Wisconsin Administrative Code
Public Service Commission
Chapter PSC 135 - Gas Safety
Subchapter II - Additions to 49 CFR Part 192
Section PSC 135.319 - Installation of pipe in a ditch additions [49 CFR 192.319]
Universal Citation: WI Admin Code ยง PSC 135.319
Current through August 26, 2024
(1) After 49 CFR 192.319(a), insert:
(aw) This includes grading the ditch so that
the pipe has a firm, substantially continuous bearing on the bottom of the
ditch. When long sections of pipe that have been welded alongside the ditch are
lowered in, care shall be exercised so as not to jerk the pipe or impose any
strains that may kink or put a permanent bend in the pipe.
(2) After 49 CFR 192.319(b)(2), insert:
(3w) If there are large rocks in the material
to be used for backfill, care should be used to prevent damage to the coating
or pipe by such means as the use of rock shield material, or by making the
initial fill with rock free material to a sufficient depth over the pipe to
prevent damage.
(4w) Where flooding
of the trench is done to consolidate the backfill, care shall be exercised to
see that the pipe is not floated from its firm bearing on the trench bottom.
(3) After 49 CFR 192.319(c), insert:
(cw) The provisions of
49 CFR
192.319(a) shall also apply
to mains operating at less than 20% of the SMYS.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.