Wyoming Administrative Code
Agency 053 - Workforce Services, Department of
Sub-Agency 0013 - OSHA - Oil & Gas Well Services
Chapter 7 - SPECIAL OPERATIONS
Section 7-4 - Cementing
Universal Citation: WY Code of Rules 7-4
Current through September 21, 2024
(a) Specific requirements.
(i) A pressure test on pump discharge lines
when squeeze cementing shall be made at 1,000 psi over the maximum pressure
specified by customer for his well equipment.
(ii) All valves in discharge lines shall be
checked to see that they are open before giving orders to pump.
(iii) During operations each employee
designated to handle the pumping shall remain constantly at his designated
position while the pump is in operation, unless relieved by an authorized
employee as directed by the supervisor on that job.
(iv) Unauthorized persons shall remain at
least 75 feet from all pumping operations and pressure testing
operations.
(v) Cementing pressure
shall not exceed the equipment's maximum safe working pressure.
Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.