Petitions for Modification, 3255-3261 [2010-935]
Download as PDF
pwalker on DSK8KYBLC1PROD with NOTICES
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
approved Part 48 training plans to the
District Manager for the area in which
the mine is located. The training will
include the following: (a) Training in
mining methods and operating
procedures that will protect the cable
against damage; (b) training in proper
procedures for examining the trailing
cables to ensure the cables are in safe
operating condition; (c) training in
hazards of setting the instantaneous
circuit breakers too high to adequately
protect the trailing cable(s); and (d)
training in how to verify the circuit
interrupting device(s) protecting the
trailing cable(s) are properly set and
maintained. The petitioner further states
that the procedures of 30 CFR 48.3 for
approval of proposed revisions to
already approved training plans will
apply. The petitioner asserts that the
proposed alternative method will at all
times guarantee no less than the same
measure of protection to all miners at
Owlco Energy, LLC provided by the
existing standard.
Docket Number: M–2009–062–C.
Petitioner: American Energy
Corporation, 43521 Mayhugh Hill Road,
Twp. Hwy. 88, Beallsville, Ohio 43716.
Mine: Century Mine, MSHA I.D. No.
33–01070, located in Monroe County,
Ohio.
Regulation Affected: 30 CFR 75.503
(Permissible electric face equipment;
maintenance) and 30 CFR 18.35
(Portable trailing cables and cords).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the maximum length
of trailing cables for supplying power to
permissible equipment used in
continuous mining sections to be
increased. The petitioner states that: (1)
This petition will apply only to trailing
cables supplying three-phase, 480-volt
A.C. power to roof bolters; (2) the
maximum length of the 480-volt A.C.
trailing cables supplying power to roof
bolters will be 850 feet. The 480-volt
trailing cables for roof bolters will no be
smaller than #2 American Wire Gauge
(AWG); (3) all circuit breakers used to
protect #2 AWG trailing cables
exceeding 700 feet in length will have
instantaneous trip units calibrated to
trip at 700 amperes. The trip setting of
these circuit breakers will be sealed or
locked, and these circuit breakers will
have permanent, legible labels. Each
label will identify the circuit breakers as
being suitable for protecting No. 2 AWG
cables. The label will be maintained
legible; (4) replacement instantaneous
trip units, used to protect No. 2 AWG
trailing cables, will be calibrated to trip
at 700 amperes and this setting will be
sealed or locked; (5) all components that
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
provide short-circuit protection will
have a sufficient interruption rating in
accordance with the maximum
calculated fault currents available; (6)
during each production day, persons
designated by the mine operator will
visually examine the trailing cables to
ensure that the cables are in safe
operating condition and that the
instantaneous settings of the specially
calibrated breakers do not have seals or
locks removed and that they do not
exceed the stipulated settings; (7) any
trailing cable that is not in safe
operating condition will be removed
from service immediately and repaired
or replaced; (8) each splice or repair in
the trailing cables will be made in a
workmanlike manner and in accordance
with the instructions of the
manufacturer of the splice or repair
materials. The splice or repair will
comply with 30 CFR §§ 75.603 and
75.604; (9) permanent warning labels
will be installed and maintained on the
cover(s) of the power center identifying
the location of each sealed short-circuit
protective device. These labels will
warn miners not to change or alter these
short-circuit settings; (10) the alternative
method will not be implemented until
designated miners have been trained to
examine the integrity of seals or locks,
verify the short-circuit settings, and
properly examine trailing cables for
defects and damage; and (11) within 60
days after this petition is granted,
proposed revisions for their approved
30 CFR Part 48 training plans will be
submitted to the District Manager for the
area in which the mine is located. The
training plan will include: (a) Training
in the mining methods and operating
procedures for protecting the trailing
cables against damage; (b) training in
proper procedures for examining the
trailing cables to ensure the cables are
in safe operating condition; (c) training
in hazards of setting short-circuit
interrupting device(s) too high to
adequately protect the trailing cable(s);
and (d) training in how to verify that the
circuit interrupting device(s) protecting
the trailing cable(s) are properly set and
maintained. The petitioner further states
that the procedures of 30 CFR 48.3 for
approval of proposed revisions to
already approved training plans will
apply. The petitioner asserts that the
alternative method will at all times
guarantee no less than the same measure
of protection afforded to all miners at
the Century Mine as would be provided
by the existing standard.
Docket Number: M–2009–063–C.
Petitioner: Prairie State Generating
Company, LLC, 4274 County Highway
12, Marissa, Illinois 62257.
PO 00000
Frm 00063
Fmt 4703
Sfmt 4703
3255
Mine: Lively Grove Mine, MSHA I.D.
No. 11–03193, located in Washington
County, Illinois.
Regulation Affected: 30 CFR
75.1909(b)(6) (Non-permissible dieselpowered equipment; design and
performance requirements).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the Getman Road
Builder, Serial Number 460–002 to be
operated as it was originally designed,
without front brakes. The petitioner
states that: (1) The rule does not address
equipment with more than four (4)
wheels, specifically the Getman, Model
RDG–1504S Road Builder, with six (6)
wheels; (2) the machine has dual brake
systems on the four (4) rear wheels, and
is designed to prevent loss of braking
due to a single component failure. The
petitioner proposes to: (1) Limit the
speed of the machine to 10 miles per
hour (MPH) by permanently blocking
out any gear that would provide higher
speed or use transmission and
differential ratios that would limit the
maximum speed to 10 MPH; (2) provide
training for the operators to recognize
appropriate speeds for different road
conditions and slopes; and (3) provide
training for the operators to lower the
grader blade to provide additional
stopping capability. The petitioner
asserts that the safety of the miners will
not be compromised if the machines are
operated as described in this petition.
Dated: January 14, 2010.
Patricia W. Silvey,
Director, Office of Standards, Regulations and
Variances.
[FR Doc. 2010–936 Filed 1–19–10; 8:45 am]
BILLING CODE 4510–43–P
DEPARTMENT OF LABOR
Mine Safety and Health Administration
Petitions for Modification
AGENCY: Mine Safety and Health
Administration, Labor.
ACTION: Notice of petitions for
modification of existing mandatory
safety standards.
SUMMARY: Section 101(c) of the Federal
Mine Safety and Health Act of 1977 and
30 CFR Part 44 govern the application,
processing, and disposition of petitions
for modification. This notice is a
summary of petitions for modification
filed by the parties listed below to
modify the application of existing
mandatory safety standards published
in Title 30 of the Code of Federal
Regulations.
E:\FR\FM\20JAN1.SGM
20JAN1
3256
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
pwalker on DSK8KYBLC1PROD with NOTICES
DATES: All comments on the petitions
must be received by the Office of
Standards, Regulations and Variances
on or before February 19, 2010.
ADDRESSES: You may submit your
comments, identified by ‘‘docket
number’’ on the subject line, by any of
the following methods:
1. Electronic Mail: StandardsPetitions@dol.gov.
2. Facsimile: 1–202–693–9441.
3. Regular Mail: MSHA, Office of
Standards, Regulations and Variances,
1100 Wilson Boulevard, Room 2350,
Arlington, Virginia 22209, Attention:
Patricia W. Silvey, Director, Office of
Standards, Regulations and Variances.
4. Hand-Delivery or Courier: MSHA,
Office of Standards, Regulations and
Variances, 1100 Wilson Boulevard,
Room 2350, Arlington, Virginia 22209,
Attention: Patricia W. Silvey, Director,
Office of Standards, Regulations and
Variances.
MSHA will consider only comments
postmarked by the U.S. Postal Service or
proof of delivery from another delivery
service such as UPS or Federal Express
on or before the deadline for comments.
Individuals who submit comments by
hand-delivery are required to check in
at the receptionist desk on the 21st
floor.
Individuals may inspect copies of the
petitions and comments during normal
business hours at the address listed
above.
FOR FURTHER INFORMATION CONTACT:
Barbara Barron, Office of Standards,
Regulations and Variances at 202–693–
9447 (Voice), barron.barbara@dol.gov
(E-mail), or 202–693–9441 (Telefax).
[These are not toll-free numbers].
SUPPLEMENTARY INFORMATION:
I. Background
Section 101(c) of the Federal Mine
Safety and Health Act of 1977 (Mine
Act) allows the mine operator or
representative of miners to file a
petition to modify the application of any
mandatory safety standard to a coal or
other mine if the Secretary determines
that: (1) An alternative method of
achieving the result of such standard
exists which will at all times guarantee
no less than the same measure of
protection afforded the miners of such
mine by such standard; or (2) that the
application of such standard to such
mine will result in a diminution of
safety to the miners in such mine. In
addition, the regulations at 30 CFR
44.10 and 44.11 establish the
requirements and procedures for filing
petitions for modification.
II. Petitions for Modification
Docket Number: M–2009–049–C.
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
Petitioner: INR–WV Operating, LLC,
100 Market Street, Suite A, Man, West
Virginia 25635.
Mine: North Fork Coal Refuse
Disposal Facility—WV04–02140–01,
MSHA I.D. No. 46–02140, located in
Logan County, West Virginia.
Regulation Affected: 30 CFR 75.214(a)
(Refuse piles; general).
Modification Request: The petitioner
requests a modification of the existing
standard to permit existing mine
openings to be covered during
construction of the North Fork Coal
Refuse Disposal Facility. The petitioner
states that: (1) There are 18 mine
openings within the limits of the North
Fork Coal Refuse Facility; (2) the
openings are associated with the Buffalo
Mining Company’s No. 8-C Mine in the
Upper Winifrede coal seam and the TriEnergy Resources, Inc., No. 3 Mine and
Hart-Hat Coal Company’s No. 3 Mine in
the Buffalo Creek seam; (3) all of the
mines are abandoned; and (4) only a few
of the openings are currently exposed.
The petitioner further states that: (1) All
mine openings will be exposed and
sealed and underdrains installed at the
lowest elevation opening; (2) the mine
openings will be backfilled with earthen
material that will extend approximately
25 feet into the mine and at least 4 feet
in all directions beyond the limits of the
opening; (3) any exposed coal seam
along the mine bench will also be
covered with soil at least 4 feet above
the seam; (4) one 12-inch, SDR–11 high
density polyethylene pipe will be
placed at the mine opening with the
lowest elevation; (5) a rock underdrain,
consisting of 3-inch to 9-inch diameter
rock cobbles wrapped with filter fabric
will be installed to convey potential
flow from the pipe to the main rock
underdrain or to a groin ditch, and (6)
since the existing mines are abandoned,
the proposed plan will provide the same
measure of protection for the miners as
given to them by the standard.
