Section 3-8 - Permit Duration
Current through September 21, 2024
(a) In general, any construction, installation, modification, reuse of treated wastewater or land application permits authorized by a permit issued under this Chapter shall be completed within five (5) years from the date of issuance. A permit may specify a shorter deadline.
(b) If the construction, installation, or modification, reuse of treated wastewater, or land application is not completed within five (5) years of the date of issuance or by the deadline specified in the permit (whichever is sooner), the permit automatically terminates, and the applicant shall obtain a new permit before constructing, installing, or modifying the facility, or continuing to reuse treated wastewater, or land apply.
(c) If the permittee completes construction, installation, or modification of the facility, or reuse of treated wastewater or land application before the deadline established by this paragraph or the permit (whichever is sooner), the permit continues as a permit to operate the facility. The permittee may continue to operate the facility in compliance with the terms of the permit until the permit is suspended, revoked, or terminated under Section 13 of this Chapter.
(d) Operational, record keeping, and reporting requirements shall remain in effect for the life of the facility.