(a) Authority: The authority for the rules and regulations promulgated in this chapter is the Wyoming Environmental Quality Act, Wyoming Statutes (W.S.) 35-11-101 et seq.

(b) Permit transition:

(i) Existing facilities:
(A) Existing facilities that have received wastes after the effective date of these regulations:
(I) The operator of any facility with a complete application or a valid permit or an authorization that has not expired by the effective date of these regulations shall either:
(1.) Submit a renewal application before the existing permit or authorization expires, or

(2.) Cease receipt of wastes before the existing permit or authorization expires and close in conformance with the closure standards in this chapter.

(II) The operator of any facility without a complete application or a permit or authorization that has expired by the effective date of these regulations shall either:
(1.) Submit a renewal application no later than six (6) months after the effective date of these regulations, or

(2.) Cease receipt of wastes within six (6) months after the effective date of these regulations and close in conformance with the closure standards in this chapter.

(B) Existing facilities that have not received wastes after the effective date of these regulations: The operator may be required to submit a closure plan upon request by the Administrator. The Administrator may request such a plan whenever the Administrator has reason to believe that health and safety hazards are present or there is evidence of environmental contamination.

(ii) New facilities: The operator of any new facility shall submit an application as specified in Chapter 1 and shall obtain a permit prior to construction;

(iii) Closing facilities:
(A) Anticipated closure: The operator of any facility with a valid permit on the effective date of these regulations shall provide written notice of the intent to close to the Administrator at least thirty (30) days prior to commencing closure and close the facility in conformance with the closure standards in the facility's permit and this chapter. Closure shall be completed within ninety (90) days, unless additional time is granted by the Administrator. Within thirty (30) days after closure activities have been completed, the operator shall submit written documentation of closure to the Administrator. When the Administrator determines that closure has been properly completed and there are no health and safety hazards or environmental contamination, the permit shall be terminated and financial assurance will no longer be necessary.

(B) Unanticipated closure: In the event any facility ceases operation, as determined by nonreceipt of solid wastes for a continuous nine (9) month period or any continuous one (1) year period for petroleum-contaminated soils land treatment facilities and mobile transfer, treatment and storage facilities, the operator shall provide written notification to the Administrator no later than thirty (30) days after the end of such nine (9) month or one (1) year period and close the facility in conformance with the closure standards in the facility's permit and this chapter. Closure shall be completed within ninety (90) days, unless additional time is granted by the Administrator. Within thirty (30) days after closure activities have been completed, the operator shall submit written documentation of closure to the Administrator. When the Administrator determines that closure has been properly completed and there are no health and safety hazards or environmental contamination, the permit shall be terminated and financial assurance will no longer be necessary.

(C) Mobile transfer, treatment and storage facility closure: The operator of any mobile facility shall provide written notification to the Administrator within thirty (30) days if the operator no longer plans to operate the facility.

(c) Permit terms:

(i) Permits shall be issued for the operating life of the facility through closure and completion of any required remediation activities, as approved by the Administrator.

(ii) Mobile facilities shall not be operated in a single location for more than one (1) year, unless the Administrator provides specific written authorization;

(d) Definitions: The definitions in W.S. W.S. 35-11-103(a) and (d) of the Wyoming Environmental Quality Act and the definitions in Solid Waste Rules and Regulations Chapter 1 apply to these rules.

Disclaimer: These regulations may not be the most recent version. Wyoming may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.