Clarification plants prior to filtration shall meet all of
the following requirements unless other design criteria are justified through
pilot testing under s.
NR 811.44 or other specific information provided to the
department supports the proposed design, as determined by the
department:
(1) Provide a minimum of 2
units each for rapid mix, flocculation and sedimentation.
(2) Permit operation of the units either in
series or parallel.
(3) Be
constructed to permit units to be taken out of service without disrupting
operation with drains or pumps sized to allow dewatering in a reasonable period
of time.
(4) Provide multiple-stage
treatment facilities if required by the department.
(5) Be started manually following
shutdown.
(6) Minimize hydraulic
head losses between units to allow future changes in processes without the need
for repumping.
(7) Meet the
following specific requirements:
(a)
Presedimentation. Waters containing high turbidity or having
unusual treatment requirements may require pretreatment, usually sedimentation
or detention either with or without the addition of coagulation chemicals.
1. 'Basin design.' Presedimentation basins
shall have the following:
a. Hopper bottoms or
be equipped with continuous mechanical sludge removal apparatus, and provide
arrangements for dewatering.
b.
Cover or superstructure.
2. 'Inlet.' Incoming water shall be dispersed
across the full width of the line of travel as quickly as possible. Short
circuiting shall be prevented.
3.
'Bypass.' Provisions for bypassing presedimentation basins shall be
included.
4. 'Detention time.'
Three hours detention is the minimum period required for presedimentation.
Greater detention may be required in individual cases of chemical
pretreatment.
5. 'Raw water
samples.' A means for collecting raw water samples prior to any chemical
addition shall be provided.
(b)
Rapid mix. Mixing shall
mean the rapid dispersion of chemicals throughout the water to be treated,
usually by violent agitation. For surface water plants using direct or
conventional filtration, the use of a primary coagulant is required at all
times.
1. 'Mixing.' The detention period shall
not be more than 30 seconds with mixing equipment capable of imparting a
minimum velocity gradient (G) of at least 750 feet per second per foot or as
determined through jar testing. The appropriate G value and detention time
shall be determined through jar testing.
2. 'Equipment.' Basins shall be equipped with
mechanical mixing devices unless other methods, such as baffling, or injection
of chemicals at a point of high velocity, are approved by the department after
determining that the other requirements of this chapter will be met. Variable
speed drive equipment is recommended.
3. 'Location.' The rapid mix and flocculation
basin shall be as close together as possible.
(c)
Flocculation - slow
mixing. Flocculation installations shall meet all of the following
requirements:
1. 'Basin design.' Inlet and
outlet design shall prevent short circuiting and destruction of floc. Series
compartments shall be provided to minimize short-circuiting and to provide
decreasing mixing energy with time. Basins shall be designed so that individual
basins may be isolated without disrupting plant operation. A drain or pumps or
both shall be provided to allow dewatering and sludge removal.
2. 'Detention.' Flow-through velocity may be
not less than 0.5 nor greater than 1.5 feet per minute with a detention time
for floc formation of at least 30 minutes. Tapered energy with diminishing
velocity gradient shall be considered in the design of the flocculation
basin.
3. 'Equipment.' Agitators
shall be driven by variable speed drives or other means which vary the
peripheral speed of paddles in the range of 0.5 to 3.0 feet per second and the
tip speed of vertical shaft impellors in the range of 6 to 10 feet per second.
Uniform mixing shall be provided to prevent settling in the flocculation
basin.
4. 'Piping.' Flocculation
and sedimentation basins shall be as close together as possible. The velocity
of flocculated water through pipes or conduits to settling basins may not be
less than 0.5 nor greater than 1.5 feet per second. Allowances shall be made to
minimize turbulence at bends and changes in direction.
5. 'Other designs.' Baffling may be used to
provide flocculation only after approval by the department. The design shall be
such that the velocities and flows in this section shall be
maintained.
6. 'Superstructure.' A
superstructure shall be provided over the flocculation basins.
(d)
Sedimentation. Sedimentation shall follow flocculation. The
detention time for effective clarification is dependent upon factors related to
basin design as well as the nature of the raw water, such as turbidity, color
and colloidal matter, and taste and odor causing compounds.
