(a)
Description of waste stream sampling: The Chapter 6
permit application for each facility shall include a description of the
proposed methodology for periodic monitoring and sampling of incoming wastes
for the purpose of determining the weight of material in representative samples
of unprocessed wastes. This weight, designated as UP in Section 7(c) of this
chapter, shall be determined initially for purposes of compliance with the test
demonstration requirements of Section 4 of this chapter. For operating
facilities, this weight shall be monitored by sampling representative wastes at
least once per month.
(b)
Other descriptions required: The Chapter 6 permit
application for each facility shall include detailed descriptions of the
systems, processes, equipment, personnel, and procedures to be used to comply
with the waste screening, waste processing, and waste recovery requirements of
this chapter. The descriptions shall include:
(i) Narrative discussions of the waste flows
and routings including but not limited to procedures used to receive wastes,
locations and routes for transfer of wastes from initial receipt of wastes to
ultimate disposition of treatment residues, locations and methods for storage
and removal of useful components of the waste stream, and other applicable
waste handling practices or procedures planned for use at the
facility.
(ii) Detailed design
drawings of facility structures, roads, loading and unloading structures,
environmental monitoring systems, and any other improvements associated with
the facility.
(iii) Detailed design
drawings, process flow information, and any available test results for
equipment or systems used for waste screening, waste processing, and recovery
of useful components of the waste stream. Information shall be of sufficient
detail to allow department evaluation of the ability of the equipment or
systems to perform as represented, and to comply with the standards of Sections
5, 6 and 7 of this chapter.
(iv) A
description of the equipment used to sample in- coming wastes, sampling
procedure(s) to be used, the frequency of sampling or inspecting incoming
wastes and a discussion of how such frequency will adequately detect prohibited
wastes.
(v) Narrative plan
describing the facility compliance monitoring systems used by the operator to
continuously monitor, record, and report to the department the facility's
compliance with the rules and regulations.
(vi) A description of the proposed test
demonstration, which shall be conducted to comply with the requirements of
Section 4 of this chapter. The test demonstration description shall address
sampling and analysis protocols for wastes to be used in the demonstration,
describe how the demonstration wastes are representative of wastes to be
received at the facility when full-scale operations commence, and include an
evaluation of the facility's ability to screen incoming waste shipments to
detect prohibited wastes.
(vii)
Procedures used to manage prohibited wastes removed from the wastes received at
the facility. The application shall include documentation that the planned
management methods for such prohibited wastes comply with applicable state and
federal requirements.
(viii) Any
other information needed by the department to evaluate compliance with the
requirements of this chapter.