Docket Number: M–2009–050–C.
Petitioner: Wolf Run Mining
Company, 300 Corporate Centre Drive,
Scott Depot, West Virginia 25560.
Mine: Sentinel Mine, MSHA I.D. No.
46–04168, located in Barbour County,
West Virginia.
Regulation Affected: 30 CFR 75.1700
(Oil and gas wells).
Modification Request: The petitioner
requests to be permitted to continue
mining through the vertical boreholes
and horizontal legs and branches
(laterals) of CBM wells that penetrate
the coalbed it is mining. The petitioner
states that one of the following
method(s) will be implemented to
protect against hazards from such wells
PO 00000
Frm 00064
Fmt 4703
Sfmt 4703
to the miners in the mine while mining
through CBM wells with horizontal
branches in coal seams: (1) The process
outlined will be executed under the
direction of a certified and qualified
person. Only those personnel directly
associated with the mine-through
process will be present in the heading
which is to encounter the borehole
during the initial mine intersection of
such borehole; and (2) upon
approaching a fifty-foot (50′) radius from
the nearest portion of an in-seam
borehole through the process of
through-mining an in-seam borehole—
initial mine-through and/or subsequent
through-mining of another segment of
the same borehole (excluding
subsequent mining of a continuous
section of the same borehole). The
petitioner proposes to: (1) Install
vacuum pump(s) or a compressor at the
wellhead, capable of maintaining a
vacuum, which is lower than the mine
operating pressure in the working faces,
to the farthest reaches of the associated
boreholes; (2) equip the well with
continuous flow, pressure and oxygen
monitoring equipment. A flame
arresting device will be installed on the
surface equipment of the well as close
as practicable to the outlet connection of
the vertical wellhead component. The
producing well system will be equipped
with an automatic flare stack designed
to fall open to the atmosphere in case of
compressor shutdown, high pressure, or
high oxygen content; (3) configure
telemetry equipment to provide
automatic warning to both the mine
operator and well operator should the
vacuum system shut down or lose
vacuum force. The warning system will
be capable of notification by telephone
and/or fax to both organizations
simultaneously. Warning alarms will be
monitored twenty-four (24) hours per
day, seven (7) days per week. Personnel
for both organizations will be trained
and simulated drills will be performed
to ensure emergency preparedness.
Once mining is within twenty-four (24)
hours of intersecting the borehole,
qualified personnel will be stationed
continuously at the well site until the
mine-through has been achieved. If
communications become unavailable or
inadequate during such period, mining
will cease until suitable
communications are reestablished; (4)
ensure that the well liquid level is
maintained below the lower coal seam
junction; (5) notify MSHA Morgantown
District Manager, MSHA Bridgeport
Field Office, and appropriate state
agencies at least twenty-four (24) hours
prior to the shift on which the minethrough is projected to occur; (6)
E:\FR\FM\20JAN1.SGM
20JAN1
pwalker on DSK8KYBLC1PROD with NOTICES
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
position firefighting equipment,
including two 20 pound fire
extinguishers, 240 pounds of rock dust,
and a fire hose long enough to reach the
face having the capability of delivering
a minimum of 50 gallons per minute of
water at a nozzle pressure of 50 pounds
per square inch; (7) assure that no less
than the volume of air prescribed in the
approved face ventilation plan is
delivered to the face of the heading
which will encounter the borehole; (8)
calibrate the onboard methane monitor
on the applicable continuous miner at
the end of the last production shift prior
to the projected mine-through; (9)
reduce the interval for methane readings
from 20 minutes to 10 minutes as
mining progresses through the minethrough procedure; (10) de-energize face
equipment and inspect the area as soon
as the borehole is breached, including
methane readings at the face, behind the
line curtain, and in the immediate
return. If mine air flows into the lateral
as expected, or if gas inflow is
acceptably low, proceed with mining
only to the extent that a clean face has
been prepared for roof-bolting and
borehole plugging. If gas inflow from the
well is unacceptably high (1.0%
methane by volume, or higher, as
measured at least twelve inches from
the roof, rib, face, and floor), take
appropriate action on the section and
immediately, from under supported
roof, install a cup type packer device
with a minimum of 20 feet of pipe. Load
the hole with water to ensure inflow is
controlled. Monitor liquid level in case
of leakage and refill liquid as required;
and (11) take a methane reading at least
once every 10 minutes, using a properly
calibrated hand-held methane detector,
while bolting and cleaning up
(scooping) the face for the sealing
operation, and heavily rock dust the
affected face and entry. The petitioner
states that MSHA personnel may
interrupt or halt the mining-through
operation when it is necessary for the
safety of the miners. Persons may
review a complete list of procedures for
this petition at the MSHA address listed
in this notice. The petitioner asserts that
the proposed alternative method will at
all times guarantee no less than the
same measure of protection at the
Sentinel Mine as would be afforded by
the existing standard.
Docket Number: M–2009–051–C.
Petitioner: Rockhouse Creek
Development, LLC, 210 Larry Joe
Harless Drive, P.O. Box 1389, Gilbert,
West Virginia 25621.
Mine: No. 3–A Mine, MSHA I.D. No.
46–09279, located in Mingo County,
West Virginia.
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
Regulation Affected: 30 CFR 75.11011(b) (Deluge-type water spray systems).
Modification Request: The petitioner
requests a modification of the existing
standard to allow Rockhouse Creek
Development (RCD) to continue its
weekly inspections and functional
testing of its complete deluge-type water
spray system, and to remove blow-off
dust covers from the nozzles. The
petitioner states that: (1) Sections
75.1101–1 through 75.1101–4 set forth
requirements regarding deluge-type
water spray systems and among those
requirements there is no mandate to
inspect and functional-test such
systems. Nevertheless, RCD conducts a
weekly inspection and functional-tests
of its complete deluge-type spray
system. The system consists of an
average of thirty (30) sprays along each
of approximately ten (10) primary beltconveyor drives and an average of sixty
(60) sprays along each of eight (8)
secondary drives; and (2) Currently RCD
provides blow-off dust covers for each
nozzle as required in 75.1101–1. In view
of the frequent inspections and
functional testing of the system, the dust
covers are not necessary because the
nozzles can be maintained in an
unclogged condition through weekly
use. Further, it is burdensome to recap
the large number of covers weekly after
each inspection and functional test. The
petitioner asserts that the proposed
alternative method would at all times
guarantee no less than the same measure
of protection afforded the miners
employed at Rockhouse Creek
Development by the existing standard.
Docket Number: M–2009–052–C.
Petitioner: ICG Beckley, LLC, 300
Corporate Centre Drive, Scott Depot,
West Virginia 25560.
Mine: Beckley Pocahontas Mine,
MSHA I.D. No. 46–05252, located in
Raleigh County, West Virginia.
Regulation Affected: 30 CFR 75.1700
(Oil and gas wells).
Modification Request: The petitioner
requests a modification of the existing
standard to be permitted to continue
mining through the vertical boreholes
and horizontal legs and branches
(laterals) of coalbed methane (CBM)
wells that penetrate the coalbed it is
mining. Intact Coal Bed Methane
Borehole (Surface Articulated/Drilled)
(CBM) Mine Through Plans. One of the
following method(s) will be
implemented to protect against hazards
from such wells to the miners in the
mine while mining through CBM wells
with horizontal branches in coal seams:
Option A: Water plug under pressure:
(1) The CBM well will be infused with
water prior to the underground mining
PO 00000
Frm 00065
Fmt 4703
Sfmt 4703
3257
operations breaching the CBM well. A
positive pressure will be maintained on
the CBM well in an effort to infuse the
coal around the CBM hole with water,
as well; (2) the CBM well system will be
equipped with a flame arrestor and
sufficient lightning protection; (3)
mining will be completed in accordance
with the underground mine-through
procedures as listed in the plan; (4) legs/
laterals that are opened after mining
will be evaluated to determine the
quantity of methane being produced in
order to determine if the lateral will
have to be plugged or simply ventilated;
(5) if a plug is required, it will be
installed in accordance with the
contingency plans as listed; (6)
typically, open legs/laterals will be
breached multiple times during mining.
The segmented hole(s) will be ventilated
or filled with water each time it is
breached. The larger or outby portions
of the borehole/degas hole will be
pressurized with water. Option B:
Maintain Negative (Vacuum) Pressure
on Degas Hole: (1) The CBM well will
have a vacuum pump or compressor
system setup at the wellhead that will
have the capability of maintaining a
sufficient vacuum pressure on the entire
CBM borehole and provide a pressure
that is lower than the mine operating
pressure at any intersection point; (2)
the CBM well will be set up with a 24
hour monitoring system that will
immediately notify the mine operator of
any reductions or losses in vacuum
pressure; (3) the well system will be
equipped with a flame arrestor and
sufficient lightning protection. An
automatic vent and oxygen sensor
system will be installed and maintained
such that when oxygen from the
underground mine/pipe system is
detected, the vent will open and vent
the methane to the atmosphere; (4) the
CBM gas well on the surface will be
pressurized and a negative (vacuum)
pressure will be maintained on the legs/
laterals of the system; (5) mining will be
completed in accordance with the
underground mining procedures listed
in this plan; (6) when a degas hole is
intercepted, mine air will be pulled into
the open borehole and will ventilate the
outby portion of the degas borehole
immediately; (7) legs/laterals on the
inby portion of the hole that are not
being pulled to the surface will be
evaluated to determine the quantity of
methane being produced in order to
determine if the lateral will have to be
plugged or simply ventilate; (8) if a plug
is required it will be installed in
accordance with the contingency plan
as listed; (9) typically, open legs/laterals
will be breached multiple times during
E:\FR\FM\20JAN1.SGM
20JAN1
pwalker on DSK8KYBLC1PROD with NOTICES
3258
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
mining. The segmented hole(s) will be
ventilated by mine air or by the pressure
from the vacuum pump on the surface;
(10) short segments of CBM legs/laterals
(100 feet or less) will be ventilated and
air forced through the segment to sweep
away any methane in that segment.