1. 'Detention time.' Plants with conventional
sedimentation shall provide a minimum of 4 hours of settling time. This may be
reduced to 2 hours for lime-soda softening facilities treating only
groundwater. Also, reduced sedimentation time may be approved when equivalent
effective settling is demonstrated or when overflow rate is not more than 0.5
gallons per minute per square foot.
2. 'Inlet devices.' Inlets shall be designed
to distribute the water equally and at uniform velocities. Open ports,
submerged ports, and similar entrance arrangements are required. A baffle shall
be constructed across the basin, close to the inlet end, and project several
feet below the water surface to dissipate inlet velocities and provide uniform
flows across the basin.
3. 'Outlet
devices.' Outlet devices shall be designed to maintain velocities suitable for
settling in the basin and to minimize short circuiting. The use of submerged
orifices is recommended in order to provide volume above the orifices for
storage when there are fluctuations in flow.
4. 'Weir overflow rate.' The rate of flow
over the outlet weir may not exceed 20,000 gallons per day per foot of weir
length. If submerged ports or orifices are used as an alternate for overflow
weirs, they may not be lower than 3 feet below the flow line with flow rates
equivalent to weir loadings. The entrance velocity through the submerged
orifices shall not exceed 0.5 feet per second.
5. 'Drainage.' Basins shall be provided with
a means for dewatering. Basin bottoms shall slope toward the drain not less
than one foot in 12 feet where mechanical sludge collection is not
provided.
6. 'Covers.' Covers or
superstructures are required at all plants. Where covers are used, access
hatches shall be provided as well as drop light connections so that observation
of the floc can take place at the inlet, midpoint and outlet of the
basin.
7. 'Velocity.' The velocity
through settling basins may not exceed 0.5 feet per minute. The basins shall be
designed to minimize short circuiting. Fixed or adjustable baffles shall be
provided as necessary to achieve the maximum potential for
clarification.
8. 'Overflow.' An
overflow weir or pipe shall be installed, which will establish the maximum
water level desired on top of the filters. It shall discharge by gravity with a
downturned pipe elbow a minimum of one foot above a concrete splash pad and
shall be covered with 4-mesh corrosion resistant screen at a location where the
discharge is visible and where the water can be appropriately
drained.
9. 'Safety.' Guard rails
shall be installed around openings which may be hazardous to maintenance
personnel. Permanent holders or handholds shall be provided on the inside walls
of basins above the water level.
10. 'Sludge collection.' Mechanical sludge
collection equipment may be provided.
11. 'Sludge removal.' Facilities for disposal
of sludge are required by the department. Sludge removal design shall provide:
a. Sludge pipes not less than 3 inches in
diameter and so arranged as to facilitate cleaning.
b. Entrance to sludge withdrawal piping to
prevent clogging.
c. Valves located
outside the tank for accessibility.
d. Provisions for the operator to observe and
sample sludge being withdrawn from the unit.
12. 'Sludge disposal.' Sections
NR 811.858 and 811.861
contain additional specific requirements for sludge disposal. Flushing lines or
hydrants shall be provided to backflush sludge lines and basins or for other
purposes. Protection shall be provided for all potable water lines used if
potable water could become contaminated by nonpotable water.
(e)
Solids contact
unit. Units designed for combined softening and clarification, if
water characteristics, especially temperature, do not fluctuate rapidly and
flow rates are uniform and operation is continuous, may be used if specifically
approved by the department. Units shall be designed for the maximum uniform
rate and be adjustable to changes in flow, which are less than the design rate
and for changes in water characteristics. A minimum of 2 units are required
unless the department waives this requirement. For plants with multiple units,
the rated capacity of the plant shall be available with one unit out of
service.
1. 'Installation of equipment.'
Supervision by a representative of the manufacturer shall be provided whenever
mechanical equipment is installed and at the time of initial
operation.
2. 'Operating
equipment.' A complete outfit of tools and accessories shall be provided.
Laboratory equipment to control the treatment process shall be provided at all
waterworks. In addition, sampling taps with adequate piping located to permit
the collection of samples of water from critical portions of the units shall be
provided.
3. 'Chemical feed.'
Chemicals shall be applied at points and by means as to ensure satisfactory
mixing of the chemicals with the water.
4. 'Mixing.' Mixing devices employed shall be
constructed to provide adequate mixing of the raw water with previously formed
sludge particles and to prevent deposition of solids in the mixing zone. A
rapid mix device or chamber ahead of the solids contact unit may be required by
the department.
