8246
Federal Register / Vol. 74, No. 35 / Tuesday, February 24, 2009 / Notices
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers (p–459–253). All documents
(original and eight copies) should be
filed with: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington DC
20426. A copy of any motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
p. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the
‘‘e-Filing’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–3857 Filed 2–23–09; 8:45 am]
BILLING CODE 6717–01–P
VerDate Nov<24>2008
17:23 Feb 23, 2009
Jkt 217001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–58–000]
Rockies Express Pipeline LLC; Notice
of Application
February 17, 2009.
Take notice that on February 3, 2009,
Rockies Express Pipeline LLC (Rockies
Express) 370 Van Gordon Street,
Lakewood, Colorado 80228, filed an
application in Docket No. CP09–58–000,
pursuant to section 7(c) of the Natural
Gas Act (NGA) and Part 157 of the
Commission’s regulations, requesting a
certificate of public convenience and
necessity to construct and operate
facilities to expand the capacity of its
system in Zone 1 by 200,000 Dth per
day. Specifically, Rockies Express
proposes to increase compression at two
certificated compressor stations: (1) Big
Hole Compressor Station in Moffat
County, Colorado—one new 20,500
horsepower (hp) unit; and (2) Arlington
Compressor Station in Carbon County,
Wyoming—one new 17,500 hp unit.
Rockies Express requests a
determination that rolled-in rate
treatment is appropriate for the
proposed facilities.
Any questions regarding this
application should be directed to Robert
F. Harrington, Vice President, Rockies
Express Pipeline LLC, P.O. Box 281304,
Lakewood, Colorado 80228–8304,
telephone no. (303) 763–3258, and
e-mail: Robert_Harrington@
kindermorgan.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
E:\FR\FM\24FEN1.SGM
24FEN1
Federal Register / Vol. 74, No. 35 / Tuesday, February 24, 2009 / Notices
www.ferc.gov. Persons unable to file
electronically should submit an original
and 14 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: March 10, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–3853 Filed 2–23–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9202–150]
Upper Yampa Water Conservancy
District; Notice of Application
Accepted for Filing, Soliciting Motions
To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting
Comments, Recommendations, Terms
and Conditions, and Fishway
Prescriptions
mstockstill on PROD1PC66 with NOTICES
February 17, 2009.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Amendment of
License.
b. Project No.: 9202–150.
c. Date Filed: December 4, 2008.
d. Applicant: Upper Yampa Water
Conservancy District.
e. Name of Project: Stagecoach
Project.
f. Location: The project is located on
the Yampa River, in Routt County,
Colorado.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Kevin
McBride, Director, Upper Yampa Water
Conservancy District, P.O. Box 880339,
Steamboat Springs, CO 80488–0339,
(970) 879–2424.
i. FERC Contact: Anthony DeLuca,
(202) 502–6632.
j. Deadline for filing comments,
protests, motions to intervene,
VerDate Nov<24>2008
17:23 Feb 23, 2009
Jkt 217001
recommendations, preliminary terms
and conditions, and fishway
prescriptions is due 60 days from the
issuance date of this notice; reply
comments are due 105 days from the
issuance date of this notice. All
documents (original and eight copies)
should be filed with: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. Please include
the project number (P–9202–150) on any
comments or motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Request: The Upper
Yampa Water Conservancy District
requests Commission approval to amend
the project’s existing license issued by
the Federal Energy Regulatory
Commission (FERC) to raise the storage
level of Stagecoach Reservoir by 4 feet.
This proposal will increase the spillway
crest elevation, thereby enlarging the
project’s reservoir storage capacity from
33,275 to 36,460 Ac-ft and increasing
the project’s potential for increasing
downstream water supply. The physical
composition of most of the Stagecoach
Project developments (e.g., the
powerhouse, turbines and generators,
transmission and substation, and other
mechanical, electrical, and transmission
equipment) will not be impacted.
However, the project spillway and
reservoir will be altered by the proposal.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
8247
n. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application. Comments, protests,
interventions, recommendations, terms
and conditions, and fishway
prescriptions may be filed electronically
via the Internet in lieu of paper; See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s web
site under ‘‘e-filing’’ link. The
Commission strongly encourages
electronic filing.
o. Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the title ‘‘PROTEST’’,
‘‘MOTION TO INTERVENE’’,
‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or ‘‘FISHWAY
PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). All comments,
recommendations, terms and conditions
or prescriptions should relate to project
works which are the subject of the
license amendment. Agencies may
obtain copies of the application directly
from the applicant. A copy of all other
filings in reference to this application
must be accompanied by proof of
service on all persons listed in the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
p. As provided for in 18 CFR
4.34(b)(5)(i), a license applicant must
file, no later than 60 days following the
date of issuance of this notice of
acceptance and ready for environmental
analysis: (1) A copy of the water quality
certification; (2) a copy of the request for
certification, including proof of the date
on which the certifying agency received
E:\FR\FM\24FEN1.SGM
24FEN1
Agencies
[Federal Register Volume 74, Number 35 (Tuesday, February 24, 2009)]
[Notices]
[Pages 8246-8247]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-3853]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-58-000]
Rockies Express Pipeline LLC; Notice of Application
February 17, 2009.
Take notice that on February 3, 2009, Rockies Express Pipeline LLC
(Rockies Express) 370 Van Gordon Street, Lakewood, Colorado 80228,
filed an application in Docket No. CP09-58-000, pursuant to section
7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission's
regulations, requesting a certificate of public convenience and
necessity to construct and operate facilities to expand the capacity of
its system in Zone 1 by 200,000 Dth per day. Specifically, Rockies
Express proposes to increase compression at two certificated compressor
stations: (1) Big Hole Compressor Station in Moffat County, Colorado--
one new 20,500 horsepower (hp) unit; and (2) Arlington Compressor
Station in Carbon County, Wyoming--one new 17,500 hp unit. Rockies
Express requests a determination that rolled-in rate treatment is
appropriate for the proposed facilities.
Any questions regarding this application should be directed to
Robert F. Harrington, Vice President, Rockies Express Pipeline LLC,
P.O. Box 281304, Lakewood, Colorado 80228-8304, telephone no. (303)
763-3258, and e-mail: Robert--Harrington@kindermorgan.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either complete
its environmental assessment (EA) and place it into the Commission's
public record (eLibrary) for this proceeding; or issue a Notice of
Schedule for Environmental Review. If a Notice of Schedule for
Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://
[[Page 8247]]
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: March 10, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-3853 Filed 2-23-09; 8:45 am]
BILLING CODE 6717-01-P