Chapter PSC 184 - Construction Of And Placing Into Operation Of Water And Sewer Facilities
Section PSC 184.05 - Commission procedures
Current through August 26, 2024
(1) APPLICATION REVIEW.
(2) TIME FOR REVIEW. Unless the application requires the preparation of an environmental assessment under s. PSC 4.10(2), if no action is taken by the commission within 90 days after the commission issues a notice of investigation under sub. (1) (a), the utility may proceed with the construction work. If the commission requests additional information to process an application after issuing a notice of investigation, the 90-day waiting period before construction work may commence begins the date the additional information is received by the commission.
(3) HEARING. The commission is not required to hold a hearing on a utility application for a certificate unless any of the following apply: