Chapter 12 - DESIGN AND CONSTRUCTION STANDARDS FOR PUBLIC WATER SUPPLIES
Section 12-10 - Design Requirements for Preliminary Treatment and Redundancy
Current through September 21, 2024
(a) 2018 TSS, parts 2.9-2.9(c), monitoring equipment; 2.10, sample taps; 2.11, facility water supply; and 2.14, piping color code are herein incorporated by reference.
(b) The proposed design shall demonstrate that the capacity of the water treatment or water production system is designed for the maximum daily demand at the design year based on historical usage records.
(c) The structural design shall demonstrate consideration of:
(d) Proposed treatment facilities locations shall demonstrate that:
(e) Proposed treatment shall demonstrate that the facility will produce potable water that is bacteriologically, chemically, radiologically, and physically safe, as required by 40 CFR Part 141.
(f) Designs for proposed treatment facilities with 100,000 gpd capacity and over shall include duplicate units, as a minimum, for chemical feed, flocculation, clarification, sedimentation, filtration, and disinfection.
(g) Designs for proposed treatment facilities under 100,000 gpd capacity shall include:
(h) All treatment facility pumping shall provide the maximum daily demand flow with the largest single-unit not in service. Finished water pumping in combination with finished water storage that floats on the distribution systems shall provide the maximum hourly demand with the largest single-unit not in service. For designs that include fire protection, pumping, and finished water storage that floats on the system shall provide the fire demand plus the maximum daily demand, or the maximum hourly demand, whichever is greater.
(i) Where the finished water storage volume that floats on the distribution system is not capable of supplying the maximum daily demand, the proposed design shall include alternative power for the finished water pumps that demonstrates:
(j) Process equipment, filters and appurtenances, disinfection, chemical feed and storage, electrical and controls, and pipe galleries shall be located in suitable structures.
(k) All equipment not required to be in or on open basins, such as clarifier drives and flocculators, shall be located in heated, lighted, and ventilated structures.
(l) Piping shall be buried below frost level, placed in heated structures, or provided with heat and insulated.
(m) Structure entrances shall be above grade.
(n) Selected construction materials shall provide water tightness, corrosion protection, and resistance to weather variations.
(o) NSF/ANSI/CAN 61-2020/NSF/ANSI/CAN 600-2021 certified coatings used to protect structures, equipment, and piping shall be suitable for atmospheres containing moisture and low concentrations of chlorine.
(p) Surfaces exposed in chemical areas shall be protected from chemical attack.
(q) Paints shall not contain lead, mercury, or other toxic metals or chemicals.
(r) All enclosed spaces shall be provided with forced ventilation, except pumping station wetwells or clearwells that meet the following requirements:
(s) Service transformers and other critical electrical equipment shall be located above the 100-year flood and above grade. Transformers shall be located so that they are remote or protected by substantial barriers from traffic. Motor controls shall be located in superstructures and in rooms that do not contain corrosive atmospheres.
(t) All treatment facilities shall have a flow-measuring device provided for raw water influent and clear well effluent and each shall provide totalized flow. The accuracy of the device shall be at least plus or minus two percent of span and shall meet the following requirements:
(u) Water treatment plants shall be provided with continuous water turbidimeters (including recorders) that demonstrate compliance with the Guidance Manual for Compliance with the Surface Water Treatment Rules, Turbidity Provisions.