Wyoming Administrative Code
Agency 053 - Workforce Services, Department of
Sub-Agency 0012 - OSHA - Oil & Gas Well Special Servicing
Chapter 9 - FRACTURING AND TEST TANKS
Section 9-3 - Nitrogen Pumping

Universal Citation: WY Code of Rules 9-3

Current through July 13, 2024

(a) Nitrogen vaporizing units shall be spotted upwind or crosswind of the well.

(b) A shutoff (plug) valve and two (2) check valves shall be installed on a nitrogen line upstream of a commingling tee or manifold.

(c) A shutoff (plug) and a check valve shall be installed on a liquid line upstream of a commingling tee or manifold.

(d) Two (2) shutoff (plug) valves and a choke valve shall be installed on the release line with the shutoff valves located upstream of the choke valve.

(e) A check valve shall be installed in the fluid line immediately upstream of the nitrogen connection to that line.

(f) When the nitrogen is being mixed with fluid, the nitrogen and fluid lines shall be teed together as closely to the well head as possible.

(g) When nitrogen line is connected directly to the wellhead, all well head connections shall be inspected to insure they meet or exceed the anticipated working pressure.

(h) The discharge manifold shall be staked or anchored in such a manner that manifold movement is limited in the event of a connection failure.

(i) Liquid lines shall be pressure tested with liquid only.

(j) Nitrogen lines shall be pressure tested with nitrogen only. This shall be a leak test only.

(k) No manifold shall be pressure tested with nitrogen at a pressure above its normal working pressure.

Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.