Sunshine Act Meeting, 29781 [2013-12194]
Download as PDF
Federal Register / Vol. 78, No. 98 / Tuesday, May 21, 2013 / Notices
Contact Person: Dr. Gail Dodge, Program
Director for Nuclear Physics; National
Science Foundation, 4201 Wilson Blvd.,
Arlington, VA 22230. Telephone: (703) 292–
8958.
Purpose of Meeting: Annual Site Visit as
per the terms of the Laboratory’s Five-year
Cooperative Agreement.
Agenda
June 18, 2013
8:00 a.m.–10:15 a.m. Closed—Executive
Session, Laboratory, Operations,
Upgrades and Commissioning Overview
10:15 a.m.–11:15 a.m. Open—Accelerator
Physics Research, and Research,
Education and Mentoring Overview
11:15 a.m.–11:45 a.m. Closed—Executive
Session
12:00 p.m.–12:45 p.m. Open—Meet with
President and Provost
12:45 p.m.–1:00 p.m. Closed—Executive
Session
1:00 p.m.–3:00 p.m. Open—ReA3,
Astrophysics, GRETINA, MoNA Decay
Studies, BECOLA, and LEBIT
3:00 p.m.–3:40 p.m. Open—Meet with
Students and Postdocs
3:40 p.m.–5:00 p.m. Open—Tour
5:00 p.m.–6:00 p.m. Closed—Executive
Session
June 19, 2013
8:30 a.m.–1:00 p.m. Closed—Executive
Session and Report Writing
Reason for Closing: The work being
reviewed includes information of a
proprietary or confidential nature, including
technical information; financial data, such as
salaries; and personal information
concerning individuals associated with the
proposals. These matters are exempt under
(4) and (6) of 5 U.S.C. 552b(c), the
Government in the Sunshine Act.
Dated: May 15, 2013.
Susanne Bolton,
Committee Management Officer.
[FR Doc. 2013–11996 Filed 5–20–13; 8:45 am]
BILLING CODE 7555–01–P
Sunshine Act Meeting
TKELLEY on DSK3SPTVN1PROD with NOTICES
9:30 a.m., Tuesday, June
4, 2013
PLACE: NTSB Conference Center, 429
L’Enfant Plaza SW., Washington, DC
20594.
STATUS: The one item is open to the
public.
MATTERS TO BE CONSIDERED:
8492 Safety Study—Characteristics of
Single-Unit Truck Accidents
Resulting in Injuries and Deaths
News Media Contact: Telephone:
(202) 314–6100.
The press and public may enter the
NTSB Conference Center one hour prior
to the meeting for set up and seating.
VerDate Mar<15>2010
17:07 May 20, 2013
Dated: Friday, May 17, 2013.
Candi R. Bing,
Federal Register Liaison Officer.
[FR Doc. 2013–12194 Filed 5–17–13; 4:15 pm]
BILLING CODE 7533–01–P
NUCLEAR REGULATORY
COMMISSION
Atomic Safety and Licensing Board
[Docket No. 52–033–COL; ASLBP No.
09–880–05–COL–BD01]
Before Administrative Judges: Ronald
M. Spritzer, Chairman, Dr. Anthony J.
Baratta, Dr. Randall J. Charbeneau; In
the Matter of Detroit Edison Company
(Fermi Nuclear Power Plant, Unit 3);
Notice of Hearing (Notice of
Evidentiary Hearing and Opportunity
To Provide Oral and Written Limited
Appearance Statements)
May 15, 2013.
NATIONAL TRANSPORTATION
SAFETY BOARD
TIME AND DATE:
Individuals requesting reasonable
accommodations should contact
Rochelle Hall at (202) 314–6305 or by
email at Rochelle.Hall@ntsb.gov by
Friday, May 31, 2013.
The public may view the meeting via
a live or archived webcast by accessing
a link under ‘‘News & Events’’ on the
NTSB home page at www.ntsb.gov.
Schedule updates including weatherrelated cancellations are also available
at www.ntsb.gov.
FOR MORE INFORMATION CONTACT: Candi
Bing, (202) 314–6403 or by email at
bingc@ntsb.gov.
FOR MEDIA INFORMATION CONTACT: Keith
Holloway, at (202) 314–6100 or by email
at hollowk@ntsb.gov.
Jkt 229001
Pursuant to 10 CFR 2.312, the Atomic
Safety and Licensing Board hereby
provides notice that it will convene an
evidentiary session to receive testimony
and exhibits in the contested portion of
this proceeding. In addition, the Board
gives notice that, in accordance with 10
CFR 2.315(a), it will entertain oral and
written limited appearance statements
from members of the public in
connection with this proceeding.
