(a) The Director may modify a permit for any of the following reasons:

(i) Existing, unknown, or changing site conditions that would prevent compliance with the Water Quality Rules;

(ii) Receipt of additional information; or

(iii) The Administrator determines that modifying the permit is necessary to achieve compliance with Water Quality Rules or the Environmental Quality Act; or

(iv) The permittee requests a permit modification.

(b) The Department shall notify the permittee in writing of its intent to modify an individual permit. The notification shall include the proposed permit modification and the reasons for modifying the permit. The modified permit is effective twenty (20) days after the permittee receives notice of the Department's intent to modify the permit unless within that time the permittee requests a contested case hearing before the Environmental Quality Council.

(c) The Director shall issue a new individual permit that reflects the modifications when the permit becomes effective.

(d) The Director shall review each general permit at least every five (5) years from the date of issuance, make modifications as needed, and reissue the general permit.

(i) All proposed modifications to the general permit shall be subject to public notice and opportunity for public comment according to Section 5(c) of this Chapter before the general permit is modified.

(ii) Facilities that are covered under a general permit shall continue to be covered under the modified general permit. To continue to be covered, facilities shall comply with all requirements of the modified general permit.

(e) A permittee may request a modification to its permit at any time by submitting a new application, an amended application, or a request to modify the permit.

(f) Any request to modify a permit, deviate from the plans submitted with the permit application, or use alternative materials or procedures shall be made in writing, and no modification to the permit shall be effective until the Director issues written authorization or a modified permit, except that:

(i) To prevent construction delays, a permittee may verbally request to use alternative materials or procedures, and the Administrator may verbally approve the request. The Administrator may approve the request if the materials or procedures specified in the issued permit cannot be obtained or accomplished and alternative materials or procedures meet the minimum design standards of this Chapter, Water Quality Rules Chapter 11, Water Quality Rules Chapter 12, Water Quality Rules Chapter 25, and Water Quality Rules Chapter 28; and

(ii) Verbal approval to use alternative materials or procedures is immediately effective, provided that the permittee submits a written request within five (5) days of receiving verbal approval.

Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.