After the hole has been ventilated, it
will be allowed to remain open and be
ventilated with the remainder of the
mine. Option C: Plugging the Coalbed
Methane Well (CBM) from the Surface:
(1) Procedures for cleaning out and
preparing the CBM well for plugging: (a)
Make a diligent and reasonable effort to
remove all metal casing from the CBM/
well borehole unless it has been grouted
in place. Metal casing that has been
grouted in place will be perforated or
ripped at intervals to allow for any
expanding cement or slurry mixtures to
infiltrate the annulus between the
casing and the borehole wall; (b) a
diligent and reasonable effort will be
made to reenter the CBM/well borehole
to the original total measured distance.
If the total measured distance cannot be
reached, the borehole will be reentered
to the maximum extent practicable.
Similarly, any known laterals will be
reentered to the maximum extent
practicable; (c) a directional deviation
survey completed during the drilling of
the borehole/well or during the cleanout
will be utilized to determine the relative
location of the coal seam and of the
location of the boreholes within the coal
seam; (2) Plugging Coalbed Methane
(CBM) wells: (a) Once the borehole has
been reentered to the maximum extent
practicable, expanding grout will be
pumped into the CBM. Where laterals
are encountered, a diligent and
reasonable effort will be made to reenter
each known lateral and grout to the
maximum extent practicable. Upon
completion of grouting each lateral, the
inby portion of the main trunk line of
the CBM will be filled with expanding
grout to the maximum extent
practicable, and will be repeated until
the CBM is grouted/filled to the surface;
(b) the MSHA District Manager will
determine what alternate materials other
than grout are suitable for use in sealing
the borehole; and (c) a small quantity of
steel shavings or magnetic material will
be installed at the top of the grouted
CBM borehole and utilized as a
monument locating the site; (3) If the
CBM well is located such that it may be
used as a bleeder borehole, the grout
mixture quantity will be limited to fill
only the coal seam drill hole void. In all
other circumstances, the CBM will be
filled with grout to at least fifty feet
above the upper most underground
minable coal seam. The petitioner states
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
that: (1) The operator will notify the
District Manager or his designee prior to
mining within 300 feet of any well and
when a specific plan is designated for
mining through each well. The District
Manager or his designee, the
representative of miners, and the
appropriate State agency will receive
reasonable notification prior to the
mining-through operation in order to
have an opportunity to have a
representative present; (2) the miningthrough operation will be under the
direct supervision of a certified person
in charge. Personnel will not be
permitted in the area of the miningthrough operation except those actually
engaged in the operation, company
personnel, a representative of the
miners, the MSHA representative(s) and
the representative(s) from the
appropriate State agency; (3)
underground procedures for mining
through a degas borehole will include
firefighting equipment, fire
extinguishers, rock dust and sufficient
fire hose to reach the working face to be
available near the working place where
the cut-through will take place. The
surrounding area within 20 feet of the
cut-through area will be heavily rock
dusted immediately prior to the cutthrough. Adequate roof support and
ventilation materials will be available
near the working place where the cutthrough will take place. Ventilation
quantities will be maintained at the
working face throughout the minethrough operation. Equipment will be in
compliance with permissibility
requirements and compliance will be
verified on the shift immediately prior
to the cut-through. Persons may review
a complete description of the
petitioner’s procedures for mining
through CBM wells at the MSHA
address listed in this notice. The
petitioner asserts that the proposed
alternative method will at all times
guarantee no less than the same measure
of protection at the Beckley Pocahontas
Mine as would be afforded by the
existing standard.
Docket Number: M–2009–053–C.
Petitioner: ICG Beckley, LLC, 2221
Old Eccles Road, P.O. Box 49, Eccles,
West Virginia 25836.
Mine: Beckley Pocahontas Mine,
MSHA I.D. No. 46–05252, located in
Raleigh County, West Virginia.
Regulation Affected: 30 CFR
75.1909(b)(6) (Non-permissible dieselpowered equipment; design and
performance requirements).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the Getman
Roadbuilder, Serial Number 460–001 to
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
be operated as it was originally
designed, without front brakes. The
petitioner states that: (1) The rule does
not address equipment with more than
four (4) wheels, specifically the Getman
Roadbuilder, Model RDG–1504S, with
six (6) wheels; (2) the machine has dual
brake systems on the four (4) rear
wheels, and is designed to prevent loss
of braking due to a single component
failure; (3) seventy-four percent (74%)
of the machines total weight is over the
four (4) rear wheels; and (4) with the
weight distribution, brakes on the rear
of the machine are sufficient to safely
stop the machine. The petitioner further
states that: (1) Training will be provided
to the grader operators to lower the
moldboard to provide additional
stopping capability in emergency
situations; and (2) training will be
provided to the grader operators to
recognize the appropriate speeds to use
on different roadway conditions, and to
limit the maximum speed to 10 miles
per hour. The petitioner asserts that the
proposed alternative method will
provide the same degree/level of safety
as the existing regulation.
Docket Number: M–2009–054–C.
Petitioner: Pinnacle Mining Company,
LLC, P.O. Box 338, Pineville, West
Virginia 24874.
Mine: Pinnacle Mine, MSHA I.D. No.
46–01816, located in Wyoming County,
West Virginia.
Regulation Affected: 30 CFR
75.507–1 (Electric equipment other than
power-connection points; outby the last
open crosscut; return air; permissibility
requirements).
Modification Request: The petitioner
requests a modification of the existing
standard to permit 2,400-volt or 4,160volt alternating current submersible
pump(s) to be installed and operated in
return and/or bleeder entries and sealed
areas in the Pinnacle Mine. The
petitioner states that the three phase
2,400-volt or 4,160-volt alternating
current electric power circuit(s) for the
pump(s) will be designed and installed
to: (a) contain either a direct or a
derived neutral, which will be grounded
through a suitable resistor at the source
transformer of power center. A
grounding circuit originating at the
grounded side of the grounding resistor
will extend along with the power
conductors and serve as the grounding
conductor for the frame of the pump(s)
and all associated electric equipment
that may be supplied power from the
circuit(s). The borehole casing will be
bonded to the system grounding
medium; and (b) contain a grounding
resistor that limits the ground-fault
current to not more than 6.5 amperes.
E:\FR\FM\20JAN1.SGM
20JAN1
pwalker on DSK8KYBLC1PROD with NOTICES
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
The grounding resistor must be rated for
the maximum fault current available
and must be insulated from ground for
a voltage equal to the phase-to-phase
voltage of the system. The petitioner
asserts that the proposed alternative
method will provide an acceptable
alternative and provide at least the same
degree of safety as the existing standard.
Docket Number: M–2009–055–C.
Petitioner: Prairie State Generating
Company, LLC, 4274 County Highway
12, Marissa, Illinois 62257.
Mine: Lively Grove Mine, MSHA I.D.
No. 11–03193, located in Washington
County, Illinois.
Regulation Affected: 30 CFR 75.503
(Permissible electric face equipment;
maintenance).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the trailing cables to
be increased to the maximum length of
950 feet for the 995 volt three-phase
alternating current continuous mining
machines and the 480-volt to 995 volt
three-phase alternating current roofbolting machines. The petitioner states
that: (1) The maximum length of the
trailing cables supplying power to threephase 995 continuous miners will be
950 feet. The maximum length of the
trailing cables supplying power to threephase 480-volt or 995-volt roof bolting
machines will be 950 feet; (2) the
trailing cables for the 995-volt
continuous mining machines will not be
smaller than No. 2 American Wire
Gauge (AWG), SHD–GC. The trailing
cables for the 480-volt or 995-volt roof
bolting machines will not be smaller
than No. 2 AWG, SHD–GC; (3) all circuit
breakers used to protect the No. 2 AWG
trailing cables exceeding 850 feet in
length will have instantaneous trip units
calibrated to trip at 1,500 amperes. The
trip setting will be sealed so that the
setting cannot be changed, and these
circuit breakers will have permanent,
legible labels. Each label will identify
the circuit breakers as being suitable for
protecting No. 2 AWG cables. The label
will be maintained legible. Replacement
instantaneous trip units used to protect
No. 2 AWG trailing cables will be
calibrated to trip at 1,500 amperes and
the setting will be sealed or locked for
trailing cables exceeding 850 feet in
length; (4) all circuit breakers used to
protect No. 2 AWG trailing cables
exceeding 700 feet in length and less
than 850 feet in length, will have
instantaneous trip units calibrated to
trip at 800 amperes. The trip setting will
be sealed to that the setting cannot be
changed, and will have permanent,
legible labels. Each label will identify
the circuit breakers as being suitable for
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
protecting No. 2 AWG cables. The label
will be maintained legible. Replacement
instantaneous trip units used to protect
No. 2 AWG trailing cables will be
calibrated to trip at 800 amperes and
this setting will be sealed or locked for
trailing cables exceeding 700 feet in
length and less than 850 feet in length;
(5) all components that provide shortcircuit protection will have a sufficient
interruption rating in accordance with
the maximum calculated fault currents
available. Short-circuit current setting
must not exceed 70 percent of the
minimum available current; (6) during
each production day, persons
designated by the mine operator will
visually examine the trailing cables to
ensure that the cables are in safe
operating condition and that the
instantaneous settings of the specially
calibrated breakers do not have seals or
locks removed and that they do not
exceed the settings stipulated in items 5
and 6; (7) permanent warning labels will
be installed and maintained on the
cover(s) of the power center identifying
the location of each sealed short-circuit
protective device; (8) any trailing cable
that is not in safe operating condition
will be removed from service
immediately and repaired or replaced;
(9) splices and repairs in trailing cables
will be made in accordance with the
instructions of the splice or repair
manufacturer and 30 CFR 75.603 and 30
CFR 75.604; (10) all miners who have
been designated to examine the integrity
of seals, verify the short-circuit settings,
and examine trailing cables for defects
will receive part 48 training in the
following: (a) The mining methods and
operating procedures that will protect
the trailing cables against damage; (b)
the proper procedures for examining the
trailing cables to ensure that they are in
safe condition; (c) the hazards if setting
the short-circuit interrupting device(s)
too high to adequately protect the
trailing cables; and (d) how to verify
that the circuit interrupting device(s)
protecting the trailing cable(s) are
properly set and maintained. The
petitioner asserts that the alternative
method will at all times guarantee no
less than the same measure of protection
afforded by the existing standard.
Docket Number: M–2009–056–C.
Petitioner: Prairie State Generating
Company, LLC, County Highway12,
Marissa, Illinois 62257.
Mine: Lively Grove Mine, MSHA I.D.
No. 11–03193, located in Washington
County, Illinois.
