Current through August 26, 2024
Ozonation can be used for a variety of purposes including
disinfection, oxidation, and microflocculation. When applied, all of these
reactions may occur but typically only one is the primary purpose for its use.
Ozonation can be used for the removal of color, taste and odors, organics,
algae, cyanide, hydrogen sulfide, iron, manganese, and heavy metals. In
addition to these treatment processes, ozone is an acceptable alternative to
chlorine disinfectants. Given the sophisticated nature of the ozone process,
consideration shall be given to the need for maintaining qualified operators to
operate and maintain the equipment. The following requirements shall be
met:
(1) GENERAL. The following general
requirements shall be met:
(a) All process
designs shall be based on bench or pilot scale studies of dosage requirements,
application points, and detention times conducted in accordance with s.
NR 811.44.
(b) When ozone is used as a disinfectant,
ozonation and detention shall provide the required disinfection CT value.
Additionally, application of a disinfectant which maintains a measurable
residual in the distribution system shall be required.
(c) Where ozonation is approved by the
department to be used for disinfection of a bacteriologically unsafe water
supply, duplicate process streams shall be provided. This includes air supply,
air preparation equipment, ozone generators, ozone contact chambers, ozone
diffusers, power supply, and post disinfection equipment. This requirement may
be waived by the department where other acceptable water sources having
sufficient capacity are available.
(2) FEED GAS PREPARATION. Feed gas can be
air, oxygen enriched air, or high purity oxygen. Sources of high purity oxygen
include purchased liquid oxygen; on site generation using cryogenic air
separation; or temperature, pressure or vacuum swing, adsorptive separation,
technology. For high purity oxygen-feed systems, dryers typically are not
required. Feed gas preparation shall meet the following requirements:
(a)
Air handling equipment.
Air handling equipment on conventional low pressure air-feed systems shall
consist of an air compressor unless drawn by vacuum, water or air separator,
refrigerant and desiccant dryers and particulate filters. For oxygen-feed
systems, compressors, separators, and dryers may not be required by the
department depending on the purity of the oxygen. In all cases the design shall
ensure that the maximum dew point of -60°C (-76°F) will not be exceeded
at any time.
(b)
Air
compression.1. Air compressors shall
be of the liquid-ring or rotary lobe, oil-less, positive displacement type for
smaller systems or dry rotary screw compressors for larger systems.
2. The air compressors shall have the
capacity to simultaneously provide for maximum ozone demand, provide the air
flow required for purging the desiccant dryers, where required, and allow for
standby capacity.
3. Air feed for
the compressor shall be drawn from a point protected from rain, snow,
condensation, mist, and fog to minimize moisture content of the air supply. The
air feed shall be protected from contaminated air sources. Outside air intakes
shall consist of a downturned pipe elbow installed at a location least
susceptible to vandalism and covered with a 24-mesh corrosion resistant
screen.
4. A compressed air
after-cooler or entrainment separator or both with automatic drain shall be
provided prior to the dryers to reduce the water vapor.
(c)
Air drying.
1. Dry, dust-free, and oil-free feed gas
shall be provided to the ozone generator. Sufficient drying to a maximum dew
point of -60°C (-76°F) shall be provided at the end of the drying
cycle.
2. Drying for high pressure
systems shall be accomplished using desiccant dryers. For low pressure systems,
a refrigeration air dryer in series with desiccant dryers shall be
used.
3. A refrigeration dryer
capable of reducing the inlet air temperature to 4°C (40°F) shall be
provided for low pressure air preparation systems. The dryer may be of the
compressed refrigerant type or chilled water type.
4. The desiccant dryers shall be of the
external heated or heatless type.
5. For heat-reactivated desiccant dryers, the
unit shall contain 2 desiccant filled towers complete with pressure relief
valves, 2 4-way valves and a heater. In addition, external type dryers shall
have a cooler unit and blowers. The size of the unit shall be such that the
specified dew point will be achieved during a minimum absorption cycle time of
16 hours while operating at the maximum expected moisture loading
conditions.
6. Each dryer shall be
capable of venting dry gas to the atmosphere, prior to the ozone generator, to
allow start-up when other dryers are on-line.
(d)
Air filters.
1. Air filters shall be provided on the
suction side of the air compressors, between the air compressors and the dryers
and between the dryers and the ozone generators.
