Wisconsin Administrative Code
Department of Natural Resources
NR 800 - Environmental Protection - Water Supply
Chapter NR 811 - Requirements For The Operation And Design Of Community Water Systems
Subchapter XIII - Aquifer Storage Recovery
Section NR 811.93 - Operating an ASR system
Current through August 26, 2024
(1) Department approval to operate an ASR system shall be obtained prior to recovery of any water retrieved through an aquifer storage recovery well into a municipal water system.
(2) Only the owner of a municipal water system may submit a request to operate an ASR system.
(3) Completion of an ASR pilot study is required before a municipal water system may submit a request to operate an ASR system.
(4) Completion of an ASR system development test and approval of the department is required before any additional aquifer storage recovery well that was not approved as part of an original request to operate an ASR system is connected to the existing ASR system.
(5) A request to operate an ASR system shall be submitted to the department in writing and shall contain the following:
(6) The department may require modification of any plans and specifications, operating plans, demand management and water accountability plans or compliance and monitoring plans required in sub. (5) in any manner necessary to ensure compliance with the performance standards set forth in s. NR 811.88.
(7) If requested, the department may consider and approve the modification of plans and specifications, operating plans, demand management and water accountability plans or compliance and monitoring plans required in sub. (5) if information submitted in support of a requested modification demonstrates to the satisfaction of the department that the proposed modifications will continue to ensure compliance with the standards set forth in s. NR 811.88 and any other applicable requirements contained in ch. NR 811.