Regulation Affected: 30 CFR 75.1002
(Installation of electric equipment and
conductors; permissibility).
Modification Request: The petitioner
requests a modification of the existing
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
3259
standard to permit the use of 2,400-volt
continuous miners in the Lively Grove
Mine. The petitioner states that: (1) The
nominal voltage of power circuits will
not exceed 2,400 volts; (2) the nominal
voltage of the control circuits will not
exceed 120 volts; (3) the ground-fault
current will be limited by a neutral
grounding resistor to not more than 0.5
ampere; (4) high-voltage circuits will be
protected against short-circuits,
overload, ground-faults, and
undervoltage by a circuit interrupting
device of adequate interrupting
capacity; (5) the high-voltage cable for
the 2,400-volt continuous miner circuit
will be provided with instantaneous
ground-fault protection set at not more
than 0.125 ampere; (6) the neutral
grounding resistor will be provided with
backup ground-fault protection that will
de-energize the primary of the
transformer if a ground fault occurs with
the neutral grounding resistor open; (7)
each ground-fault current device will be
provided with a test circuit that will
inject a current of 50 percent or less of
the current rating of the grounding
resistor and cause each corresponding
circuit-interrupting device to open. The
test circuit will not subject the
equipment to an actual phase-to-groundfault condition. The petitioner further
states that within 60-days after the
Proposed Decision and Order become
final, the petitioner will submit
provisions for its approved part 48
training plan to the District Manger. The
proposed revisions will include, but not
limited to, task training, hazard training,
and specialized training for qualified
persons under 30 CFR 75.153, and
annual refresher training. In addition,
the following will be adopted: (a) Safety
precautions for the handling and use of
high-voltage trailing cables, for all
mines assigned to work in the area of
the high-voltage trailing cable; and (b)
specialized training for qualified
electricians that will be required to
repair, maintain and/or trouble-shoot
the high-voltage trailing cable or
equipment. This training will focus on
the requirements of this modification.
Persons may review a complete
description of the petitioner’s proposed
alternative method at the MSHA address
listed in this notice. The petitioner
asserts that the alternative method will
at all times guarantee no less than the
same measure of protection afforded by
the existing standard.
Docket Number: M–2009–057–C.
Petitioner: Prairie State Generating
Company, LLC, 4274 County Highway
12, Marissa, Illinois 62257.
E:\FR\FM\20JAN1.SGM
20JAN1
pwalker on DSK8KYBLC1PROD with NOTICES
3260
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
Mine: Lively Grove Mine, MSHA I.D.
No. 11–03193, located in Washington
County, Illinois.
Regulation Affected: 30 CFR 75.1700
(Oil and gas wells).
Modification Request: The petitioner
requests a modification of the existing
standard to permit an alternative
method of plugging and mining through
oil and gas wells. The petitioner states
that: (1) Lively Grove Mine will be
mining the Herrin #6 coal and will
experience mining around or through
oil and gas wells; (2) copies of the
plugging affidavits have been acquired
from the Illinois State Geological Survey
in the reserve area; and (3) before the
well is approached, a drawing will be
submitted to the District Office for
approval to either mine around the well
or through the well if necessary. The
petitioner also states that the following
procedures will be utilized when
plugging oil and gas wells: (1) Cleaning
out and preparing oil and gas wells: (i)
A diligent effort will be made to clean
the borehole to the original total depth.
If this depth cannot be reached, the
borehole will be cleaned out to a depth
which would permit the placement of at
least 200 feet of expanding cement
below the base of the lowest minable
coalbed; (ii) when clearing the borehole,
a diligent effort will be made to remove
all the casing in the borehole. If it is not
possible to remove all casing, the casing
which remains will be perforated or
ripped at intervals spaced close enough
to permit expanding cement slurry to
infiltrate the annulus between the
casing and the borehole wall for
distance of at least 200 feet below the
base of the lowest minable coalbed; (iii)
if the cleaned out borehole produces
gas, a mechanical bridge plug will be
place in the borehole in a competent
stratum at least 200 feet below the base
of the lowest minable coalbed, but
above the top of the uppermost
hydrocarbon producing stratum. If it is
not possible to set a mechanical bridge
plug, a substantial brush plug may be
used in place of the mechanical bridge
plug; (iv) a suite of logs will be made
consisting of a caliper survey directional
deviation survey, and log(s) suitable for
determining the top and bottom of the
lowest minable coalbed and potential
hydrocarbon producing strata and the
location for the bridge plug. An electric
well log to determine hole diameter will
be conducted to accurately predict the
quantity of cement required to plug the
hole from 200 feet below the base of the
lowest minable coal seam to the surface;
(v) if the uppermost hydrocarbonproducing stratum is within 200 feet of
the base of the lowest minable coalbed,
properly placed mechanical bridge
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
plugs or a suitable brush plug described
in subparagraph (a)(3) will be used to
isolate the hydrocarbon producing
stratum from the expanding cement
plug. Nevertheless, a minimum of 200
feet of expanding cement will be place
below the lowest minable coalbed; and
(vi) the wellbore will be completely
filled and circulated with a gel that
inhibits any flow of gas, supports the
walls of the borehole, and increases the
density of the expanding cement. This
gel will be pumped through an openend tubing run to a point approximately
20 feet above the bottom of the cleaned
out area of the borehole bridge plug. (2)
Plugging oil and gas wells to the surface.
Procedures to be utilized when plugging
gas or oil wells to the surface are as
follows: (i) A cement plug will be set in
the wellbore by pumping an expanding
cement slurry down the tubing to
displace the gel and fill the borehole to
the surface. As an alternative, the
cement slurry may be pumped down the
tubing so that the borehole is filled with
Portland cement or a Portland cementfly ash mixture from a point
approximately 100 feet above the top of
the lowest minable coalbed to the
surface with an expanding cement plug
extending from at least 200 feet below
the lowest minable coalbed to the
bottom of the Portland cement. There
will be at least 200 feet of expanding
cement below the base of the lowest
minable coalbed, and (ii) a surface
casing, small quantity of steel turnings,
or other small magnetic particles, will
be embedded in the top of the cement
near the surface to serve as a permanent
magnetic monument of the borehole. As
an alternative, a steel rod may be driven
into the ground next to the borehole. (3)
Plugging oil or gas wells using the vent
pipe method. Procedures to be utilized
when using the vent pipe method for
plugging gas or oil wells are as follows:
(i) A 41⁄2 inch or larger vent pipe will
be run into the wellbore to a depth of
100 feet below the lowest minable
coalbed and welded to a smaller
diameter pile, if desired, which will
extend to a point approximately 20 feet
above the bottom of the cleaned out area
of the borehole or bridge plug; (ii) a
cement plug will be set in the wellbore
by pumping an expanding cement
slurry, Portland cement, or a Portland
cement-fly ash mixture down the tubing
to displace gel so that the borehole is
filled with cement. The borehole and
the vent pipe will be filled with
expanding cement for minimum of 200
feet below the base of the lowest
minable coalbed. The top of the
expanding cement will extend to a point
approximately 100 feet above the top of
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
the lowest minable coalbed; (iii) all
fluid will evacuated from the vent pipe
to facilitate testing for gases. During the
evacuation of fluid, the expanding
cement will not be disturbed; and (vi)
the top of the vent pipe will be
protected to prevent liquids or solids
from entering the wellbore, but permit
ready access to the full internal
diameter of the vent pipe when
necessary. (4) Plugging oil or gas wells
for use as degasification boreholes.
Procedures to be utilized when plugging
gas or oil wells for subsequent use of
degasification boreholes are as follows:
(i) A cement plug will be set in the
wellbore by pumping an expanding
cement slurry down the tubing to
displace the gel and provide at least 200
feet of expanding cement below the
lowest minable coalbed; (ii) to facilitate
methane drainage, degasification casing
of suitable diameter, slotted or
perforated throughout its lower 150 to
200 feet will be set in the borehole to
a point 10 to 30 feet above the top of the
expanding cement; (iii) the annulus
between the degasification casing and
the borehole wall will be cemented from
a point immediately above the slots or
perforations to the surface; (iv) the
degasification casing will be cleaned out
for its total length; and (v) the top of the
degasification casing will be fitted with
a wellhead equipped as required by the
District Manager. Such equipment may
include check valves, shut-in valves,
sampling port, flame arrester
equipment, and security fencing. The
petitioner further states that when
mining through a plugged oil or gas
well, the District Manager or designee
will be notified prior to mining within
300 feet of the well and when a specific
plan is developed for mining through
each well. Within 60 days after this
Proposed Decision and Order becomes
final, the petitioner will submit
proposed revisions for its approved 30
CFR Part 48 training plan to the District
Manager. These proposed revisions will
include initial and refresher training
regarding compliance with the terms
and conditions stated in the Proposed
Decision and Order. Persons may review
a complete description of the
petitioner’s procedures for
implementing the proposed alternative
method at the MSHA address listed in
this notice. The petitioner asserts that
the alternative method will at all times
guarantee no less than the same measure
of protection afforded by the existing
standard.
Docket Number: M–2009–058–C.
Petitioner: Perry County Coal
Corporation, 1845 S KY Hwy 15,
Hazard, Kentucky 41701.
E:\FR\FM\20JAN1.SGM
20JAN1
pwalker on DSK8KYBLC1PROD with NOTICES
Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices
Mine: E4–1 Mine, MSHA I.D. No. 15–
18565, located in Perry County,
Kentucky.
Regulation Affected: 30 CFR 75.503
(Permissible electric face equipment;
maintenance).
