Current through August 26, 2024
Chlorine installations shall meet the following
requirements:
(1) CHLORINATION
equipment.
(a)
Type. The
following types of chemical feed equipment may be used to feed chlorine:
1. Solution-feed-gas-type
chlorinators.
2. Positive
displacement diaphragm type pumps.
3. Digitally controlled constant stroke
length positive displacement type pumps.
4. Peristaltic type pumps.
5. Tablet chlorinator type.
(b)
Capacity. The
chlorinator capacity shall be such that a free chlorine dose of at least 2 mg/L
can be attained when maximum flow rates coincide with anticipated maximum
chlorine demands. Liquid chemical feed equipment shall be designed to operate
in accordance with the requirements under s.
NR 811.39 (2)
(c). Solution-feed-gas-type chlorination
chemical feed equipment shall be designed to operate between 10 percent and 70
percent of the rotameter capacity. This may require that 2 rotameters be
provided, one for normal feed rates and one for emergency feed rates. For all
chemical feed systems, the emergency feeder setting shall be designed to
provide a minimum of 2 mg/L of chlorine.
(c)
Standby equipment. Where
chlorination is necessary for protection of the water supply, standby equipment
of sufficient capacity shall be available to replace the largest unit during
shut-downs. Spare parts shall be made available to replace parts subject to
scaling, wear, and breakage.
(d)
Automatic proportioning. Automatic proportioning chlorinators
shall be required where the rate of flow of the water is not reasonably
constant or where the rate of flow of the water is not manually
controlled.
(2) POINT OF
APPLICATION. Chlorine application points shall meet the following requirements:
(a) Chlorine shall be applied at a point
which will provide the maximum contact time. Provisions shall be made to
minimize short-circuiting.
(b) At
plants treating surface water, piping provisions shall be made for applying
chlorine to the raw water, settled or clarified water, filtered water, and the
plant effluent.
(c) At plants
treating groundwater, provision shall be made for applying chlorine to the raw
water, the clearwell inlet, and the discharge piping as applicable.
(d) At plants treating groundwater where CT
is required by the department, provision shall be made for applying chlorine to
the raw water, at the inlet to all CT reservoir detention basins, and the
high-lift pump discharge piping as required by the department.
(3) RESIDUAL TESTING EQUIPMENT.
Chlorine residual testing equipment shall meet the following requirements:
(a) Chlorine residual testing methodology
shall be as specified in s.
NR 809.563 (2), Table R. The equipment shall enable
measurement of residuals to the nearest 0.1 mg/1 in the range below 0.5 mg/1
and to the nearest 0.2 mg/1 between 0.5 mg/1 to 2.0 mg/1.
Note: It is recommended that all systems, at a
minimum, use an instrument using the DPD colorimetric method with a digital
readout and a self contained light source. Automatic chlorine residual pacers
and recorders are recommended where the chlorine demand varies appreciably over
a short period of time.
(b)
Water systems that rely on chlorination for inactivation of bacteria or other
microorganisms present in the source water shall have continuous chlorine
residual analyzers and other equipment that automatically shut down the
facility when the chlorine residuals required by the department are not met.
The department may approve less than continuous monitoring for municipal water
systems serving 3,300 or fewer people and other-than-municipal water systems on
a case-by-case basis provided that replacement measures or practices are
implemented to provide comparable public health protection.
(4) GAS CHLORINATOR PIPING. The
water supply piping shall be designed to prevent contamination of the treated
water supply by sources of impure or unknown quality. Pipes carrying elemental
liquid or dry gaseous chlorine under pressure shall be Schedule 80 seamless
steel tubing or other materials recommended by the Chlorine Institute. PVC pipe
may not be used. Chlorine solution piping and fittings shall be rubber, PVC,
polyethylene, or other materials recommended by the Chlorine
Institute.
(5) CHLORINE GAS
HOUSING. Chlorine gas feed and storage installations shall meet the following
requirements:
(a) Chlorine gas feed and
storage installations shall be separated from other operating areas by
gas-tight rooms or enclosures in order to prevent injury to personnel and
damage to equipment.
(b) Chlorine
gas rooms shall be provided with a safety glass inspection window installed in
an interior wall or exterior door to permit viewing of the interior of the room
and the equipment.
(c) Chlorine gas
rooms shall be provided with a minimum of one door having emergency or panic
hardware opening outward to the building exterior. Rooms may have additional
doors to the building exterior.
