and sufficient fire hose to reach the working face area of the
mine-through (when either the conventional or continuous mining method
is used), will be available and operable during each well mine-through.
A fire hose will be located in the last open crosscut of the entry or
room. A water line to the belt conveyor tailpiece will be maintained
along with a sufficient amount of fire hose to reach the farthest point
of penetration on the section. When the longwall mining method is used,
a hose to the longwall water supply is sufficient. All fire hoses will
be connected and ready for use, but do not have to be charged with
water during the cut-through.
(d) The operator will keep available at the working section a
sufficient supply of roof support and ventilation materials. In
addition, emergency plugs, packers, and setting tools to seal both
sides of the well or branch will be available in the immediate area of
the cut-through.
(e) When mining advances within the minimum working barrier
distance from the well or branch of the well, the operator will service
all equipment and check for permissibility at least once daily. Daily
permissibility examinations must continue until the well or branch is
intersected or until mining exits the minimum working barrier around
the well or branch.
(f) When mining advances within the minimum working barrier
distance from the well or branch of the well, the operator will
calibrate the methane monitor(s) on the longwall, continuous mining
machine and loading machine at least once daily. Daily methane monitor
calibration must continue until the well or branch is intersected or
until mining exits the minimum working barrier around the well or
branch.
(g) When mining is in progress, the operator will perform tests for
methane with a handheld methane detector at least every 10 minutes from
the time mining with the continuous mining machine or longwall face is
within the minimum working barrier around the well or branch. During
the cutting
[[Page 34706]]
process, no individual will be allowed on the return side until the
mine-through has been completed and the area has been examined and
declared safe. The shearer must be idle when any miners are inby the
tail drum.
(h) When using continuous or conventional mining methods, the
working place will be free from accumulations of coal dust and coal
spillages, and rock dust will be placed on the roof, rib, and floor to
within 20 feet of the face when mining through the well or branch. On
longwall sections, rock dust will be applied on the roof, rib, and
floor up to both the headgate and tailgate pillared area.
(i) Immediately after the well or branch is intersected, the
operator will de-energize all equipment, and the certified person will
thoroughly examine and determine the working place safe before mining
is resumed.
(j) After a well or well branch has been intersected and the
working place determined safe, mining will continue inby the well a
sufficient distance to permit adequate ventilation around the area of
the well or branch.
(k) No open flame will be permitted in the area until adequate
ventilation has been established around the wellbore or branch. Any
casing, tubing or stuck tools will be removed using the methods
approved in the mine ventilation plan.
(l) No person will be permitted in the working place of the mine-
through operation during active mining except those persons actually
engaged in the mining operation, including mine management,
representatives of miners, personnel from MSHA, and personnel from the
appropriate State agency.
(m) The mine operator will warn all personnel in the mine of the
planned intersection of the well or branch prior to their going
underground if the planned intersection is to occur during their shift.
This warning will be repeated for all shifts until the well or branch
has been intersected.
(n) A certified official will directly supervise the mine-through
operation and only the certified official in charge will issue
instructions concerning the mine-through operation.
(o) All miners will be in known locations and will stay in
communication with the responsible person, in accordance with the site
specific approved emergency response plan when active mining occurs
within the minimum working barrier of the well or branch.
(p) The responsible person required in 30 CFR 75.1501 is
responsible for well intersection emergencies. The well intersection
procedures must be reviewed by the responsible person prior to any
planned intersection.
(q) A copy of the approved petition will be maintained at the mine
and be available to the miners.
(r) The provisions of the approved petition do not impair the
authority of representative of MSHA to interrupt or halt the mine-
through operation and to issue a withdrawal order when its deemed
necessary for the safety of the miners. MSHA may order an interruption
or cessation of the mine-through operation and/or withdrawal of
personnel by issuing either a verbal or a written order to that effect
to a representative of the operator, and will include the basis for the
order. Operations in the affected area of the mine may not resume until
a representative of MSHA permits resumption of mine-through operations.
The miner operator and miners will comply with verbal or written MSHA
orders immediately. All verbal orders will be committed to in writing
within a reasonable time as conditions permit.
(s) For subsequent intersections of branches of a well, appropriate
procedures to protect the miners will be specified in the mine
ventilation plan.
d. The petitioner proposes to use the following mandatory
procedures after SDD intersections:
(1) All intersections with SDD wells and branches that are in
intake air courses will be examined as part of the pre-shift
examinations required in 30 CFR 75.360.
(2) All other intersections with SDD wells and branches will be
examined as part of the weekly examinations required in 30 CFR 75.364.
Within 30 days after this petition becomes final, the petitioner
will submit proposed revisions for its approved Part 48 training plan
to the DM. These proposed revisions will include initial and refresher
training regarding compliance with the terms and conditions stated in
the petition. The mine operator will provide all miners involved in the
mine-through of a well or branch with training regarding the
requirements of this petition prior to mining within the minimum
working barrier of the next well or branch intended to be mined
through.
Within 30 days after this petition becomes final, the petitioner
will submit proposed revisions for its approved mine emergency
evacuation and firefighting program of instruction required in 30 CFR
75.1502. The mine operator will revise the program to include the
hazards and evacuation procedures to be used for well intersections.
All underground miners will be trained in the revised program within 30
days of the approval of the revised mine emergency evacuation and
firefighting program of instruction.
The petitioner asserts that the proposed alternative method will
always guarantee the miners no less than the same measure of protection
afforded by the standard.
Sheila McConnell,
Director, Office of Standards, Regulations, and Variances.
[FR Doc. 2017-15674 Filed 7-25-17; 8:45 am]
BILLING CODE 4520-43-P