Modification Request: The petitioner
requests a modification of the existing
standard to permit the E4–1 Mine to
increase the maximum length of trailing
cables supplying power to permissible
pumps in the mines. The petitioner
states that: (1) This petition will apply
only to trailing cables supplying threephase, 480-volt power for permissible
pumps; (2) the maximum length of the
480-volt power for permissible pump
will be 4,000 feet; (3) all circuit breakers
used to protect trailing cables exceeding
the pump approval length or Table 9 of
Part 18 will have an instantaneous trip
unit calibrated to trip at 75 percent of
phase to phase short-circuit current. The
trip setting of these circuit breakers will
be sealed or locked, and these circuit
breakers will have permanent legible
labels. Each label will identify the
circuit breaker as being suitable for
protecting the trailing cables, and the
labels will be maintained legible. In
instances where a 75 percent
instantaneous set point will not allow a
pump to start due to motor inrush, a
thermal magnetic breaker will be
furnished. The thermal rating of the
circuit breaker will be no greater than 75
percent of the available short-circuit
current and the instantaneous setting
will be adjusted one setting above the
motor inrush trip point. This setting
will also be sealed or locked; (4)
replacement instantaneous trip units
used to protect pump trailing cables
exceeding the length of Table 9 of Part
18 will be calibrated to trip at 75
percent of the available phase to phase
short circuit current and this setting will
be sealed or locked; (5) permanent
warning labels will be installed and
maintained on the cover(s) of the power
center to identify the location of each
sealed or locked short-circuit protection
device. These labels will warn miners
not to change or alter the short circuit
settings; (6) the pump circuits attached
to this petition have greater lengths than
approved or in Table 9. All future pump
installation with excessive cable lengths
will have a short-circuit survey
conducted and items 1–5 will be
implemented. A copy of each pump’s
short-circuit survey will be available at
the mine site for inspection; and (7) the
petitioner’s alternative method will not
be implemented until designated miners
have been trained to examine the
integrity of the seals or locks, verify the
short-circuit settings, and perform
proper procedures for examining
VerDate Nov<24>2008
16:06 Jan 19, 2010
Jkt 220001
trailing cables for defects and damage.
The petitioner further states that within
60 days after the Proposed Decision and
Order becomes final, proposed revisions
for approved 30 CFR Part 48 training
plan at any of the listed mines will be
submitted to the Coal Mine Safety and
Health District Manager. The training
plan will include: (a) Training in the
mining methods and operating
procedures for protecting the trailing
cables against damage; (b) training in
proper procedures for examining the
trailing cables to ensure they are in safe
operating condition; (c) training in
hazards of setting the instantaneous
circuit breakers too high to adequately
protect the trailing cables; and (d)
training in how to verify that the circuit
interrupting device(s) protecting the
trailing cable(s) are properly set and
maintained; and (e) the procedures of 30
CFR 48.3 for approval of proposed
revisions to already approved training
plans will apply. The petitioner asserts
that the proposed alternative method
will at all times guarantee no less than
the same measure of protection to all
miners at Perry County Coal
Corporation than is provided the
existing standard.
Dated: January 14, 2010.
Patricia W. Silvey,
Director, Office of Standards, Regulations and
Variances.
[FR Doc. 2010–935 Filed 1–19–10; 8:45 am]
BILLING CODE 4510–43–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 40–9075; NRC–2009–0575]
Powertech (USA) Inc.; Dewey-Burdock
Project; New Source Material License
Application; Notice of Intent To
Prepare a Supplemental Environmental
Impact Statement
AGENCY: U.S. Nuclear Regulatory
Commission.
ACTION: Notice of Intent (NOI).
SUMMARY: By letter dated August 10,
2009, Powertech (USA) (Powertech)
submitted to the U.S. Nuclear
Regulatory Commission (NRC) an
application for a new source material
license. The requested license, or the
proposed action, would authorize the
construction, operation, and
decommissioning of Powertech’s
proposed in-situ uranium recovery (ISR,
also known as in-situ leach) facilities,
and would require restoration of the
aquifer from which the uranium would
be extracted. A notice of receipt and
availability of the license application,
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
3261
including the Environmental Report
(ER), and opportunity to request a
hearing was published in the Federal
Register on January 05, 2010 (75 FR
467–471).
The purpose of this notice of intent is
to inform the public that the NRC will
be preparing a site-specific
Supplemental Environmental Impact
Statement (SEIS) regarding the proposed
action. The SEIS will tier off of the
Generic Environmental Impact
Statement for In-Situ Leach Uranium
Milling Facilities (ISR GEIS) that was
published in 2009. As outlined in 36
CFR 800.8, ‘‘Coordination with the
National Environmental Policy Act,’’ the
NRC plans to use the environmental
review process set forth in its 10 CFR
Part 51 regulations to coordinate
compliance with Section 106 of the
National Historic Preservation Act.
FOR FURTHER INFORMATION CONTACT: For
general information on the NRC
National Environmental Policy Act
(NEPA) process or the environmental
review process related to the DeweyBurdock Uranium Project application,
please contact the NRC Environmental
Project Manager, Haimanot Yilma, at
(301) 415–8029 or
haimanot.yilma@nrc.gov.
Information and documents
associated with the Dewey-Burdock
Uranium Project, including the license
application, are available for public
review through our electronic reading
room: https://www.nrc.gov/reading-rm/
adams.html and on the NRC’s DeweyBurdock Uranium Project web page:
https://www.nrc.gov/info-finder/
materials/uranium/apps-in-review/
dewey-burdock-new-app-review.html.
Documents may also be obtained from
NRC’s Public Document Room at the
U.S. Nuclear Regulatory Commission
Headquarters, 11555 Rockville Pike
(first floor), Rockville, Maryland.
SUPPLEMENTARY INFORMATION:
1.0
Background
Powertech submitted its application
for a 10 CFR Part 40 license by letter
dated August 10, 2009. A notice of
receipt and availability of the license
application, including the ER, and
opportunity to request a hearing was
published in the Federal Register on
January 5, 2010 (75 FR 467471).
The NRC is required by 10 CFR
51.20(b)(8) to prepare an environmental
impact statement (EIS) or supplement to
an EIS for the issuance of a license to
possess and use source material for
uranium milling. The ISR GEIS and the
site-specific SEIS will meet this
regulatory requirement. The purpose of
this NOI is to inform the public that the
E:\FR\FM\20JAN1.SGM
20JAN1
Agencies
[Federal Register Volume 75, Number 12 (Wednesday, January 20, 2010)]
[Notices]
[Pages 3255-3261]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-935]
-----------------------------------------------------------------------
DEPARTMENT OF LABOR
Mine Safety and Health Administration
Petitions for Modification
AGENCY: Mine Safety and Health Administration, Labor.
ACTION: Notice of petitions for modification of existing mandatory
safety standards.
-----------------------------------------------------------------------
SUMMARY: Section 101(c) of the Federal Mine Safety and Health Act of
1977 and 30 CFR Part 44 govern the application, processing, and
disposition of petitions for modification. This notice is a summary of
petitions for modification filed by the parties listed below to modify
the application of existing mandatory safety standards published in
Title 30 of the Code of Federal Regulations.
[[Page 3256]]
DATES: All comments on the petitions must be received by the Office of
Standards, Regulations and Variances on or before February 19, 2010.
ADDRESSES: You may submit your comments, identified by ``docket
number'' on the subject line, by any of the following methods:
1. Electronic Mail: Standards-Petitions@dol.gov.
2. Facsimile: 1-202-693-9441.
3. Regular Mail: MSHA, Office of Standards, Regulations and
Variances, 1100 Wilson Boulevard, Room 2350, Arlington, Virginia 22209,
Attention: Patricia W. Silvey, Director, Office of Standards,
Regulations and Variances.
4. Hand-Delivery or Courier: MSHA, Office of Standards, Regulations
and Variances, 1100 Wilson Boulevard, Room 2350, Arlington, Virginia
22209, Attention: Patricia W. Silvey, Director, Office of Standards,
Regulations and Variances.
MSHA will consider only comments postmarked by the U.S. Postal
Service or proof of delivery from another delivery service such as UPS
or Federal Express on or before the deadline for comments. Individuals
who submit comments by hand-delivery are required to check in at the
receptionist desk on the 21st floor.
Individuals may inspect copies of the petitions and comments during
normal business hours at the address listed above.
FOR FURTHER INFORMATION CONTACT: Barbara Barron, Office of Standards,
Regulations and Variances at 202-693-9447 (Voice),
barron.barbara@dol.gov (E-mail), or 202-693-9441 (Telefax). [These are
not toll-free numbers].
SUPPLEMENTARY INFORMATION:
I. Background
Section 101(c) of the Federal Mine Safety and Health Act of 1977
(Mine Act) allows the mine operator or representative of miners to file
a petition to modify the application of any mandatory safety standard
to a coal or other mine if the Secretary determines that: (1) An
alternative method of achieving the result of such standard exists
which will at all times guarantee no less than the same measure of
protection afforded the miners of such mine by such standard; or (2)
that the application of such standard to such mine will result in a
diminution of safety to the miners in such mine. In addition, the
regulations at 30 CFR 44.10 and 44.11 establish the requirements and
procedures for filing petitions for modification.
II. Petitions for Modification
Docket Number: M-2009-049-C.
Petitioner: INR-WV Operating, LLC, 100 Market Street, Suite A, Man,
West Virginia 25635.
Mine: North Fork Coal Refuse Disposal Facility--WV04-02140-01, MSHA
I.D. No. 46-02140, located in Logan County, West Virginia.
Regulation Affected: 30 CFR 75.214(a) (Refuse piles; general).
Modification Request: The petitioner requests a modification of the
existing standard to permit existing mine openings to be covered during
construction of the North Fork Coal Refuse Disposal Facility. The
petitioner states that: (1) There are 18 mine openings within the
limits of the North Fork Coal Refuse Facility; (2) the openings are
associated with the Buffalo Mining Company's No. 8-C Mine in the Upper
Winifrede coal seam and the Tri-Energy Resources, Inc., No. 3 Mine and
Hart-Hat Coal Company's No. 3 Mine in the Buffalo Creek seam; (3) all
of the mines are abandoned; and (4) only a few of the openings are
currently exposed. The petitioner further states that: (1) All mine
openings will be exposed and sealed and underdrains installed at the
lowest elevation opening; (2) the mine openings will be backfilled with
earthen material that will extend approximately 25 feet into the mine
and at least 4 feet in all directions beyond the limits of the opening;
(3) any exposed coal seam along the mine bench will also be covered
with soil at least 4 feet above the seam; (4) one 12-inch, SDR-11 high
density polyethylene pipe will be placed at the mine opening with the
lowest elevation; (5) a rock underdrain, consisting of 3-inch to 9-inch
diameter rock cobbles wrapped with filter fabric will be installed to
convey potential flow from the pipe to the main rock underdrain or to a
groin ditch, and (6) since the existing mines are abandoned, the
proposed plan will provide the same measure of protection for the
miners as given to them by the standard.
Docket Number: M-2009-050-C.
Petitioner: Wolf Run Mining Company, 300 Corporate Centre Drive,
Scott Depot, West Virginia 25560.
Mine: Sentinel Mine, MSHA I.D. No. 46-04168, located in Barbour
County, West Virginia.
Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).