(d)
Chlorine gas rooms shall be heated to prevent freezing and insure proper
operation of the equipment.
(f)
Full and empty cylinders of chlorine gas shall be:
1. Isolated from operating areas.
2. Restrained in position to prevent movement
of the cylinders.
3. Stored in
rooms separate from ammonia storage.
4. Stored in areas not in direct sunlight or
exposed to excessive heat.
(g) Pressurized chlorine feed lines may not
carry chlorine gas beyond the chlorine room. Vacuum chlorine feed lines may
carry gas beyond the chlorine room if the chlorine lines are either schedule 40
polyethylene tubing or schedule 80 PVC pipe. Polyethylene tubing shall be
enclosed in a protective conduit running from the chlorine room to a point near
the ejector. The end of the conduit in the chlorine room shall be sealed.
Polyethylene tubing connections shall be made using tube adaptors especially
designed for this purpose. PVC pipe joints may be socket welded using PVC
cement or threaded using polytetrafluoroethylene pipe joint tape.
(h) Premanufactured chlorine cabinets may be
used for retrofit situations only. These cabinets shall have an observation
window, fan, air intake, and light as required in par. (b) and sub. (6) for
normal chlorine gas rooms.
Note: It is recommended that these cabinets
not be placed on the sunny side of the building.
(6) VENTILATION OF CHLORINE GAS ROOMS.
Ventilation of chlorine gas rooms shall meet the following requirements:
(a) One complete air change per minute shall
be provided when the room is occupied.
(b) The exhaust fan suction shall be within
12 inches of the floor as far as practical from the door and air inlet, with
the point of discharge located to avoid contamination of air inlets to other
rooms and structures, and to avoid being blocked by snow or other
obstructions.
(c) Air inlets shall
be located near the ceiling and controlled to prevent adverse temperature
variations.
(d) Louvers for the
chlorine room air intake and exhaust shall be corrosion resistant and shall
facilitate airtight closure.
(e)
The exhaust fan switch shall be located outside the entrance to the chlorine
room with a signal light indicating fan operation when the fan can be
controlled from more than one point. Outside switches shall be protected from
vandalism. As an alternative, the fan may be controlled by an automatic door
switch with manual shut-off.
Note: It is recommended that switches for fans
and lights be interlocked for simultaneous operation.
(f) Vent lines from feeders and storage shall
discharge to the outside atmosphere, above grade, in a downward direction, be
screened, and be located as required in par. (b). In addition, vent lines shall
conform with the manufacturer's installation recommendations.
(7) SAFETY EQUIPMENT. The
following safety equipment shall be provided when chlorine gas is used:
(a) Respiratory protection equipment, known
as gas masks, meeting the requirements of the National Institute for
Occupational Safety and Health (NIOSH) shall be available where chlorine gas is
handled, and shall be stored at a convenient heated location, but not inside
any room where chlorine is used or stored. The gas masks shall use compressed
air, have at least a 30-minute capacity, and be compatible with or exactly the
same as the gas masks used by the fire department responsible for the plant.
The gas masks shall be available at all installations where chlorine gas is
handled and shall be placed outside every room where chlorine gas is used or
stored. At installations utilizing 150-pound, or less, cylinders, an agreement
with the local fire department that has an approved type of gas mask for the
fire department to handle water system chlorine gas leaks may be approved by
the department. Instructions for using, testing and replacing gas mask parts
shall be posted. Other protective clothing shall be provided as
necessary.
(b) A bottle of
concentrated ammonium hydroxide, 56 percent ammonia solution, shall be
available for chlorine leak detection.
(c) If pressurized chlorine gas is present,
continuous chlorine leak detection equipment shall be installed and equipped
with both an audible alarm and a warning light. Automatic emergency chlorine
cylinder shutdown valves shall also be provided.
(d) If ton cylinders are used, leak repair
kits, approved by the Chlorine Institute, shall be available at the waterworks
or a nearby fire department.
(8) AMMONIA. Ammonia chemical feed
installations shall meet all of the following requirements:
(a)
Gaseous ammonia. Housing
and ventilation for ammoniation shall meet the requirements under subs. (5) and
(6) for chlorine, except that the exhaust fan inlet shall be within 12 inches
of the ceiling and the fresh air inlet shall be within 12 inches of the floor.
Ammonia storage and feed facilities shall be separate from chlorine facilities
because of the combustion hazard. A plastic bottle of hydrochloric acid shall
be available and used for leak detection.
(b)
Ammonium sulfate.
Ammonium sulfate chemical feed installation shall meet the chemical storage
requirements under s.
NR 811.40.
(c)
Aqua ammonia. Aqua
ammonia installation shall meet all of the following requirements:
1. An aqua ammonia chemical feed and storage
system shall be installed in its own dedicated room.
2. Bulk liquid storage tanks and day tanks
shall be vented to the outside of the building and discharge downward facing
with a 24-mesh corrosion resistant screen a minimum of 24 inches above grade.
The chemical tank vents shall be provided with inert liquid traps.
3. An incompatible connector or lockout
provisions shall be provided to prevent accidental addition of other chemical
to the bulk liquid storage tanks.
4. The bulk liquid storage tanks shall be
designed to avoid temperature increases that cause the ammonia vapor pressure
over the aqua ammonia to exceed atmospheric pressure. The provisions shall
include a means of external cooling or dilution and mixing of the contents with
water without opening the bulk liquid storage tank.
5. An exhaust fan shall be installed to
withdraw air from high points in the room and makeup air shall be allowed to
enter at a low point.
6. The aqua
ammonia feed pump, regulators, and lines shall be fitted with pressure relief
vents discharging outside the building away from any air intake and with water
purge lines leading back to the headspace of the bulk storage tanks.
7. The aqua ammonia shall be conveyed
directly from a day tank to the treated water stream injector without the use
of a carrier water stream unless the carrier stream is softened.
(9) CALCIUM
HYPOCHLORITE TABLET CHLORINATORS. Calcium hypochlorite tablet chlorinators
shall meet the following design requirements:
(a)
Calcium hypochlorite solution
formation. The calcium hypochlorite solution shall be produced by
dissolving tablets with a department approved feed water source using an
erosion chamber or an upward directed spray system. The department may approve
other methods or technology for producing calcium hypochlorite solution after
the submittal of data from a department-approved pilot program.
(b)
Tablets. The calcium
hypochlorite tablets used in the chlorinator shall be supplied by the
manufacturer of the tablet chlorinator equipment. The supplier of the calcium
hypochlorite tablets shall have obtained NSF/ANSI Standard 60 certification for
the tablets in accordance with s.
NR 810.09.
(c)
Tablet hoppers.
1. The tablet hopper shall be sized to
provide a minimum of 2 days of supply assuming average day consumption of the
tablets.
2. Load cells shall be
provided on the hopper so that the weight of the tablets consumed in a 24-hour
period can be determined. The design shall allow for collection of the data
necessary to determine the theoretical daily chlorine usage. The design shall
allow any solution to be drained out of the hopper before weighing the tablets.
The load cell equipment shall be capable of providing an alarm when the weight
of the tablets approaches a one day supply based upon an average day use. The
alarm signal shall be automatically annunciated by the water system controls. A
local alarm shall be sounded or signaled by an exterior red light at the pump
station if the operation of the pump station is not remotely
controlled.
3. The tablet hopper
shall include a screened air-vacuum relief device if the possibility of a
vacuum condition could develop during the operation of the tablet
chlorinator.
(d)
Solution tank.1. The open
area for any pipe penetration through the walls of the solution tank shall be
sealed sanitarily so that insects and foreign material cannot contaminate the
chlorine solution.
2. The on and
off operation of the process to produce chlorine solution from the tablets
shall be controlled by float switches or sensors located in the solution
tank.
3. Float switches or sensors
shall be installed and wired to provide automatic shut-off and operator alarms
for low and high solution level conditions. The shut-off and alarm signals
shall be automatically annunciated by the water system controls. A local alarm
shall be sounded or signaled by an exterior red light at the pump station if
the operation of the pump station is not remotely controlled.
4. The tank shall be capable of being drained
for maintenance purposes.
5. The
solution tank shall be sized to keep an adequate supply of calcium hypochlorite
in the tank at all times based upon the capabilities of the tablet chlorinator
to produce solution and the chemical feed pump withdrawal rates necessary to
achieve the required dosages.
(e)
Feed water piping
requirements.1. The flow rate and
pressure of the feed water piping shall be regulated so as to meet the design
flow requirements provided by the supplier of the equipment. A shut-off valve,
flow meter, and pressure gauge shall be installed on the feed water
piping.