2. The filter before the compressor shall be
of the coalescing type and be capable of removing all particles larger than 10
microns in diameter. The filter before the dryer shall be of the coalescing
type and be capable of removing all particles larger than 0.3 microns in
diameter. The filter after the dryer shall be of the particulate type and be
capable of removing all particles larger than 0.1 microns in diameter or a size
specified by the generator manufacturer.
(e)
Air preparation piping.
Piping in a compressed air preparation system shall be common grade steel,
seamless copper, stainless steel, or galvanized steel. The piping shall be
designed to withstand the maximum pressures in the air preparation system. PVC
piping may be used in a vacuum air preparation system when located and
supported to be protected from physical damage including from heat.
(3) OZONE GENERATORS. Ozone
generators shall meet the following requirements:
(a)
Capacity. The production
rating of the ozone generators shall be provided in pounds per day and pounds
per kilowatt-hour. The capacity of any ozone generators shall be determined by
ozone demand tests including tests under critical conditions. Where ozone is
approved for use by the department as a disinfectant, the generators shall be
sized in conjunction with the detention basins to provide the required
inactivation CT values for viruses,
Giardia lamblia, and
Cryptosporidium contained in ss.
NR 810.59, 810.60,
and 810.61.
1. The design shall ensure that the minimum
concentration of ozone in the generator exit gas will be 1.0% by
weight.
2. Generators shall be
sized to have sufficient reserve capacity so that the system does not operate
at peak capacity for extended periods of time. Low, medium, and high frequency
systems which operate at lower peak voltages require less reserve
capacity.
3. Generators with
individual dielectrics shall have the capability of operating satisfactorily
while individual dielectrics are out-of-service. This shall be accomplished
through the use of individually fused dielectrics.
4. At least 2 generators, each with a
capacity of supplying the normal ozone demand, shall be provided. If determined
by the department to be not critical to maintaining production capacity,
smaller installations employing ozone generators with multiple individually
fused dielectrics may be able to employ a fewer number of generators each
having excess ozone production capacity.
5. If there is to be a variation in the
supply temperature of the generator cooling water throughout the year, then
curves or other data shall be furnished to the department to show ozone
production changes due to the varying temperature of the supplied cooling
water. The design shall ensure that the generators can produce the required
ozone at the maximum coolant temperature.
(b)
Electrical. The
generators may be low, medium, or high frequency type. The specifications shall
require that the transformers and other electrical hardware be proven, high
quality components designed for ozone service.
(c)
Cooling. Adequate
cooling shall be provided. Cooling water supplied to the ozone generators may
not be corrosive or scale forming and shall be sufficiently free of
microbiological and inorganic contaminants to prevent fouling of the water side
of the tubes. If natural water quality does not meet this requirement,
treatment shall be required. A closed loop cooling water system shall be used
if proper cooling water conditions cannot be assured.
(d)
Materials. To prevent
corrosion, the ozone generator shell and tubes shall be constructed of type
304L or 316L stainless steel.
(4) OZONE CONTACTORS. The selection or design
of the contactor and method of ozone application depends on the purpose for
which the ozone is being used. Contactors can be of the diffused bubble,
venturi, or aspirating turbine mixer type as approved by the department. Ozone
contactors shall meet the following requirements:
(a) Where ozone is used as a disinfectant, a
minimum of 2 contact chambers shall be provided with the chambers designed to
prevent short-circuiting. Contactors shall be closed vessels.
(b) Contactors shall be separate vessels
having no common walls with the remainder of the facility, unless common walls
are approved by the department on a case-by-case basis. If common walls are
used, the contactor shall be kept under negative pressure and sufficient ozone
monitors shall be provided to protect worker safety. No normally inhabited
structure may be constructed over an ozone contactor or reservoir containing
ozone.
(c) Contact vessels shall be
made of reinforced poured concrete. All reinforcement bars shall be covered
with a minimum of 1.5 inches of concrete. Ozone resistant interior coatings
shall be approved by the department in accordance with s.
NR 810.09 (5). Smaller contact vessels may be made of
stainless steel, fiberglass, or other material which will be stable in the
presence of residual ozone and ozone in the gas phase above the water
level.
(d) Contact chambers shall
be of sufficient depth and size to allow for adequate contact time and
freeboard for foaming where applicable. The depth of water in bubble diffuser
contactors shall normally be a minimum of 18 feet unless a shallower depth can
be justified to the department. A minimum freeboard of 3 feet shall be provided
where foaming will be an issue.
(e)
The contact time for disinfection shall be determined based on the required
inactivation CT values for viruses, Giardia lamblia, and
Cryptosporidium contained in ss.