Modification Request: The petitioner requests to be permitted to
continue mining through the vertical boreholes and horizontal legs and
branches (laterals) of CBM wells that penetrate the coalbed it is
mining. The petitioner states that one of the following method(s) will
be implemented to protect against hazards from such wells to the miners
in the mine while mining through CBM wells with horizontal branches in
coal seams: (1) The process outlined will be executed under the
direction of a certified and qualified person. Only those personnel
directly associated with the mine-through process will be present in
the heading which is to encounter the borehole during the initial mine
intersection of such borehole; and (2) upon approaching a fifty-foot
(50') radius from the nearest portion of an in-seam borehole through
the process of through-mining an in-seam borehole--initial mine-through
and/or subsequent through-mining of another segment of the same
borehole (excluding subsequent mining of a continuous section of the
same borehole). The petitioner proposes to: (1) Install vacuum pump(s)
or a compressor at the wellhead, capable of maintaining a vacuum, which
is lower than the mine operating pressure in the working faces, to the
farthest reaches of the associated boreholes; (2) equip the well with
continuous flow, pressure and oxygen monitoring equipment. A flame
arresting device will be installed on the surface equipment of the well
as close as practicable to the outlet connection of the vertical
wellhead component. The producing well system will be equipped with an
automatic flare stack designed to fall open to the atmosphere in case
of compressor shutdown, high pressure, or high oxygen content; (3)
configure telemetry equipment to provide automatic warning to both the
mine operator and well operator should the vacuum system shut down or
lose vacuum force. The warning system will be capable of notification
by telephone and/or fax to both organizations simultaneously. Warning
alarms will be monitored twenty-four (24) hours per day, seven (7) days
per week. Personnel for both organizations will be trained and
simulated drills will be performed to ensure emergency preparedness.
Once mining is within twenty-four (24) hours of intersecting the
borehole, qualified personnel will be stationed continuously at the
well site until the mine-through has been achieved. If communications
become unavailable or inadequate during such period, mining will cease
until suitable communications are reestablished; (4) ensure that the
well liquid level is maintained below the lower coal seam junction; (5)
notify MSHA Morgantown District Manager, MSHA Bridgeport Field Office,
and appropriate state agencies at least twenty-four (24) hours prior to
the shift on which the mine-through is projected to occur; (6)
[[Page 3257]]
position firefighting equipment, including two 20 pound fire
extinguishers, 240 pounds of rock dust, and a fire hose long enough to
reach the face having the capability of delivering a minimum of 50
gallons per minute of water at a nozzle pressure of 50 pounds per
square inch; (7) assure that no less than the volume of air prescribed
in the approved face ventilation plan is delivered to the face of the
heading which will encounter the borehole; (8) calibrate the onboard
methane monitor on the applicable continuous miner at the end of the
last production shift prior to the projected mine-through; (9) reduce
the interval for methane readings from 20 minutes to 10 minutes as
mining progresses through the mine-through procedure; (10) de-energize
face equipment and inspect the area as soon as the borehole is
breached, including methane readings at the face, behind the line
curtain, and in the immediate return. If mine air flows into the
lateral as expected, or if gas inflow is acceptably low, proceed with
mining only to the extent that a clean face has been prepared for roof-
bolting and borehole plugging. If gas inflow from the well is
unacceptably high (1.0% methane by volume, or higher, as measured at
least twelve inches from the roof, rib, face, and floor), take
appropriate action on the section and immediately, from under supported
roof, install a cup type packer device with a minimum of 20 feet of
pipe. Load the hole with water to ensure inflow is controlled. Monitor
liquid level in case of leakage and refill liquid as required; and (11)
take a methane reading at least once every 10 minutes, using a properly
calibrated hand-held methane detector, while bolting and cleaning up
(scooping) the face for the sealing operation, and heavily rock dust
the affected face and entry. The petitioner states that MSHA personnel
may interrupt or halt the mining-through operation when it is necessary
for the safety of the miners. Persons may review a complete list of
procedures for this petition at the MSHA address listed in this notice.
The petitioner asserts that the proposed alternative method will at all
times guarantee no less than the same measure of protection at the
Sentinel Mine as would be afforded by the existing standard.
Docket Number: M-2009-051-C.
Petitioner: Rockhouse Creek Development, LLC, 210 Larry Joe Harless
Drive, P.O. Box 1389, Gilbert, West Virginia 25621.
Mine: No. 3-A Mine, MSHA I.D. No. 46-09279, located in Mingo
County, West Virginia.
Regulation Affected: 30 CFR 75.1101-1(b) (Deluge-type water spray
systems).
Modification Request: The petitioner requests a modification of the
existing standard to allow Rockhouse Creek Development (RCD) to
continue its weekly inspections and functional testing of its complete
deluge-type water spray system, and to remove blow-off dust covers from
the nozzles. The petitioner states that: (1) Sections 75.1101-1 through
75.1101-4 set forth requirements regarding deluge-type water spray
systems and among those requirements there is no mandate to inspect and
functional-test such systems. Nevertheless, RCD conducts a weekly
inspection and functional-tests of its complete deluge-type spray
system. The system consists of an average of thirty (30) sprays along
each of approximately ten (10) primary belt-conveyor drives and an
average of sixty (60) sprays along each of eight (8) secondary drives;
and (2) Currently RCD provides blow-off dust covers for each nozzle as
required in 75.1101-1. In view of the frequent inspections and
functional testing of the system, the dust covers are not necessary
because the nozzles can be maintained in an unclogged condition through
weekly use. Further, it is burdensome to recap the large number of
covers weekly after each inspection and functional test. The petitioner
asserts that the proposed alternative method would at all times
guarantee no less than the same measure of protection afforded the
miners employed at Rockhouse Creek Development by the existing
standard.
Docket Number: M-2009-052-C.
Petitioner: ICG Beckley, LLC, 300 Corporate Centre Drive, Scott
Depot, West Virginia 25560.
Mine: Beckley Pocahontas Mine, MSHA I.D. No. 46-05252, located in
Raleigh County, West Virginia.
Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).
Modification Request: The petitioner requests a modification of the
existing standard to be permitted to continue mining through the
vertical boreholes and horizontal legs and branches (laterals) of
coalbed methane (CBM) wells that penetrate the coalbed it is mining.
Intact Coal Bed Methane Borehole (Surface Articulated/Drilled) (CBM)
Mine Through Plans. One of the following method(s) will be implemented
to protect against hazards from such wells to the miners in the mine
while mining through CBM wells with horizontal branches in coal seams:
Option A: Water plug under pressure: (1) The CBM well will be infused
with water prior to the underground mining operations breaching the CBM
well. A positive pressure will be maintained on the CBM well in an
effort to infuse the coal around the CBM hole with water, as well; (2)
the CBM well system will be equipped with a flame arrestor and
sufficient lightning protection; (3) mining will be completed in
accordance with the underground mine-through procedures as listed in
the plan; (4) legs/laterals that are opened after mining will be
evaluated to determine the quantity of methane being produced in order
to determine if the lateral will have to be plugged or simply
ventilated; (5) if a plug is required, it will be installed in
accordance with the contingency plans as listed; (6) typically, open
legs/laterals will be breached multiple times during mining. The
segmented hole(s) will be ventilated or filled with water each time it
is breached. The larger or outby portions of the borehole/degas hole
will be pressurized with water. Option B: Maintain Negative (Vacuum)
Pressure on Degas Hole: (1) The CBM well will have a vacuum pump or
compressor system setup at the wellhead that will have the capability
of maintaining a sufficient vacuum pressure on the entire CBM borehole
and provide a pressure that is lower than the mine operating pressure
at any intersection point; (2) the CBM well will be set up with a 24
hour monitoring system that will immediately notify the mine operator
of any reductions or losses in vacuum pressure; (3) the well system
will be equipped with a flame arrestor and sufficient lightning
protection. An automatic vent and oxygen sensor system will be
installed and maintained such that when oxygen from the underground
mine/pipe system is detected, the vent will open and vent the methane
to the atmosphere; (4) the CBM gas well on the surface will be
pressurized and a negative (vacuum) pressure will be maintained on the
legs/laterals of the system; (5) mining will be completed in accordance
with the underground mining procedures listed in this plan; (6) when a
degas hole is intercepted, mine air will be pulled into the open
borehole and will ventilate the outby portion of the degas borehole
immediately; (7) legs/laterals on the inby portion of the hole that are
not being pulled to the surface will be evaluated to determine the
quantity of methane being produced in order to determine if the lateral
will have to be plugged or simply ventilate; (8) if a plug is required
it will be installed in accordance with the contingency plan as listed;
(9) typically, open legs/laterals will be breached multiple times
during
[[Page 3258]]
mining. The segmented hole(s) will be ventilated by mine air or by the
pressure from the vacuum pump on the surface; (10) short segments of
CBM legs/laterals (100 feet or less) will be ventilated and air forced
through the segment to sweep away any methane in that segment. After
the hole has been ventilated, it will be allowed to remain open and be
ventilated with the remainder of the mine. Option C: Plugging the
Coalbed Methane Well (CBM) from the Surface: (1) Procedures for
cleaning out and preparing the CBM well for plugging: (a) Make a
diligent and reasonable effort to remove all metal casing from the CBM/
well borehole unless it has been grouted in place. Metal casing that
has been grouted in place will be perforated or ripped at intervals to
allow for any expanding cement or slurry mixtures to infiltrate the
annulus between the casing and the borehole wall; (b) a diligent and
reasonable effort will be made to reenter the CBM/well borehole to the
original total measured distance. If the total measured distance cannot
be reached, the borehole will be reentered to the maximum extent
practicable. Similarly, any known laterals will be reentered to the
maximum extent practicable; (c) a directional deviation survey
completed during the drilling of the borehole/well or during the
cleanout will be utilized to determine the relative location of the
coal seam and of the location of the boreholes within the coal seam;
(2) Plugging Coalbed Methane (CBM) wells: (a) Once the borehole has
been reentered to the maximum extent practicable, expanding grout will
be pumped into the CBM. Where laterals are encountered, a diligent and
reasonable effort will be made to reenter each known lateral and grout
to the maximum extent practicable. Upon completion of grouting each
lateral, the inby portion of the main trunk line of the CBM will be
filled with expanding grout to the maximum extent practicable, and will
be repeated until the CBM is grouted/filled to the surface; (b) the
MSHA District Manager will determine what alternate materials other
than grout are suitable for use in sealing the borehole; and (c) a
small quantity of steel shavings or magnetic material will be installed
at the top of the grouted CBM borehole and utilized as a monument
locating the site; (3) If the CBM well is located such that it may be
used as a bleeder borehole, the grout mixture quantity will be limited
to fill only the coal seam drill hole void. In all other circumstances,
the CBM will be filled with grout to at least fifty feet above the
upper most underground minable coal seam. The petitioner states that:
(1) The operator will notify the District Manager or his designee prior
to mining within 300 feet of any well and when a specific plan is
designated for mining through each well. The District Manager or his
designee, the representative of miners, and the appropriate State
agency will receive reasonable notification prior to the mining-through
operation in order to have an opportunity to have a representative
present; (2) the mining-through operation will be under the direct
supervision of a certified person in charge. Personnel will not be
permitted in the area of the mining-through operation except those
actually engaged in the operation, company personnel, a representative
of the miners, the MSHA representative(s) and the representative(s)
from the appropriate State agency; (3) underground procedures for
mining through a degas borehole will include firefighting equipment,
fire extinguishers, rock dust and sufficient fire hose to reach the
working face to be available near the working place where the cut-
through will take place. The surrounding area within 20 feet of the
cut-through area will be heavily rock dusted immediately prior to the
cut-through. Adequate roof support and ventilation materials will be
available near the working place where the cut-through will take place.