5. 'Flocculation.'
Flocculation equipment shall be adjustable by speed, or pitch or both, provide
for coagulation to occur in a separate chamber or baffled zone within the unit,
and provide a flocculation and mixing period of not less than 30
minutes.
6. 'Sludge concentrators.'
Sludge concentrators shall provide either internal or external concentrators in
order to obtain a concentrated sludge with a minimum of wastewater.
7. 'Sludge removal.' Sludge removal design
shall provide all of the following:
a. Sludge
pipes not less than 3 inches in diameter, arranged to facilitate
cleaning.
b. Entrance to sludge
withdrawal piping to prevent clogging.
c. Valves located outside the tank for
accessibility.
d. Facilities for an
operator to observe or sample sludge being withdrawn from the unit.
8. 'Cross-connections.' Sludge
blow-off outlets and drains shall terminate and discharge at places approved by
the department. Cross-connection control shall be included for all potable
water lines such as those used to backflush sludge lines or flush basins if
potable water could become contaminated by nonpotable water.
9. 'Detention period.' The detention time
shall be established on the basis of the raw water characteristics and local
conditions that affect the operation of the unit. Based on design flow rates,
the minimum detention time shall be 2 to 4 hours for suspended solids contact
clarifiers and softeners treating surface waters, and one to 2 hours for the
suspended solids contact softeners treating only groundwater.
10. 'Suspended slurry concentrate.' Softening
units shall be designed so that continuous slurry concentrates of 1% or more,
by weight, can be effectively maintained.
11. 'Water losses.'
a. Units shall be provided with suitable
controls for sludge withdrawal.
b.
Total water loss may not exceed 5% for clarifiers or 3% for softening
units.
c. Solids concentration of
sludge discharged to waste shall be at least 3% by weight for clarifiers and 5%
by weight for softeners.
12. 'Weir or orifices.' The units shall be
equipped with either overflow weirs or orifices. Weirs shall be adjustable, at
least equivalent in length to the perimeter of the tank, and constructed so
that surface water does not travel over 10 feet horizontally to the collection
trough.
13. 'Weir or orifice
loading.' Weir loading may not exceed 20 gallons per minute per foot of weir
length for units used for softeners, or 10 gallons per minute per foot of weir
length for units used for clarifiers. Where orifices are used, the loading rate
per foot shall be equivalent to weir loadings. Orifices or weirs shall produce
uniform rising rates over the entire area of the tank.
14. 'Upflow rates.' Unless supporting data is
submitted to the department and the department grants an exception, the
following rates may not be exceeded:
a. 1.75
gallons per minute per square foot of area at the slurry separation line if
units are used for softeners.
b.
1.0 gallon per minute per square foot of area at the sludge separation line if
units are used for clarifiers.
(f)
Tube or plate settlers.
Proposals for settler unit clarification shall include pilot plant or a full
scale demonstration or both satisfactory to the department prior to the
preparation of final plans and specifications for approval. Settler units
consisting of variously shaped tubes or plates which are installed in multiple
layers and at an angle to the flow, may be used for sedimentation, following
flocculation. Tube or plate settler installations shall meet the following:
1. 'Inlet and outlet considerations.' Design
the inlets and outlets to maintain velocities suitable for settling in the
basin and to minimize short-circuiting.
2. 'Drainage.' Drain piping from the settler
units shall be sized to facilitate a quick flush of the settler units and to
prevent flooding other portions of the plant.
3. 'Protection from freezing.' Units shall be
located within a plant or within a covered basin.
4. 'Application rate for tubes.' A maximum
application rate of 2 gallons per minute per square foot of cross-sectional
area, unless higher rates are successfully shown through pilot plant or
in-plant demonstration studies and are approved by the department.
5. 'Application rate for plates.' A maximum
plate loading rate of 0.5 gallons per minute per square foot, based on 80
percent of the projected horizontal plate area.
6. 'Flushing lines.' Flushing lines shall be
provided to facilitate maintenance and shall be properly protected against
backflow or back siphonage.
7.
'Placement.' Modules shall be placed in zones of stable hydraulic conditions
and in areas nearest effluent launders for basins not completely covered by the
modules.
8. 'Inlets and outlets.'
Inlets and outlets shall conform with par. (d) 2. and 3.