2. Pre-treatment devices
shall be installed as necessary if the feed water does not meet the water
quality requirements designated for the tablet chlorinator. Any pre-treatment
device shall be compatible for use in a potable water system and shall not be
used unless approved by the department. A strainer-filter shall be installed on
the feed water piping, if necessary.
3. A check valve shall be installed on the
feed water piping upstream of any treatment equipment, control valve, or
solenoid valve.
4. A solenoid valve
shall be installed on the feed water piping to control the flow of water into
the tablet chlorinator. The operation of the solenoid valve shall be controlled
based upon float switches or sensors located in the solution tank.
5. Erosion type tablet chlorinators shall be
provided with a control valve capable of regulating the flow of water through
the erosion cell. The submittal for review to the department for an
erosion-type tablet chlorinator shall include the chlorine delivery rate versus
flow rate curve for the specified model.
(f)
Chemical feed pumps.
1. The chemical feed pump shall be wired to
operate in association with the well or service pump as required by s.
NR 811.39 (4).
2. A tablet chlorinator producing calcium
hypochlorite solution shall use a chemical feed pump installed in compliance
with s.
NR 811.39 (2), or a centrifugal pump.
3. Centrifugal pumps shall be sized to match
or exceed the maximum head condition at the point of injection.
4. Flow paced chemical feed pumps installed
in compliance with s.
NR 811.39 (2) or centrifugal pumps with variable speed
motors shall be incorporated into the design if the flow rate of the water
being treated may vary based upon automatic control of the well or service
pump. The requirements of s.
NR 811.39 (2)
(d) shall be met.
(g)
Chemical injection
location.1. Tablet chlorinator
chemical feed pumps shall discharge at locations and in a manner that complies
with the installation requirements of s.
NR 811.39 (2)
(f).
2. When a centrifugal pump will discharge at
a point not under continuous positive pressure, the outlet piping between the
centrifugal pump and the point of chemical injection shall be installed with a
vertical pipe loop that will extend to a height that is a minimum of 12 inches
above the top of the solution tank and the location of the chemical addition
pipe connection with the water system piping. A vacuum relief valve shall be
installed on the top of the pipe loop. As an alternative to the installation of
a vertical pipe loop, an electrically operated shut-off valve on the outlet
piping, wired to operate in series with the operation of the well or service
pump motor and the chemical feed pump, may be installed.
(h)
Centrifugal pump discharge
piping. The outlet piping of a centrifugal pump shall also be provided
with a check valve and a manually operated shut-off valve. These valves shall
be installed upstream of any pipe loop or electrically operated shut-off valve
as required by par. (g) 2.
(10) SODIUM CHLORITE FOR CHLORINE DIOXIDE
GENERATION. Proposals for the storage and use of sodium chlorite shall be
submitted to the department for approval. Department approval shall be obtained
prior to the preparation of final plans and specifications. Provision shall be
made for proper storage and handling of sodium chlorite to eliminate any danger
of fire or explosion.
(a)
Storage.1. Sodium chlorite
shall be stored by itself in a separate room and preferably shall be stored in
an outside building detached from the water treatment facility. Sodium chlorite
shall be stored away from organic materials with which it could react
violently.
2. Storage structures
shall be constructed of noncombustible materials.
3. If the storage structure is located in an
area where a fire may occur, water shall be available to keep the sodium
chlorite area cool enough to prevent heat induced explosive decomposition of
the sodium chlorite.
(b)
Handling.1. Care shall be
taken to prevent spillage of sodium chlorite.
2. An emergency plan of operation shall be
available for the clean up of any spillage.
3. Storage drums containing sodium chlorite
shall be thoroughly flushed and the waste shall be discharged to an acceptable
location prior to recycling or disposal.
(c)
Feeders.
1. Chemical feed pumps shall meet the
requirements of s.
NR 811.39 (2).
2. Tubing for conveying sodium chlorite or
chlorine dioxide solutions shall be Type 1 PVC, polyethylene or materials
recommended by the manufacturer.
3.
Chemical feeders may be installed in chlorine gas rooms if sufficient space is
provided or in separate rooms meeting the requirements of subs. (5) and
(6).
4. Feed lines shall be
installed in a manner to prevent formation of gas pockets and shall terminate
at a point of positive pressure.
5.
Check valves shall be provided to prevent the backflow of chlorine into the
sodium chlorite line.