Wisconsin Administrative Code
Public Service Commission
Chapter PSC 113 - Service Rules For Electrical Utilities
Subchapter IX - Electric Meter Testing Programs and Record Requirements
Section PSC 113.0911 - Testing of self-contained single-phase meters and 3-wire network meters at fixed periodic intervals
Universal Citation: WI Admin Code ยง PSC 113.0911
Current through August 26, 2024
In this section, "meter" or "meters" may refer to metering system(s).
(1) Self-contained single-phase meters and 3-wire network meters, together with associated equipment such as demand devices, control devices, etc., shall be tested for accuracy at unity power factor at the point where they are installed or at a central testing point or in a mobile testing laboratory under any of the following circumstances:
(a) Before being
placed in service. For new meters given a prior test by the manufacturer, a
sample test program meeting the requirements of s.
PSC 113.0920 or use of the manufacturer's certified test
results for all meters tested under the provisions of s.
PSC 113.0921, may be substituted for this
requirement.
(b) When they are
suspected of being inaccurate or damaged.
(c) When the accuracy is questioned by a
customer. See s.
PSC 113.0922.
(d) When they are removed from
service.
(e) Within a period of 6
months before to 6 months after 5 years of service for non-magnetic-bearing
meters and 20 years of service for magnetic-bearing surge-proof meters or in
accordance with the plan outlined in s.
PSC 113.0921.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.