Section 7-2 - Closure and Post-Closure Cost Estimates

Universal Citation: WY Code of Rules 7-2

Current through September 21, 2024

(a) Along with the closure plan and post-closure plan required for a regulated facility, the operator must submit closure and post-closure estimates.

(i) An incinerator, resource recovery facility, compost facility, or storage surface impoundment may omit the post-closure cost estimate if onsite disposal of wastes or residues is not planned or required.

(b) The closure cost estimate shall:

(i) Include an itemized written estimate of the cost, in current dollars of completing all work described in the closure plan;

(ii) Be based on the cost required for a third-party contractor to complete the closure plan at the most expensive point in the life of the facility. The Director may obtain additional cost estimates from a third-party contractor to substantiate the accuracy of the estimated costs; and

(iii) Account for the following factors if applicable:
(A) The size and topography of the site;

(B) The daily or weekly volume of waste to be received at the site;

(C) Availability of cover and fill material needed for site grading;

(D) The type of waste to be received at the site;

(E) Disposal method and sequential disposal plan;

(F) The location of the site and the character of the surrounding area;

(G) Requirements for surface drainage;

(H) Operation and maintenance of the leachate collection and treatment system, and the off-site disposal of leachate;

(I) Environmental quality monitoring system;

(J) Structures and other improvements to be dismantled and removed. Salvage values cannot be used to offset demolition costs;

(K) Site storage capacity for solid waste, incinerator residue and compost material;

(L) Off-site disposal requirements. Salvage values cannot be used to offset waste removal costs;

(M) Vector control requirements;

(N) Cleaning of all solid waste management units and equipment;

(O) A minimum of fifteen percent variable contingency fee to cover other closure costs as determined appropriate by the Director. and

(P) Any other relevant site-specific factors.

(c) The post-closure cost estimate shall:

(i) Include an itemized written estimate, in current dollars, of the cost of completing all work described in the post-closure plan;

(ii) Be based on the cost required for a third-party contractor to complete the work described in the post-closure plan. The Director may obtain additional cost estimates from a third-party contractor to substantiate the accuracy of the estimated cost; and

(iii) Account for the following factors if applicable:
(A) The size and topography of the site;

(B) The type and quantity of waste received;

(C) Disposal method and sequential disposal plan;

(D) The potential for significant leachate production and the possibility of contaminating water supplies;

(E) Environmental quality monitoring systems;

(F) Soil conditions;

(G) The location of the site and the character of the surrounding area;

(H) Planned inspections of facility;

(I) A minimum of fifteen percent contingency fee to cover other post-closure costs as determined appropriate by the Director; and

(J) Any other relevant site-specific factors.

(d) Closure and post-closure cost estimates shall be updated, revised, and submitted to the Director as specified in Section 13 of this Chapter.

Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.