NR 810.59, 810.60,
and 810.61.
The minimum contact time shall be 10 minutes. A shorter contact time may be
approved by the department if justified by appropriate design and CT
considerations. Sufficient ozone capacity and contact chamber size shall be
provided to achieve the desired CT value when injecting ozone into only one of
the 2 contact chambers. The diffusion system shall normally work on a
countercurrent basis such that the ozone shall enter through porous diffusers
at the bottom of the vessel and water shall enter from the top of the vessel.
Countercurrent flow shall be provided in all chambers of the vessels.
Co-current diffusion systems shall only be approved by the department where
adequate justification can be supplied.
(f) For ozone applications in which
precipitates are formed, such as with iron and manganese removal, porous
diffusers may not be used.
(g)
Where taste and odor control is of concern, multiple application points and
contactors shall be considered.
(h)
A system shall be provided between the contactor and the off-gas destruct unit
to remove foam from the air and return the froth to the contactor or other
location acceptable to the department when foam will be an issue. A potable
water spray system shall be placed in the contactor head space if foaming is
expected to be excessive.
(i) All
openings into the contactor for pipe connections, hatchways, etc., shall be
properly sealed to prevent the escape of ozone using welds or ozone resistant
gaskets such as Teflon or Hypalon.
(j) A pressure or vacuum relief valve shall
be provided in the contactor as appropriate. Pressure or vacuum relief valve
discharge piping shall be piped to a location where there will be no damage to
the ozone destruction unit or an uncontrolled release of ozone.
(k) Sampling faucets and monitors shall be
provided on the inlet and outlet of each contact chamber to monitor water
quality and the ozone residual. If allowed by the department, a portable
monitor or a comparable testing method may be used to analyze water collected
from sample taps provided on the inlet and outlet of each contact
chamber.
(l) A water meter shall be
provided on the inlet to the contact chambers to measure water flow.
(m) If required by the department, contactors
or reservoirs used as contactors shall be fitted with the improvements
necessary to allow sampling of water from intermediate points for ozone
residual.
(n) All contactors shall
have provisions for cleaning, maintenance, and drainage. Each contactor
compartment shall also be equipped with an access hatchway.
(5) OZONE DESTRUCTION. Ozone
destruction shall meet the following requirements:
(a) A method or combination of methods for
destroying or recirculating the final off gas from the ozone contactors shall
be provided to meet safety and air quality standards. Acceptable methods
include:
1. Thermal destruction.
2. Catalytic destruction.
3. Thermal and catalytic
destruction.
4. Recycling to some
point in the treatment system in addition to the installation of destruction
equipment.
(b) A
detectable ozone residual may not carry over into the distribution
system.
(c) The maximum allowable
air ozone concentration in the destruction unit discharge is 0.1 ppm by
volume.
(d) At least 2 units shall
be provided which are each capable of handling the entire gas flow unless the
second unit is deemed unnecessary by the department.
(e) Exhaust blowers shall be provided in
order to draw ozone off-gas from the contactors into the destruct
unit.
(f) Catalysts shall be
protected from foam, moisture and other impurities that may harm the
catalyst.
(g) The catalyst and
heating elements shall be located where they can be easily reached for
maintenance.
Note: In order to reduce the risk of fires,
the use of units that operate at lower temperatures is encouraged, especially
where high purity oxygen is the feed gas.
(6) PIPING MATERIALS. Piping materials used
in ozone service shall meet the following requirements:
(a) Only low carbon 304L and 316L stainless
steel piping shall be used for ozone service. Alternative piping materials may
be approved by the department on a case-by-case basis.
(b) Gasket materials shall be Teflon or
Hypalon.
(c) Rubber components may
not be used in contact with ozone.
(7) JOINTS AND CONNECTIONS.
(a) Connections on stainless steel piping
used for ozone service are to be welded where possible.
(b) Connections with meters, valves, or other
equipment are to be made with flanged joints with ozone resistant gaskets, such
as Teflon or Hypalon. Screwed fittings and field-cut threaded connections may
not be used.
(c) A positive closing
plug or butterfly valve and a leak-proof backflow prevention check valve system
shall be provided in the piping between the generator and the contactor for
pressurized ozone generation systems.
(8) INSTRUMENTATION. Instrumentation shall
meet the following requirements:
(a) Pressure
gauges shall be provided at the discharge from the air compressor, at the inlet
to the refrigerator dryers, at the inlet and outlet of the desiccant dryers, at
the inlet to the ozone generators and contactors, and at the inlet to the ozone
destruction unit.