A. Matters To Be Considered
This combined license (‘‘COL’’)
contested proceeding involves the
application of DTE Electric Company
(formerly the Detroit Edison Company)
(‘‘Applicant’’) under 10 CFR part 52,
Subpart C, to construct and to operate
a GE-Hitachi Economic Simplified
Boiling Water Reactor (‘‘ESBWR’’),
designated Unit 3, on its existing Fermi
PO 00000
Frm 00085
Fmt 4703
Sfmt 4703
29781
nuclear facility site in Monroe County,
Michigan.1
This evidentiary hearing will consider
two contentions.
i. Contention 8
Contention 8, as restated by the
Board, alleges that
the ER fails to adequately assess [Fermi Unit
3]’s impacts on the eastern fox snake and to
consider alternatives that would reduce or
eliminate those impacts.2
ii. Contention 15 (Including Subparts
A & B)
Contention 15, as restated by the
Board, alleges that
Detroit Edison (DTE) failed to comply with
Appendix B to 10 C.F.R Part 50 to
establish and implement its own quality
assurance (QA) program when it entered into
a contract with Black and Veatch (B&V) for
the conduct of safety-related combined
license (COL) application activities and to
retain overall control of safety-related
activities performed by B&V. This violation
began in March 2007 and continued through
at least February 2008. Further, DTE failed to
complete internal audits of QA programmatic
areas implemented for the Fermi 3 COL
Application, and DTE also has failed to
document trending of corrective actions to
identify recurring conditions adverse to
quality since the beginning of the Fermi Unit
3 project in March 2007.
Contention 15A:
These deficiencies adversely impact the
quality of the safety related design
information in the FSAR that is based on
B&V’s tests, investigations, or other safetyrelated activities. Because the NRC may base
its licensing decision on safety-related design
information in the FSAR only if it has
reasonable assurance of the quality of that
information, it may not lawfully issue the
COL until the deficiencies have been
adequately corrected by the Applicant, or
until the Applicant demonstrates that the
deficiencies do not affect the quality of
safety-related design information in the
FSAR.
Contention 15B:
Although DTE claims that in February
2008 it adopted a QA program that conforms
to Appendix B, DTE has failed to implement
that program in the manner required to
properly oversee the safety-related design
activities of B&V. This demonstrates an
ongoing lack of commitment on the part of
DTE’s management to compliance with NRC
QA regulations. The NRC cannot support a
finding of reasonable assurance that the
plant, as built, can and will be operated
1 Letter from Jack M. Davis, DTE, to NRC, Detroit
Edison Company Submittal of a Combined License
Application for Fermi 3 (NRC Project No. 757)
(Sept. 18, 2008) (ADAMS Accession No.
ML082730763).
2 See Detroit Edison Co. (Fermi Nuclear Power
Plant, Unit 3), LBP–09–16, 70 NRC 227, 286 aff’d,
CLI–09–22, 70 NRC 932 (2009).
E:\FR\FM\21MYN1.SGM
21MYN1
Agencies
[Federal Register Volume 78, Number 98 (Tuesday, May 21, 2013)]
[Notices]
[Page 29781]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-12194]
=======================================================================
-----------------------------------------------------------------------
NATIONAL TRANSPORTATION SAFETY BOARD
Sunshine Act Meeting
TIME AND DATE: 9:30 a.m., Tuesday, June 4, 2013
PLACE: NTSB Conference Center, 429 L'Enfant Plaza SW., Washington, DC
20594.
STATUS: The one item is open to the public.
MATTERS TO BE CONSIDERED:
8492 Safety Study--Characteristics of Single-Unit Truck Accidents
Resulting in Injuries and Deaths
News Media Contact: Telephone: (202) 314-6100.
The press and public may enter the NTSB Conference Center one hour
prior to the meeting for set up and seating.
Individuals requesting reasonable accommodations should contact
Rochelle Hall at (202) 314-6305 or by email at Rochelle.Hall@ntsb.gov
by Friday, May 31, 2013.
The public may view the meeting via a live or archived webcast by
accessing a link under ``News & Events'' on the NTSB home page at
www.ntsb.gov.
Schedule updates including weather-related cancellations are also
available at www.ntsb.gov.
FOR MORE INFORMATION CONTACT: Candi Bing, (202) 314-6403 or by email
at bingc@ntsb.gov.
FOR MEDIA INFORMATION CONTACT: Keith Holloway, at (202) 314-6100 or by
email at hollowk@ntsb.gov.
Dated: Friday, May 17, 2013.
Candi R. Bing,
Federal Register Liaison Officer.
[FR Doc. 2013-12194 Filed 5-17-13; 4:15 pm]