Ventilation quantities will be maintained at the working face
throughout the mine-through operation. Equipment will be in compliance
with permissibility requirements and compliance will be verified on the
shift immediately prior to the cut-through. Persons may review a
complete description of the petitioner's procedures for mining through
CBM wells at the MSHA address listed in this notice. The petitioner
asserts that the proposed alternative method will at all times
guarantee no less than the same measure of protection at the Beckley
Pocahontas Mine as would be afforded by the existing standard.
Docket Number: M-2009-053-C.
Petitioner: ICG Beckley, LLC, 2221 Old Eccles Road, P.O. Box 49,
Eccles, West Virginia 25836.
Mine: Beckley Pocahontas Mine, MSHA I.D. No. 46-05252, located in
Raleigh County, West Virginia.
Regulation Affected: 30 CFR 75.1909(b)(6) (Non-permissible diesel-
powered equipment; design and performance requirements).
Modification Request: The petitioner requests a modification of the
existing standard to permit the Getman Roadbuilder, Serial Number 460-
001 to be operated as it was originally designed, without front brakes.
The petitioner states that: (1) The rule does not address equipment
with more than four (4) wheels, specifically the Getman Roadbuilder,
Model RDG-1504S, with six (6) wheels; (2) the machine has dual brake
systems on the four (4) rear wheels, and is designed to prevent loss of
braking due to a single component failure; (3) seventy-four percent
(74%) of the machines total weight is over the four (4) rear wheels;
and (4) with the weight distribution, brakes on the rear of the machine
are sufficient to safely stop the machine. The petitioner further
states that: (1) Training will be provided to the grader operators to
lower the moldboard to provide additional stopping capability in
emergency situations; and (2) training will be provided to the grader
operators to recognize the appropriate speeds to use on different
roadway conditions, and to limit the maximum speed to 10 miles per
hour. The petitioner asserts that the proposed alternative method will
provide the same degree/level of safety as the existing regulation.
Docket Number: M-2009-054-C.
Petitioner: Pinnacle Mining Company, LLC, P.O. Box 338, Pineville,
West Virginia 24874.
Mine: Pinnacle Mine, MSHA I.D. No. 46-01816, located in Wyoming
County, West Virginia.
Regulation Affected: 30 CFR 75.507-1 (Electric equipment other than
power-connection points; outby the last open crosscut; return air;
permissibility requirements).
Modification Request: The petitioner requests a modification of the
existing standard to permit 2,400-volt or 4,160-volt alternating
current submersible pump(s) to be installed and operated in return and/
or bleeder entries and sealed areas in the Pinnacle Mine. The
petitioner states that the three phase 2,400-volt or 4,160-volt
alternating current electric power circuit(s) for the pump(s) will be
designed and installed to: (a) contain either a direct or a derived
neutral, which will be grounded through a suitable resistor at the
source transformer of power center. A grounding circuit originating at
the grounded side of the grounding resistor will extend along with the
power conductors and serve as the grounding conductor for the frame of
the pump(s) and all associated electric equipment that may be supplied
power from the circuit(s). The borehole casing will be bonded to the
system grounding medium; and (b) contain a grounding resistor that
limits the ground-fault current to not more than 6.5 amperes.
[[Page 3259]]
The grounding resistor must be rated for the maximum fault current
available and must be insulated from ground for a voltage equal to the
phase-to-phase voltage of the system. The petitioner asserts that the
proposed alternative method will provide an acceptable alternative and
provide at least the same degree of safety as the existing standard.
Docket Number: M-2009-055-C.
Petitioner: Prairie State Generating Company, LLC, 4274 County
Highway 12, Marissa, Illinois 62257.
Mine: Lively Grove Mine, MSHA I.D. No. 11-03193, located in
Washington County, Illinois.
Regulation Affected: 30 CFR 75.503 (Permissible electric face
equipment; maintenance).
Modification Request: The petitioner requests a modification of the
existing standard to permit the trailing cables to be increased to the
maximum length of 950 feet for the 995 volt three-phase alternating
current continuous mining machines and the 480-volt to 995 volt three-
phase alternating current roof-bolting machines. The petitioner states
that: (1) The maximum length of the trailing cables supplying power to
three-phase 995 continuous miners will be 950 feet. The maximum length
of the trailing cables supplying power to three-phase 480-volt or 995-
volt roof bolting machines will be 950 feet; (2) the trailing cables
for the 995-volt continuous mining machines will not be smaller than
No. 2 American Wire Gauge (AWG), SHD-GC. The trailing cables for the
480-volt or 995-volt roof bolting machines will not be smaller than No.
2 AWG, SHD-GC; (3) all circuit breakers used to protect the No. 2 AWG
trailing cables exceeding 850 feet in length will have instantaneous
trip units calibrated to trip at 1,500 amperes. The trip setting will
be sealed so that the setting cannot be changed, and these circuit
breakers will have permanent, legible labels. Each label will identify
the circuit breakers as being suitable for protecting No. 2 AWG cables.
The label will be maintained legible. Replacement instantaneous trip
units used to protect No. 2 AWG trailing cables will be calibrated to
trip at 1,500 amperes and the setting will be sealed or locked for
trailing cables exceeding 850 feet in length; (4) all circuit breakers
used to protect No. 2 AWG trailing cables exceeding 700 feet in length
and less than 850 feet in length, will have instantaneous trip units
calibrated to trip at 800 amperes. The trip setting will be sealed to
that the setting cannot be changed, and will have permanent, legible
labels. Each label will identify the circuit breakers as being suitable
for protecting No. 2 AWG cables. The label will be maintained legible.
Replacement instantaneous trip units used to protect No. 2 AWG trailing
cables will be calibrated to trip at 800 amperes and this setting will
be sealed or locked for trailing cables exceeding 700 feet in length
and less than 850 feet in length; (5) all components that provide
short-circuit protection will have a sufficient interruption rating in
accordance with the maximum calculated fault currents available. Short-
circuit current setting must not exceed 70 percent of the minimum
available current; (6) during each production day, persons designated
by the mine operator will visually examine the trailing cables to
ensure that the cables are in safe operating condition and that the
instantaneous settings of the specially calibrated breakers do not have
seals or locks removed and that they do not exceed the settings
stipulated in items 5 and 6; (7) permanent warning labels will be
installed and maintained on the cover(s) of the power center
identifying the location of each sealed short-circuit protective
device; (8) any trailing cable that is not in safe operating condition
will be removed from service immediately and repaired or replaced; (9)
splices and repairs in trailing cables will be made in accordance with
the instructions of the splice or repair manufacturer and 30 CFR 75.603
and 30 CFR 75.604; (10) all miners who have been designated to examine
the integrity of seals, verify the short-circuit settings, and examine
trailing cables for defects will receive part 48 training in the
following: (a) The mining methods and operating procedures that will
protect the trailing cables against damage; (b) the proper procedures
for examining the trailing cables to ensure that they are in safe
condition; (c) the hazards if setting the short-circuit interrupting
device(s) too high to adequately protect the trailing cables; and (d)
how to verify that the circuit interrupting device(s) protecting the
trailing cable(s) are properly set and maintained. The petitioner
asserts that the alternative method will at all times guarantee no less
than the same measure of protection afforded by the existing standard.
Docket Number: M-2009-056-C.
Petitioner: Prairie State Generating Company, LLC, County
Highway12, Marissa, Illinois 62257.
Mine: Lively Grove Mine, MSHA I.D. No. 11-03193, located in
Washington County, Illinois.
Regulation Affected: 30 CFR 75.1002 (Installation of electric
equipment and conductors; permissibility).
Modification Request: The petitioner requests a modification of the
existing standard to permit the use of 2,400-volt continuous miners in
the Lively Grove Mine. The petitioner states that: (1) The nominal
voltage of power circuits will not exceed 2,400 volts; (2) the nominal
voltage of the control circuits will not exceed 120 volts; (3) the
ground-fault current will be limited by a neutral grounding resistor to
not more than 0.5 ampere; (4) high-voltage circuits will be protected
against short-circuits, overload, ground-faults, and undervoltage by a
circuit interrupting device of adequate interrupting capacity; (5) the
high-voltage cable for the 2,400-volt continuous miner circuit will be
provided with instantaneous ground-fault protection set at not more
than 0.125 ampere; (6) the neutral grounding resistor will be provided
with backup ground-fault protection that will de-energize the primary
of the transformer if a ground fault occurs with the neutral grounding
resistor open; (7) each ground-fault current device will be provided
with a test circuit that will inject a current of 50 percent or less of
the current rating of the grounding resistor and cause each
corresponding circuit-interrupting device to open. The test circuit
will not subject the equipment to an actual phase-to-ground-fault
condition. The petitioner further states that within 60-days after the
Proposed Decision and Order become final, the petitioner will submit
provisions for its approved part 48 training plan to the District
Manger. The proposed revisions will include, but not limited to, task
training, hazard training, and specialized training for qualified
persons under 30 CFR 75.153, and annual refresher training. In
addition, the following will be adopted: (a) Safety precautions for the
handling and use of high-voltage trailing cables, for all mines
assigned to work in the area of the high-voltage trailing cable; and
(b) specialized training for qualified electricians that will be
required to repair, maintain and/or trouble-shoot the high-voltage
trailing cable or equipment. This training will focus on the
requirements of this modification. Persons may review a complete
description of the petitioner's proposed alternative method at the MSHA
address listed in this notice. The petitioner asserts that the
alternative method will at all times guarantee no less than the same
measure of protection afforded by the existing standard.