(b) Each
generator shall have a trip which shuts down the generator when the wattage
exceeds a preset level. It is recommended that electric power meters be
provided for measuring the electric power supplied to the ozone
generators.
(c) Dew point monitors
shall be provided for measuring the moisture of the feed gas from each
desiccant dryer. Where there is potential for moisture entering the ozone
generator from downstream of the unit or where moisture accumulation can occur
in the generator during shutdown, post-generator dew point monitors shall be
used.
(d) Air flow meters shall be
provided for measuring the air flow from the desiccant dryers to each of the
ozone generators, the air flow to each contactor, and the purge air flow to the
desiccant dryers.
(e) Temperature
gauges shall be provided for the inlet and outlet of the ozone cooling water
and the inlet and outlet of the ozone generator feed gas, and, if applicable,
for the inlet and outlet of the ozone power supply cooling water.
(f) Water flow meters shall be installed to
monitor the flow of cooling water to the ozone generators and, if applicable,
to the ozone power supply.
(g) At a
minimum, ozone monitors shall be installed and maintained to measure ozone
concentrations in both the feed-gas and the off-gas from the contactor and the
off-gas from the destruct unit. Monitors or a comparable testing method shall
also be provided for measuring ozone residuals in water in accordance with
subs. (4) and (5) (b). The number and location of ozone residual monitors shall
be such that the amount of time that the water is in contact with the ozone
residual can be determined.
(h)
Ambient air ozone monitors shall be installed in rooms where exposure to ozone
is possible.
(9) ALARMS.
The installation of alarm and shutdown systems shall meet the following
requirements:
(a) A dew point alarm and
shutdown shall shut down the generator in the event the system dew point
exceeds -60°C (-76°F).
(b)
An ozone generator cooling water flow alarm and shutdown shall shut down the
generator in the event that cooling water flows decrease to the point that
generator damage could occur.
(c)
An ozone power supply cooling water flow alarm and shutdown shall shut down the
power supply in the event that cooling water flow decreases to the point that
power supply damage could occur.
(d) An ozone generator cooling water
temperature alarm and shutdown shall shut down the generator if either the
inlet or outlet cooling water exceeds the designated preset
temperature.
(e) An ozone power
supply cooling water temperature alarm and shutdown shall shut down the power
supply if either the inlet or outlet cooling water exceeds the designated
preset temperature.
(f) An ozone
generator inlet feed-gas temperature alarm and shutdown shall shut down the
generator if the feed-gas temperature exceeds the designated preset
value.
(g) An ambient air ozone
concentration alarm and shutdown shall sound when the ozone level in the
building ambient air exceeds 0.1 ppm or a lower value chosen by the water
supplier. Ozone generator shutdown shall automatically occur when the building
ambient air ozone level exceeds 0.3 ppm or a lower value chosen by the water
supplier.
(h) An ozone destruct
temperature alarm shall sound when the temperature exceeds the designated
preset value.
(i) Audible alarms
and warning lights shall be installed and maintained to insure operators are
alerted to improper operating or hazardous conditions.
(10) SAFETY.
(a) The maximum allowable ozone concentration
in the air to which workers may be exposed may not exceed 0.1 ppm by
volume.
(b) Noise levels resulting
from the operation of the ozonation system shall be controlled to within
acceptable limits by special room construction and equipment
isolation.
(c) High voltage and
high frequency electrical equipment shall meet current electrical and fire
codes.
(d) An exhaust fan shall be
provided in the ozone generation and contactor rooms to remove ozone gas if a
leak occurs and shall meet all of the following requirements:
1. One complete air change per minute shall
be provided when the room is occupied.
2. The exhaust fan suction shall be located
near the floor with the point of discharge located to avoid contamination of
air inlets to other rooms and structures, to outside breathable air, or being
blocked by snow or other obstructions.
3. Air inlets shall be located near the
ceiling and controlled to prevent adverse temperature variations.
4. An exhaust fan switch shall be located
outside of the entrance to the room with a signal light indicating fan
operation when the fan can be controlled from more than one point.
(e) A portable purge air blower
that will remove residual ozone in the contactor prior to entry for repair or
maintenance shall be provided.
(f)
A sign shall be posted indicating "No smoking, oxygen in use" at all entrances
to the treatment plant. In addition, no flammable or combustible materials
shall be stored within the oxygen generator areas.