Wyoming Administrative Code
Agency 020 - Environmental Quality, Dept. of
Sub-Agency 0009 - Solid Waste Management
Chapter 7 - FINANCIAL ASSURANCE REQUIREMENTS
Section 7-2 - Closure and Post-Closure Cost Estimates
Universal Citation: WY Code of Rules 7-2
Current through September 21, 2024
(a) Along with the closure plan and post-closure plan required for a regulated facility, the operator must submit closure and post-closure estimates.
(i) An incinerator, resource recovery
facility, compost facility, or storage surface impoundment may omit the
post-closure cost estimate if onsite disposal of wastes or residues is not
planned or required.
(b) The closure cost estimate shall:
(i) Include
an itemized written estimate of the cost, in current dollars of completing all
work described in the closure plan;
(ii) Be based on the cost required for a
third-party contractor to complete the closure plan at the most expensive point
in the life of the facility. The Director may obtain additional cost estimates
from a third-party contractor to substantiate the accuracy of the estimated
costs; and
(iii) Account for the
following factors if applicable:
(A) The size
and topography of the site;
(B) The
daily or weekly volume of waste to be received at the site;
(C) Availability of cover and fill material
needed for site grading;
(D) The
type of waste to be received at the site;
(E) Disposal method and sequential disposal
plan;
(F) The location of the site
and the character of the surrounding area;
(G) Requirements for surface
drainage;
(H) Operation and
maintenance of the leachate collection and treatment system, and the off-site
disposal of leachate;
(I)
Environmental quality monitoring system;
(J) Structures and other improvements to be
dismantled and removed. Salvage values cannot be used to offset demolition
costs;
(K) Site storage capacity
for solid waste, incinerator residue and compost material;
(L) Off-site disposal requirements. Salvage
values cannot be used to offset waste removal costs;
(M) Vector control requirements;
(N) Cleaning of all solid waste management
units and equipment;
(O) A minimum
of fifteen percent variable contingency fee to cover other closure costs as
determined appropriate by the Director. and
(P) Any other relevant site-specific
factors.
(c) The post-closure cost estimate shall:
(i)
Include an itemized written estimate, in current dollars, of the cost of
completing all work described in the post-closure plan;
(ii) Be based on the cost required for a
third-party contractor to complete the work described in the post-closure plan.
The Director may obtain additional cost estimates from a third-party contractor
to substantiate the accuracy of the estimated cost; and
(iii) Account for the following factors if
applicable:
(A) The size and topography of the
site;
(B) The type and quantity of
waste received;
(C) Disposal method
and sequential disposal plan;
(D)
The potential for significant leachate production and the possibility of
contaminating water supplies;
(E)
Environmental quality monitoring systems;
(F) Soil conditions;
(G) The location of the site and the
character of the surrounding area;
(H) Planned inspections of
facility;
(I) A minimum of fifteen
percent contingency fee to cover other post-closure costs as determined
appropriate by the Director; and
(J) Any other relevant site-specific
factors.
(d) Closure and post-closure cost estimates shall be updated, revised, and submitted to the Director as specified in Section 13 of this Chapter.
Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.