Docket Number: M-2009-057-C.
Petitioner: Prairie State Generating Company, LLC, 4274 County
Highway 12, Marissa, Illinois 62257.
[[Page 3260]]
Mine: Lively Grove Mine, MSHA I.D. No. 11-03193, located in
Washington County, Illinois.
Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).
Modification Request: The petitioner requests a modification of the
existing standard to permit an alternative method of plugging and
mining through oil and gas wells. The petitioner states that: (1)
Lively Grove Mine will be mining the Herrin 6 coal and will
experience mining around or through oil and gas wells; (2) copies of
the plugging affidavits have been acquired from the Illinois State
Geological Survey in the reserve area; and (3) before the well is
approached, a drawing will be submitted to the District Office for
approval to either mine around the well or through the well if
necessary. The petitioner also states that the following procedures
will be utilized when plugging oil and gas wells: (1) Cleaning out and
preparing oil and gas wells: (i) A diligent effort will be made to
clean the borehole to the original total depth. If this depth cannot be
reached, the borehole will be cleaned out to a depth which would permit
the placement of at least 200 feet of expanding cement below the base
of the lowest minable coalbed; (ii) when clearing the borehole, a
diligent effort will be made to remove all the casing in the borehole.
If it is not possible to remove all casing, the casing which remains
will be perforated or ripped at intervals spaced close enough to permit
expanding cement slurry to infiltrate the annulus between the casing
and the borehole wall for distance of at least 200 feet below the base
of the lowest minable coalbed; (iii) if the cleaned out borehole
produces gas, a mechanical bridge plug will be place in the borehole in
a competent stratum at least 200 feet below the base of the lowest
minable coalbed, but above the top of the uppermost hydrocarbon
producing stratum. If it is not possible to set a mechanical bridge
plug, a substantial brush plug may be used in place of the mechanical
bridge plug; (iv) a suite of logs will be made consisting of a caliper
survey directional deviation survey, and log(s) suitable for
determining the top and bottom of the lowest minable coalbed and
potential hydrocarbon producing strata and the location for the bridge
plug. An electric well log to determine hole diameter will be conducted
to accurately predict the quantity of cement required to plug the hole
from 200 feet below the base of the lowest minable coal seam to the
surface; (v) if the uppermost hydrocarbon-producing stratum is within
200 feet of the base of the lowest minable coalbed, properly placed
mechanical bridge plugs or a suitable brush plug described in
subparagraph (a)(3) will be used to isolate the hydrocarbon producing
stratum from the expanding cement plug. Nevertheless, a minimum of 200
feet of expanding cement will be place below the lowest minable
coalbed; and (vi) the wellbore will be completely filled and circulated
with a gel that inhibits any flow of gas, supports the walls of the
borehole, and increases the density of the expanding cement. This gel
will be pumped through an open-end tubing run to a point approximately
20 feet above the bottom of the cleaned out area of the borehole bridge
plug. (2) Plugging oil and gas wells to the surface. Procedures to be
utilized when plugging gas or oil wells to the surface are as follows:
(i) A cement plug will be set in the wellbore by pumping an expanding
cement slurry down the tubing to displace the gel and fill the borehole
to the surface. As an alternative, the cement slurry may be pumped down
the tubing so that the borehole is filled with Portland cement or a
Portland cement-fly ash mixture from a point approximately 100 feet
above the top of the lowest minable coalbed to the surface with an
expanding cement plug extending from at least 200 feet below the lowest
minable coalbed to the bottom of the Portland cement. There will be at
least 200 feet of expanding cement below the base of the lowest minable
coalbed, and (ii) a surface casing, small quantity of steel turnings,
or other small magnetic particles, will be embedded in the top of the
cement near the surface to serve as a permanent magnetic monument of
the borehole. As an alternative, a steel rod may be driven into the
ground next to the borehole. (3) Plugging oil or gas wells using the
vent pipe method. Procedures to be utilized when using the vent pipe
method for plugging gas or oil wells are as follows: (i) A 4\1/2\ inch
or larger vent pipe will be run into the wellbore to a depth of 100
feet below the lowest minable coalbed and welded to a smaller diameter
pile, if desired, which will extend to a point approximately 20 feet
above the bottom of the cleaned out area of the borehole or bridge
plug; (ii) a cement plug will be set in the wellbore by pumping an
expanding cement slurry, Portland cement, or a Portland cement-fly ash
mixture down the tubing to displace gel so that the borehole is filled
with cement. The borehole and the vent pipe will be filled with
expanding cement for minimum of 200 feet below the base of the lowest
minable coalbed. The top of the expanding cement will extend to a point
approximately 100 feet above the top of the lowest minable coalbed;
(iii) all fluid will evacuated from the vent pipe to facilitate testing
for gases. During the evacuation of fluid, the expanding cement will
not be disturbed; and (vi) the top of the vent pipe will be protected
to prevent liquids or solids from entering the wellbore, but permit
ready access to the full internal diameter of the vent pipe when
necessary. (4) Plugging oil or gas wells for use as degasification
boreholes. Procedures to be utilized when plugging gas or oil wells for
subsequent use of degasification boreholes are as follows: (i) A cement
plug will be set in the wellbore by pumping an expanding cement slurry
down the tubing to displace the gel and provide at least 200 feet of
expanding cement below the lowest minable coalbed; (ii) to facilitate
methane drainage, degasification casing of suitable diameter, slotted
or perforated throughout its lower 150 to 200 feet will be set in the
borehole to a point 10 to 30 feet above the top of the expanding
cement; (iii) the annulus between the degasification casing and the
borehole wall will be cemented from a point immediately above the slots
or perforations to the surface; (iv) the degasification casing will be
cleaned out for its total length; and (v) the top of the degasification
casing will be fitted with a wellhead equipped as required by the
District Manager. Such equipment may include check valves, shut-in
valves, sampling port, flame arrester equipment, and security fencing.
The petitioner further states that when mining through a plugged oil or
gas well, the District Manager or designee will be notified prior to
mining within 300 feet of the well and when a specific plan is
developed for mining through each well. Within 60 days after this
Proposed Decision and Order becomes final, the petitioner will submit
proposed revisions for its approved 30 CFR Part 48 training plan to the
District Manager. These proposed revisions will include initial and
refresher training regarding compliance with the terms and conditions
stated in the Proposed Decision and Order. Persons may review a
complete description of the petitioner's procedures for implementing
the proposed alternative method at the MSHA address listed in this
notice. The petitioner asserts that the alternative method will at all
times guarantee no less than the same measure of protection afforded by
the existing standard.
Docket Number: M-2009-058-C.
Petitioner: Perry County Coal Corporation, 1845 S KY Hwy 15,
Hazard, Kentucky 41701.
[[Page 3261]]
Mine: E4-1 Mine, MSHA I.D. No. 15-18565, located in Perry County,
Kentucky.
Regulation Affected: 30 CFR 75.503 (Permissible electric face
equipment; maintenance).
Modification Request: The petitioner requests a modification of the
existing standard to permit the E4-1 Mine to increase the maximum
length of trailing cables supplying power to permissible pumps in the
mines. The petitioner states that: (1) This petition will apply only to
trailing cables supplying three-phase, 480-volt power for permissible
pumps; (2) the maximum length of the 480-volt power for permissible
pump will be 4,000 feet; (3) all circuit breakers used to protect
trailing cables exceeding the pump approval length or Table 9 of Part
18 will have an instantaneous trip unit calibrated to trip at 75
percent of phase to phase short-circuit current. The trip setting of
these circuit breakers will be sealed or locked, and these circuit
breakers will have permanent legible labels. Each label will identify
the circuit breaker as being suitable for protecting the trailing
cables, and the labels will be maintained legible. In instances where a
75 percent instantaneous set point will not allow a pump to start due
to motor inrush, a thermal magnetic breaker will be furnished. The
thermal rating of the circuit breaker will be no greater than 75
percent of the available short-circuit current and the instantaneous
setting will be adjusted one setting above the motor inrush trip point.
This setting will also be sealed or locked; (4) replacement
instantaneous trip units used to protect pump trailing cables exceeding
the length of Table 9 of Part 18 will be calibrated to trip at 75
percent of the available phase to phase short circuit current and this
setting will be sealed or locked; (5) permanent warning labels will be
installed and maintained on the cover(s) of the power center to
identify the location of each sealed or locked short-circuit protection
device. These labels will warn miners not to change or alter the short
circuit settings; (6) the pump circuits attached to this petition have
greater lengths than approved or in Table 9. All future pump
installation with excessive cable lengths will have a short-circuit
survey conducted and items 1-5 will be implemented. A copy of each
pump's short-circuit survey will be available at the mine site for
inspection; and (7) the petitioner's alternative method will not be
implemented until designated miners have been trained to examine the
integrity of the seals or locks, verify the short-circuit settings, and
perform proper procedures for examining trailing cables for defects and
damage. The petitioner further states that within 60 days after the
Proposed Decision and Order becomes final, proposed revisions for
approved 30 CFR Part 48 training plan at any of the listed mines will
be submitted to the Coal Mine Safety and Health District Manager. The
training plan will include: (a) Training in the mining methods and
operating procedures for protecting the trailing cables against damage;
(b) training in proper procedures for examining the trailing cables to
ensure they are in safe operating condition; (c) training in hazards of
setting the instantaneous circuit breakers too high to adequately
protect the trailing cables; and (d) training in how to verify that the
circuit interrupting device(s) protecting the trailing cable(s) are
properly set and maintained; and (e) the procedures of 30 CFR 48.3 for
approval of proposed revisions to already approved training plans will
apply. The petitioner asserts that the proposed alternative method will
at all times guarantee no less than the same measure of protection to
all miners at Perry County Coal Corporation than is provided the
existing standard.
Dated: January 14, 2010.
Patricia W. Silvey,
Director, Office of Standards, Regulations and Variances.
[FR Doc. 2010-935 Filed 1-19-10; 8:45 am]
BILLING CODE 4510-43-P