Wisconsin Administrative Code
Public Service Commission
Chapter PSC 111 - Requirements For Strategic Energy Assessments, Certificates Of Public Convenience And Necessity, And Fixed Financial Parameters For Certain Rate Base Electric Generating Facilities
Subchapter I - General
Section PSC 111.05 - SEA filing procedures

Current through August 26, 2024

(1) PRINTED AND ELECTRONIC FORMAT. Except for the data required under s. PSC 111.35(3), data required under subch. II, III or IV shall be in printed, tabular form and in electronic spreadsheet format. Data required under s. PSC 111.35(3) shall be in printed, tabular form. Data required under subch. V shall be in printed, tabular form, unless specifically exempted, and in electronic spreadsheet format. If the commission provides tabular reporting or electronic format specifications, data filings shall comply with these specifications. All data filings shall be up to date and fully documented. All data filings shall indicate and provide the source of the data.

(2) JOINT FILINGS.

(a) Any electricity provider may file the data required under subch. II, III, IV or V jointly, combining its information with that of other electricity providers. Any transmission provider may file the data required under subch. V jointly, combining its information with that of other transmission providers. Except as provided in par. (b), information in joint filings may not be aggregated in a manner that obscures provider-specific data.

(b) A wholesale electricity supplier may file data that is required under subch. II, III, IV or V on behalf of one or more municipal electric utilities or cooperatives.

(3) MULTI-STATE ELECTRICITY AND TRANSMISSION PROVIDERS.

(a) Except as provided in par. (b), electricity and transmission providers with multi-state operations may, if Wisconsin-specific information is not available, file prorated data based on an allocation of Wisconsin demand to total company system demand.

(b) Electricity and transmission providers with multi-state operations shall provide Wisconsin-specific information for all of the following:
1. Conservation activities, as required under s. PSC 111.35.

2. Forecasts of Wisconsin peak demand, as required under s. PSC 111.13.

3. Transmission and generation facilities located in Wisconsin or used specifically for Wisconsin purposes, as required under s. PSC 111.21 or 111.43.

Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.